Agani Velocity at a glance
- Possession (RERA)Dec 2030Karnataka RERA
- Construction100% builtPromoter’s RERA update · as on 30 Jun 2026
- Homes booked31 of 60 (52%)RERA update · as on 30 Jun 2026
- RERA complaints (project)None listedKarnataka RERA · as on 21 Oct 2026
- Approvals filed4 of 9 on RERAKarnataka RERA uploads · 21 Oct 2026
- Nearest metroHuskur Road · 1.97 kmstraight line · OpenStreetMap, 5 Oct 2026
- Airport driveapprox. 167 min at peak41.28 km straight line · estimate
- Nearest lakeUnnamed lake · 449 mFrom the RERA map point · OpenStreetMap, 5 Oct 2026
Project summary
Agani Velocity is a residential project by Agani Projects Private Limited in Margandanahalli, Bengaluru with 60 homes, registered with Karnataka RERA. The completion date on RERA is 31 Dec 2030.
Facts collected on 21 Oct 2026 from public records — each linked to its source. Free for buyers. If you book through us, the builder pays us a commission.
Agani Velocity buyers’ group: join to ask for a group price
No one has joined yet. Be one of the first 10 buyers in this group — the founding members.
Join free. When enough buyers have joined, our agent partner asks Agani Projects Private Limited for a group price — for example a lower price, an easier payment plan or waived charges. Nothing is promised: you see what the builder offers and book directly with the builder if you want to. Free for buyers. If you book through us, the builder pays us a commission.
- Gathering buyers
- Talking to the builder
- Group offer
- Group site visit
- Booking
0 buyers have joined · 0 committed
Committed buyers have confirmed their budget, home type and timeline with us on a call; builders negotiate with them. Joining is free and never obliges you to buy.
Join the Agani Velocity buyers’ groupHow group buying works
See it for yourself
Visit the site with our team, or get a call to clear your questions. Free, no obligation.
Key facts: home types, towers, land and possession
- Home types
- 2 BHK, 2.5 BHK, 3 BHK
- Carpet area
- 689 – 1,087 sq ft
- Towers
- 1
- Floors
- 3
- Total homes
- 60
- Land
- 0.75 acres
- Possession (RERA)
- Dec 2030
- Built (RERA update)
- 100%
Agani Velocity RERA number and registration details
- RERA number
- PRM/KA/RERA/1251/308/PR/150324/006705
- Registered on
- 15 Mar 2024
- Promised completion
- 31 Dec 2030
- Extended to
- No extension recorded
- RERA status
- New launch
- Homes booked
- 31 of 60 as on
- Price
- Not found in public records yet: price
- Project type
- Residential
Towers and blocks (RERA filing)
| Tower | Floors | Basements | Homes |
|---|---|---|---|
| velocity | 3 | 1 | 60 |
A dash (—) means the filing did not state that value.
Summary in plain English
Agani Velocity is a 60-home residential project by Agani Projects Private Limited in Margandanahalli, Anekal. The single tower has homes across 2 BHK, 2.5 BHK, and 3 BHK types with a completion date of 31 December 2030.
Written by AI from the RERA record above on 21 Oct 2026. Every number in it was checked against that record; if anything differs, the record wins.
Open space, home loans, escrow and other details
- Open space
- 57.7% of land
- Water and power
- Water source filed with RERA: BoreWell
- Home loans: approved banks
- Not found in public records yet: bank approvals
- Payment plans
- Not found in public records yet: payment plans
- Maintenance
- Not found in public records yet: maintenance
- Car parking
- Not found in public records yet: car parking charge
- Escrow bank (RERA)
- Axis Bank, HSR
- Building plan (RERA)
- Local Planing Authority · No. 20/23-24 · dated 18 Nov 2023
- Project cost declared to RERA
- ₹22.7 Cr
Open area as a share of the land, from the areas filed with RERA (includes driveways and landscaped areas).
Amenities
- Electricity
- CCTV Surveillance
- Swimming Pool
- Power Backup
Amenities and internal works as filed by the promoter with Karnataka RERA; we have not visited the site.
Agani Velocity location and address
- Address
- SURVEY No.19/1 AND 19/2 , MARGANDANAHALLI VILLAGE , Anekal , Bengaluru Urban, Karnataka - 562125
- Village (RERA)
- Margandanahalli
- Locality
- Electronic City Phase 1Also known as Electronic City, Electronics City, E-City
- PIN code
- 562125
- City
- Bengaluru
- State
- Karnataka
- Coordinates
- 12.83189, 77.66082
Distances to landmarks
Not found in public records yet: landmarksAbout Electronic City Phase 1
Not found in public records yet: locality factsCommute times to tech parks and the airport
| To | Straight line | Peak-hour drive (estimate) |
|---|---|---|
| Electronic City Phase 1Map point on OpenStreetMap (opens in a new tab) | 2.03 km | approx. 8 min |
| Outer Ring Road tech corridor (RMZ Ecospace, Bellandur)Map point on OpenStreetMap (opens in a new tab) | 10.45 km | approx. 42 min |
| KSR Bengaluru City railway station (Majestic)Map point on OpenStreetMap (opens in a new tab) | 19.04 km | approx. 77 min |
| ITPL, Whitefield (main gate)Map point on OpenStreetMap (opens in a new tab) | 19.22 km | approx. 78 min |
| Manyata Tech ParkMap point on OpenStreetMap (opens in a new tab) | 24.45 km | approx. 99 min |
| Kempegowda International AirportMap point on OpenStreetMap (opens in a new tab) | 41.28 km | approx. 167 min |
How we calculate
Straight line: from the project’s map point on RERA to the destination’s point on OpenStreetMap.
Peak-hour drive is a rough estimate, not a route: straight line × 1.35 for the road network, at 20 km/h. Real times vary a lot with the route and the hour.
Sources:Source (openstreetmap.org) (opens in a new tab)How we calculate this
Schools and hospitals nearby
Within 2 km
- 12Schools and colleges5 schools, 6 colleges, 1 kindergartens
- 9Hospitals and clinics3 hospitals, 6 clinics
Nearest schools and colleges
- Symbiosis Institute of Business Mangament · 1.3 km
- International Institute of Information Technology Bangalore · 1.4 km
- EuroSchool Electronic City · 1.46 km
Nearest hospitals and clinics
- Dietician Priyanka Khandelwal · 0.42 km
- Shree Vinayaka Multispeciality Centre · 0.55 km
- Wipro First Aid Clinic · 0.7 km
Places as mapped on OpenStreetMap (amenity=school, college, kindergarten, university; hospital, clinic), counted within 2 km in a straight line of the RERA map point. Volunteers map these, so some places may be missing or closed. Places data © OpenStreetMap contributors, extract of 5 Oct 2026.
Nearest metro station and railway
- Huskur Road (ಹುಸ್ಕೂರು ರಸ್ತೆ)Open now — nearest operating metro station1.97 km
- Heelalige (ಹೀಲಲಿಗೆ ರೈಲು ನಿಲ್ದಾಣ)Nearest railway station5.83 km
Straight-line distances from the RERA map point to the station points mapped on OpenStreetMap; status (open or under construction) as tagged there. Places data © OpenStreetMap contributors, extract of 5 Oct 2026.
Lake and lake-buffer check
The nearest mapped lake is Unnamed lake (mapped on OpenStreetMap), 449 m from the project’s RERA map point.
The site boundary is not published as a shape, so its nearest edge can be closer than this point. Whether any building sits inside a lake buffer can only be checked on the approved plan.
- Unnamed lake (mapped on OpenStreetMap) on OpenStreetMap (opens in a new tab) 449 m
- Maragondanahalli Lake on OpenStreetMap (opens in a new tab) 450 m
- Unnamed lake (mapped on OpenStreetMap) on OpenStreetMap (opens in a new tab) 455 m
The buffer rule
Bengaluru’s lake buffer rule has changed over time: the National Green Tribunal ordered a 75 m buffer in May 2016; the Supreme Court set that order aside on 5 March 2019, leaving the 30 m buffer of the Revised Master Plan 2015. Check the current rule and the approved plan before relying on either number.
- LiveLaw: SC sets aside NGT order enlarging buffer zones (2019) (livelaw.in) (opens in a new tab)
- Citizen Matters: Shrinking lake buffers (citizenmatters.in) (opens in a new tab)
Shortest distance from the RERA map point to the mapped water edge (OpenStreetMap water polygons tagged lake or reservoir, or named lake/kere/tank). Mapped shorelines can differ from the revenue-record boundary of a lake. Places data © OpenStreetMap contributors, extract of 5 Oct 2026.
Sources:Source (openstreetmap.org) (opens in a new tab)Source (livelaw.in) (opens in a new tab)Source (citizenmatters.in) (opens in a new tab)How we calculate this
Satellite time-lapse of the site
Satellite photos load when you scroll to them.
Photos from Esri World Imagery Wayback, centred on the project’s map point; dates are the capture dates in Esri’s metadata. Loaded from Esri when you scroll here.
Sources:Source (livingatlas.arcgis.com) (opens in a new tab)
Agani Velocity floor plans, brochure and elevations
Documents the builder uploaded to Karnataka RERA, shown as filed. Tap a page to see it full size; the full PDF opens on the RERA website.
Floor plans6 files

Approved Layout PlanFull PDF on RERA 
Approved Building/Plotting PlanFull PDF on RERA 
Existing Layout PlanFull PDF on RERA 
Floor PlanFiled 5 Mar 2024 · Full PDF on RERA 
Grond And Tipical floor PlanFiled 5 Mar 2024 · Full PDF on RERA 
GroUnd And Tipical floor PlanFiled 29 Jan 2024 · Full PDF on RERA
| Home type | Carpet area | Homes |
|---|---|---|
| 2 BHK | 689 – 753 sq ft | 16 |
| 2.5 BHK | 775 – 840 sq ft | 24 |
| 3 BHK | 926 – 1,087 sq ft | 20 |
Home types, counts and carpet areas as filed with Karnataka RERA (carpet area, not super built-up).
We have not collected floor-plan drawings; the builder’s sales team can share them.
Agani Velocity possession date and construction status
Promoter’s quarterly update to RERA for Q1 2026-27, submitted 2026-07-09.
Units sold and unsold, from RERA (Q1 2026-27)
| Type | Homes | Booked | Available |
|---|---|---|---|
| 2 BHK | 16 | 6 | 10 |
| 2.5 BHK | 24 | 16 | 8 |
| 3 BHK | 20 | 9 | 11 |
As reported by the promoter in the quarterly update to RERA, not verified by us.
Timeline
- 1 Dec 2023Project start date given to RERA
- 15 Mar 2024Registered with Karnataka RERA
- 31 Dec 2030Completion date given at registration
Approvals and documents checklist
| Approval | Authority | Source |
|---|---|---|
| Building plan | Local Planing Authority · No. 20/23-24 · dated 2023-11-18 | Source (rera.karnataka.gov.in) (opens in a new tab) |
| Land conversion | DEPUTY COMISSIONER · No. 28/2022-23 · dated 2023-05-18 | Source (rera.karnataka.gov.in) (opens in a new tab) |
| Commencement Certificate | scan uploaded to RERA | Source (rera.karnataka.gov.in) (opens in a new tab) |
| Electricity Permission Letter | scan uploaded to RERA | Source (rera.karnataka.gov.in) (opens in a new tab) |
| Approved Layout Plan | scan uploaded to RERA | Source (rera.karnataka.gov.in) (opens in a new tab) |
| Approved Building/Plotting Plan | scan uploaded to RERA | Source (rera.karnataka.gov.in) (opens in a new tab) |
| Approved Section Of Building/Infrastructure Plan of Plotting | scan uploaded to RERA | Source (rera.karnataka.gov.in) (opens in a new tab) |
| Conversion Certificate under section 95 of the KLR Act 1964 | scan uploaded to RERA | Source (rera.karnataka.gov.in) (opens in a new tab) |
| ESCOM/Electricity | scan uploaded to RERA | Source (rera.karnataka.gov.in) (opens in a new tab) |
| KSPCB | scan uploaded to RERA | Source (rera.karnataka.gov.in) (opens in a new tab) |
Documents uploaded to RERA
- Building or layout plan · Approved drawings from the planning authorityFiled on RERA ✓ — Local Planing Authority · No. 20/23-24 · dated 18 Nov 2023
- Commencement certificate · Permission to start buildingFiled on RERA ✓ — scanned copy uploaded; number and date not read yet
- Environment clearance · SEIAA KarnatakaNot on RERA yet
- Fire NOC · Karnataka Fire and Emergency ServicesNot on RERA yet
- Pollution board consent · KSPCBFiled on RERA ✓ — scanned copy uploaded; number and date not read yet
- Water and sewerage · BWSSBNot on RERA yet
- Electricity · BESCOMFiled on RERA ✓ — scanned copy uploaded; number and date not read yet
- Height clearance · Airports Authority of IndiaNot on RERA yet
- Occupancy certificate (OC) · Issued only when the building is finishedNot on RERA yet — expected at completion
From the documents the promoter uploaded to Karnataka RERA, collected 21 Oct 2026. “Filed” means a document is on RERA — we have not checked its contents or validity. Not every approval applies to every project (for example, smaller projects may not need an environment clearance). The project page on RERA lists each upload.
Agani Velocity RERA complaints
No complaints listed on Karnataka RERA for this registration as on Source (rera.karnataka.gov.in) (opens in a new tab)
Court and consumer cases
We list case numbers, courts and outcomes only — never names of private individuals.
About Agani Projects Private Limited
- Promoter type
- Company
- Projects on this site
- 1
- RERA complaints against promoter
- 0
- Company number (CIN)
- U70100KA2013PTC072459
From Karnataka RERA, as collected so far (21 Oct 2026). Complaints are those RERA lists against this promoter across all its projects.
Agani Projects Private Limited’s RERA recordAgani Projects Private Limited delivery record
- 1Projects in Bengaluru on RERA1 approved registration under Agani Projects Private Limited in Bengaluru Urban and Rural. Source (rera.karnataka.gov.in) (opens in a new tab)
- 60Homes registeredAs stated in each registrations.
- 0RERA complaintsas on Source (rera.karnataka.gov.in) (opens in a new tab)
- 0Complaints per 1,000 homes0 complaints ÷ 60 homes in its 1 registration on Karnataka RERA in Bengaluru.
Sources:Source (rera.karnataka.gov.in) (opens in a new tab)How we calculate this
What’s changed since Nov 2023
- 9 Jul 2026Quarterly update filed for Q1 2026-27: 100% built, 31 of 60 homes booked Source (rera.karnataka.gov.in) (opens in a new tab)
- 11 Apr 2026Quarterly update filed for Q4 2025-26: 98% built, 30 of 60 homes booked Source (rera.karnataka.gov.in) (opens in a new tab)
- 13 Jan 2026Quarterly update filed for Q3 2025-26: 97% built, 26 of 60 homes booked Source (rera.karnataka.gov.in) (opens in a new tab)
- 15 Mar 2024Registered with Karnataka RERA (PRM/KA/RERA/1251/308/PR/150324/006705); completion date 31 Dec 2030 Source (rera.karnataka.gov.in) (opens in a new tab)
- 1 Dec 2023Project start date in the RERA record Source (rera.karnataka.gov.in) (opens in a new tab)
- 18 Nov 2023Building plan approved by Local Planing Authority (No. 20/23-24) Source (rera.karnataka.gov.in) (opens in a new tab)
Newest first. No extension of the completion date is recorded on RERA. When the RERA crawl sees a new filing, complaint or extension, it is added here with its date.
Home loan EMI calculator
- Monthly EMI
- —
- Down payment
- —
- Loan amount
- —
- Total interest
- —
A calculation only, from the numbers you enter — not a loan offer.
All-in cost: GST, registration and other charges
The calculator loads when you scroll to it.
Assumptions
- Base price: the builder’s price is not published in a form we could collect — enter it from the cost sheet.
- GST 5% on the base price and charges — the usual rate for an under-construction home that is not “affordable housing” (1%).
- Stamp duty about 5.6% and registration 2% — the Karnataka rule (registration was raised from 1% to 2% on 31 Aug 2025). Calculated on the agreement value.
- Car parking, other charges and the maintenance deposit are not in the public record we collect; enter them from the builder’s cost sheet.
- Loan on the agreement value (banks usually lend up to 75–90%); EMI is the standard reducing-balance formula. Example rate only — use your bank’s quote.
Agani Velocity FAQs
What is the completion date for Agani Velocity?
The RERA record shows the completion date as 31 December 2030.
How many homes are in Agani Velocity?
Agani Velocity has 60 homes across one tower.
What home types are available in Agani Velocity?
The project offers 16 homes of 2 BHK (689 to 753 carpet sq ft), 24 homes of 2.5 BHK (775 to 840 carpet sq ft), and 20 homes of 3 BHK (926 to 1,087 carpet sq ft).
What is the RERA registration number for Agani Velocity?
The RERA registration number is PRM/KA/RERA/1251/308/PR/150324/006705, registered on 15 March 2024.
Where is Agani Velocity located?
Agani Velocity is located in Margandanahalli, Anekal taluk, Bengaluru Urban district, PIN code 562125.
What is the construction progress of Agani Velocity?
As of Q1 2026-27 (quarter ended 30 June 2026), the project is 100% complete with 31 of 60 homes booked.
Are there any RERA complaints against Agani Velocity?
There are no RERA complaints filed against this project.
Are there any RERA complaints against Agani Projects Private Limited?
There are no RERA complaints against the builder across any of their projects in our record.
How many projects does Agani Projects Private Limited have on RERA record in Bengaluru?
Agani Projects Private Limited has 1 project in our Bengaluru RERA records.
What is the tower and floor configuration of Agani Velocity?
Agani Velocity has 1 tower with a maximum of 3 floors.
Written by AI from the RERA record above on 21 Oct 2026. Answers use only that record; check them against the source before you decide.
Questions about Agani Velocity
No questions published yet. Ask the first one: you get an instant answer from this page’s public record, and our team follows up on anything the record does not show.
Bought a home from Agani Projects Private Limited? Review the builder.
Reviews of Agani Projects Private Limited by verified buyers
No verified reviews of Agani Projects Private Limited yet. If you bought a home from them, your review helps other buyers.
How reviews work: only buyers and owners can review; we confirm each purchase by phone before publishing, publish positive and negative reviews alike, never accept payment for reviews, and the builder may reply.
Similar projects within 5 km
| Project | Distance | Homes | Possession (RERA) | Built | Complaints | Price |
|---|---|---|---|---|---|---|
| Splendid EvoraSplendid Properties | 0.7 km | 114 | Dec 2030 | 3% | 0 | Not collected |
| Alchemy ElixirAratt City Towers LLP | 0.9 km | 349 | Sep 2026 | — | 1 | Not collected |
| Ayatana Residences E-CityAratt One World Private Limited | 1 km | 166 | Jun 2029 | 50% | 0 | Not collected |
| Habulus Oasis GroveHabulus Homes Private Limited | 1 km | 296 | Mar 2031 | 20% | 0 | Not collected |
| Sreenidhi E-CitySreenidhi Developers | 1.1 km | 44 | Dec 2025 | 100% | 0 | Not collected |
| Srikara Urban ParkSrikara Structures | 1.1 km | 126 | Mar 2027extended | 91% | 0 | Not collected |
Projects of the same kind within 5 km in a straight line of this project’s RERA map point, nearest first. % built is the promoter’s latest quarterly figure on RERA (shown for single-registration projects); prices are from the builder’s own website where we found one.
Sources and last checked dates
Collected on 21 Oct 2026 by AI research agents reading public pages. Facts are written in our own words. Not found yet: price; court cases; landmarks; specifications; news.
How to check on RERA: On rera.karnataka.gov.in/viewAllProjects, type the registration number in 'Registration No', press Search, then click the 'View Project Details' icon. Complaints open from the 'Complaints / Litigation' icon in the same row. Registration number: PRM/KA/RERA/1251/308/PR/150324/006705.
- RERA record last checked: 21 Oct 2026
- Last change in the record (registration, quarterly filing or complaint): 9 Jul 2026
How this page is made: software builds it from public records (Karnataka RERA filings, OpenStreetMap, the builder’s own website). AI is used only to read filings into fields and to write the plain-English summary and FAQ answers, which are checked against the record. Facts are checked automatically against the RERA filing. Methodology · How we earn · Report an error
More new projects in Electronic City Phase 1
Hebbagodi, Electronic City Phase 1Under constructionRERA registeredBuyers’ group openSplendid Evora
by Splendid Properties
Price: Price on requestGet brochure & price →
- 3 BHK, 4 BHK
- 995 – 1,694 sq ft
- Dec 2030
114 homes
Be one of the first 10 buyers in this groupFounding members — it’s free
Join group for Splendid Evora
Veerasandra, Electronic City Phase 1Under constructionRERA registeredBuyers’ group openAyatana Residences E-City
by Aratt One World
Price: Price on requestGet brochure & price →
- 3 BHK, 4 BHK
- 1,272 – 1,613 sq ft
- Jun 2029
166 homes
Be one of the first 10 buyers in this groupFounding members — it’s free
Join group for Ayatana Residences E-City
Hebbagodi, Electronic City Phase 1Artist’s impressionUnder constructionRERA registeredBuyers’ group openPurva Silversky
by Puravankara
Price: Price on requestGet brochure & price →
- 3 BHK, 4 BHK, 5 BHK
- 1,125 – 2,999 sq ft
- Jul 2030
356 homes
Be one of the first 10 buyers in this groupFounding members — it’s free
Join group for Purva Silversky