Skip to content
Log in

Halcyon

1, 2 & 3 BHK apartments by Lankipalle Haribabu · Huskur, Budigere Cross, Bengaluru

Huskur, Budigere Cross, Bengaluru

  • Under construction
  • RERA registered
  • residential

by Lankipalle Haribabu

Price: Price on request

Get brochure, floor plans & price

Brochure, floor plans and price list for Halcyon

Builders share their brochure, floor plans and price list only on request. Tell us how to reach you and we’ll get them and send them to you, free.

Free for buyers. If you book through us, the builder pays us a commission. How we earn

Project summary

Halcyon is a residential project by Lankipalle Haribabu in Huskur, Bengaluru with 346 homes, registered with Karnataka RERA. The completion date on RERA is 26 Jul 2027.

Not in the RERA record we collected yet: map location. This page fills in as the record is collected.

Facts collected on 20 Oct 2026 from public records — each linked to its source. Free for buyers. If you book through us, the builder pays us a commission.

Halcyon buyers’ group: join to ask for a group price

No one has joined yet. Be one of the first 10 buyers in this group — the founding members.

Join free. When enough buyers have joined, our agent partner asks Lankipalle Haribabu for a group price — for example a lower price, an easier payment plan or waived charges. Nothing is promised: you see what the builder offers and book directly with the builder if you want to. Free for buyers. If you book through us, the builder pays us a commission.

  1. Gathering buyers
  2. Talking to the builder
  3. Group offer
  4. Group site visit
  5. Booking

0 buyers have joined · 0 committed

Committed buyers have confirmed their budget, home type and timeline with us on a call; builders negotiate with them. Joining is free and never obliges you to buy.

Join the Halcyon buyers’ groupHow group buying works

See it for yourself

Visit the site with our team, or get a call to clear your questions. Free, no obligation.

Key facts: home types, towers, land and possession

Updated on 20 Oct 2026
Home types
1 BHK, 2 BHK, 3 BHK
Carpet area
425 – 1,550 sq ft
Towers
3
Floors
5
Total homes
346
Land
5.67 acres
Possession (extended)
Jul 2027
Built (RERA update)
70%

Halcyon RERA number and registration details

RERA number
TOR/PRM/KA/RERA/1251/446/PR/241129/001744
Registered on
29 Nov 2024
Promised completion
26 Jul 2026
Extended to
26 Jul 2027
RERA status
Under construction
Homes booked
76 of 346 as on
Price
Not found in public records yet: price
Project type
Residential

Towers and blocks (RERA filing)

TowerFloorsBasementsHomes
ROW HOUSE2014
BCDEFG BLOCKS50152
HIJKL BLOCKS50180

A dash (—) means the filing did not state that value.

Sources:Source (rera.karnataka.gov.in) (opens in a new tab)

Summary in plain English

Halcyon is a residential project by Lankipalle Haribabu in Huskur, Bengaluru East, with 346 homes across 3 towers. The project has a registered completion date of 26 July 2027, with one extension granted under Section 6.

Written by AI from the RERA record above on 20 Oct 2026. Every number in it was checked against that record; if anything differs, the record wins.

Open space, home loans, escrow and other details

Open space
56.8% of land
Water and power
Not found in public records yet: water and power
Home loans: approved banks
Not found in public records yet: bank approvals
Payment plans
Not found in public records yet: payment plans
Maintenance
Not found in public records yet: maintenance
Car parking
Not found in public records yet: car parking charge
Escrow bank (RERA)
STATE BANK OF INDIA, KASTURINAGAR BRANCH
Project cost declared to RERA
₹70 Cr

Open area as a share of the land, from the areas filed with RERA (includes driveways and landscaped areas).

Sources:Source (rera.karnataka.gov.in) (opens in a new tab)

Amenities

Not found in public records yet: amenities

Halcyon location and address

Address
Sy. No 68/2 Huskur Village, Bidarahalli Hobli, Off Old Madras road
Village (RERA)
Huskur
Locality
Budigere CrossAlso known as Budigere
PIN code
560049
City
Bengaluru
State
Karnataka
Coordinates
Not found in public records yet: coordinates

Distances to landmarks

Not found in public records yet: landmarks

About Budigere Cross

Not found in public records yet: locality facts

Halcyon floor plans, brochure and elevations

Documents the builder uploaded to Karnataka RERA, shown as filed. Tap a page to see it full size; the full PDF opens on the RERA website.

Floor plans2 files

Home typeCarpet areaHomes
1 BHK425 – 561 sq ft52
2 BHK567 – 870 sq ft208
3 BHK777 – 1,550 sq ft86

Home types, counts and carpet areas as filed with Karnataka RERA (carpet area, not super built-up).

We have not collected floor-plan drawings; the builder’s sales team can share them.

Sources:Source (rera.karnataka.gov.in) (opens in a new tab)

Halcyon possession date and construction status

  • Whole project (promoter’s RERA update)70%

    as on · 76 of 346 homes booked

Promoter’s quarterly update to RERA for Q2 2026-27, submitted 2026-10-15.

By tower (Q2 2026-27)

  • ROW HOUSE60%
  • BCDEFG BLOCKS70%
  • HIJKL BLOCKS70%

Units sold and unsold, from RERA (Q2 2026-27)

TypeHomesBookedAvailable
3 BHK862264
2 BHK20848160
1 BHK52646

As reported by the promoter in the quarterly update to RERA, not verified by us.

Timeline

  1. 19 Jan 2017Project start date given to RERA
  2. 29 Nov 2024Registered with Karnataka RERA
  3. 26 Jul 2026Completion date given at registration
  4. 26 Jul 2027Section 6 Extension: completion date moved to this date

Sources:Source (rera.karnataka.gov.in) (opens in a new tab)

Construction pace from RERA quarterly filings

As on 15 Oct 2026

At the average pace so far, construction would reach 100% around Nov 2030 — about 40 months after the completion date on RERA (26 Jul 2027).

At the pace between the 4 quarterly filings we have (31% → 70% in 9 months), it would be around Apr 2027 — about 3 months before the RERA date.

0%25%50%75%100%2018202020222024202620282030RERA date31%43%64%70%
  • Filed on RERA
  • Average pace since start
  • Pace between filings (and 0% assumed at the start date)
  • RERA completion date

Quarterly filings

QuarterFiled onBuiltHomes booked
Q2 2026-27to 30 Sep 202615 Oct 202670%76 of 346
Q1 2026-27to 30 Jun 202615 Jul 202664%64 of 346
Q4 2025-26to 31 Mar 202615 Apr 202643%53 of 346
Q3 2025-26to 31 Dec 202531 Mar 202631%33 of 346
How we calculate

Average pace = % built ÷ months since the start date in the RERA record. Here: 70% ÷ 116.3 months (19 Jan 2017 to 30 Sep 2026) = 0.6% a month.

Estimated finish = latest filing date + (100 − % built) ÷ pace = 30 Sep 2026 + 30 ÷ 0.6 = 49.9 months → Nov 2030. This is an estimate, not a date from the builder or RERA.

Pace between filings = (70% − 31%) ÷ 9 months = 4.3% a month.

A straight line is a simplification: the builder reports one overall %, which mixes excavation, structure and finishing, and work rarely moves at a constant speed. The % values are the promoter’s own figures filed with RERA, not checked by us. Promoter’s quarterly update to RERA for Q2 2026-27, submitted 2026-10-15.

Sources:Source (rera.karnataka.gov.in) (opens in a new tab)How we calculate this

Approvals and documents checklist

ApprovalAuthoritySource
Building planBMRDA - Bangalore Metropolitan Region Development AuthoritySource (rera.karnataka.gov.in) (opens in a new tab)

Documents uploaded to RERA

As on 20 Oct 2026
  • Building or layout plan · Approved drawings from the planning authorityFiled on RERA ✓ — scanned copy uploaded; number and date not read yet
  • Commencement certificate · Permission to start buildingNot on RERA yet
  • Environment clearance · SEIAA KarnatakaNot on RERA yet
  • Fire NOC · Karnataka Fire and Emergency ServicesNot on RERA yet
  • Pollution board consent · KSPCBNot on RERA yet
  • Water and sewerage · BWSSBNot on RERA yet
  • Electricity · BESCOMNot on RERA yet
  • Height clearance · Airports Authority of IndiaNot on RERA yet
  • Occupancy certificate (OC) · Issued only when the building is finishedNot on RERA yet — expected at completion

From the documents the promoter uploaded to Karnataka RERA, collected 20 Oct 2026. “Filed” means a document is on RERA — we have not checked its contents or validity. Not every approval applies to every project (for example, smaller projects may not need an environment clearance). The project page on RERA lists each upload.

Sources:Source (rera.karnataka.gov.in) (opens in a new tab)

Halcyon RERA complaints and orders

1 complaint as on Source (rera.karnataka.gov.in) (opens in a new tab)

Complaint refFiledSubjectStatusSource
00741/202515 May 2025Possesion not given by the KSR, Project is taken over by Land Owner Hari babu, No registration was done by the land OwnerDisposedSource (rera.karnataka.gov.in) (opens in a new tab)

Court and consumer cases

Not found in public records yet: court cases

We list case numbers, courts and outcomes only — never names of private individuals.

About Lankipalle Haribabu

Promoter type
Proprietorship
Projects on this site
1
RERA complaints against promoter
1
Company number (CIN)
Not found in public records yet: CIN

From Karnataka RERA, as collected so far (20 Oct 2026). Complaints are those RERA lists against this promoter across all its projects.

Lankipalle Haribabu’s RERA record

Lankipalle Haribabu delivery record

As on 20 Oct 2026

What the complaints are about

  • Delay in possession or delay interest1

1 complaint subject as written on RERA, as on . Each subject is sorted into one group by keywords (first match wins: delay, refund, registration, quality, litigation, association); one complaint often raises several issues. Source (rera.karnataka.gov.in) (opens in a new tab)

Sources:Source (rera.karnataka.gov.in) (opens in a new tab)How we calculate this

What’s changed since Jan 2017

As on 20 Oct 2026
  1. 26 Jul 2027Completion date extended to 26 Jul 2027 Source (rera.karnataka.gov.in) (opens in a new tab)
  2. 15 Oct 2026Quarterly update filed for Q2 2026-27: 70% built, 76 of 346 homes booked Source (rera.karnataka.gov.in) (opens in a new tab)
  3. 15 Jul 2026Quarterly update filed for Q1 2026-27: 64% built, 64 of 346 homes booked Source (rera.karnataka.gov.in) (opens in a new tab)
  4. 15 Apr 2026Quarterly update filed for Q4 2025-26: 43% built, 53 of 346 homes booked Source (rera.karnataka.gov.in) (opens in a new tab)
  5. 31 Mar 2026Quarterly update filed for Q3 2025-26: 31% built, 33 of 346 homes booked Source (rera.karnataka.gov.in) (opens in a new tab)
  6. 15 May 2025Complaint 00741/2025 filed with RERA: “Possesion not given by the KSR, Project is taken over by Land Owner Hari babu, No registration was done by the land Owner” — now disposed Source (rera.karnataka.gov.in) (opens in a new tab)
  7. 29 Nov 2024Registered with Karnataka RERA (TOR/PRM/KA/RERA/1251/446/PR/241129/001744); completion date 26 Jul 2026 Source (rera.karnataka.gov.in) (opens in a new tab)
  8. 19 Jan 2017Project start date in the RERA record Source (rera.karnataka.gov.in) (opens in a new tab)

Newest first. When the RERA crawl sees a new filing, complaint or extension, it is added here with its date.

Home loan EMI calculator

No listed price found — enter one to try.

Example only — use your bank’s quote.

Monthly EMI
—
Down payment
—
Loan amount
—
Total interest
—

A calculation only, from the numbers you enter — not a loan offer.

All-in cost: GST, registration and other charges

The calculator loads when you scroll to it.

Assumptions
  • Base price: the builder’s price is not published in a form we could collect — enter it from the cost sheet.
  • GST 5% on the base price and charges — the usual rate for an under-construction home that is not “affordable housing” (1%).
  • Stamp duty about 5.6% and registration 2% — the Karnataka rule (registration was raised from 1% to 2% on 31 Aug 2025). Calculated on the agreement value.
  • Car parking, other charges and the maintenance deposit are not in the public record we collect; enter them from the builder’s cost sheet.
  • Loan on the agreement value (banks usually lend up to 75–90%); EMI is the standard reducing-balance formula. Example rate only — use your bank’s quote.

How we calculate this

Halcyon FAQs

When will Halcyon be completed?

The completion date on RERA is 26 July 2027. The original completion date was 26 July 2026, which was extended once.

What home types are available in Halcyon?

Halcyon has 1 BHK (52 homes, 425–561 carpet sq ft), 2 BHK (208 homes, 567–870 carpet sq ft), and 3 BHK (86 homes, 777–1,550 carpet sq ft).

How many homes are in Halcyon?

There are 346 homes across 3 towers, each with a maximum of 5 floors.

What is the latest construction progress in Halcyon?

As of Q2 2026–27 (ended 30 September 2026), the project is 70% complete with 76 homes booked.

Where is Halcyon located?

Halcyon is in Huskur, Bengaluru East taluk, Bengaluru Urban district, PIN code 560049.

Are there RERA complaints about Halcyon?

There is 1 RERA complaint on this project registration.

Does the builder have other projects on RERA record?

Lankipalle Haribabu has 1 project in the Bengaluru RERA records with 1 RERA complaint against the builder across all projects.

What is the land area of Halcyon?

The project land area is 22,965 sq m.

Who is the escrow bank for Halcyon?

The escrow bank for the project is State Bank of India.

Written by AI from the RERA record above on 20 Oct 2026. Answers use only that record; check them against the source before you decide.

Questions about Halcyon

No questions published yet. Ask the first one: you get an instant answer from this page’s public record, and our team follows up on anything the record does not show.

Bought a home from Lankipalle Haribabu? Review the builder.

Reviews of Lankipalle Haribabu by verified buyers

No verified reviews of Lankipalle Haribabu yet. If you bought a home from them, your review helps other buyers.

How reviews work: only buyers and owners can review; we confirm each purchase by phone before publishing, publish positive and negative reviews alike, never accept payment for reviews, and the builder may reply.

Sources and last checked dates

  1. Karnataka RERA — project register (search by the registration number) (opens in a new tab)

Collected on 20 Oct 2026 by AI research agents reading public pages. Facts are written in our own words. Not found yet: price; court cases; landmarks; specifications; news.

How to check on RERA: On rera.karnataka.gov.in/viewAllProjects, type the registration number in 'Registration No', press Search, then click the 'View Project Details' icon. Complaints open from the 'Complaints / Litigation' icon in the same row. Registration number: TOR/PRM/KA/RERA/1251/446/PR/241129/001744.

  • RERA record last checked: 20 Oct 2026
  • Last change in the record (registration, quarterly filing or complaint): 20 Oct 2026

How this page is made: software builds it from public records (Karnataka RERA filings, OpenStreetMap, the builder’s own website). AI is used only to read filings into fields and to write the plain-English summary and FAQ answers, which are checked against the record. Facts are checked automatically against the RERA filing. Methodology · How we earn · Report an error

More new projects in Budigere Cross

  • Alchemy One: Site photo filed with Karnataka RERABhandapura, Budigere CrossReady to moveRERA registeredBuyers’ group open

    Alchemy One

    by Aratt Trident

    Price: Price on requestGet brochure & price →

    • 2 BHK, 3 BHK, 4 BHK
    • 653 – 2,963 sq ft
    • Jun 2026 (extended)

    162 homes

    Be one of the first 10 buyers in this groupFounding members — it’s free

    Join group for Alchemy One
  • Sobha Galera: Front elevation of Spanish-style row house (artist’s impression)Huskur, Budigere CrossArtist’s impressionUnder constructionRERA registeredBuyers’ group open

    Sobha Galera

    by Sobha

    Price: Price on requestGet brochure & price →

    • 4 BHK
    • 2,449 – 3,355 sq ft
    • Dec 2026

    40 homes · 1 RERA complaint

    Be one of the first 10 buyers in this groupFounding members — it’s free

    Join group for Sobha Galera