In That Quiet Earth Phase-2a
3 BHK apartments by Total Environment Constructions Private Limited · Bileshivale, Horamavu, Bengaluru
Bileshivale, Horamavu, BengaluruOpen on Google Maps (opens in a new tab)
- Under construction
- RERA registered
- residential
by Total Environment Constructions Private Limited
Price: Price on request
Site photo filed with Karnataka RERA Karnataka RERA filing · Source ↗ (opens in a new tab)
In That Quiet Earth Phase-2a at a glance
- Possession (RERA)Dec 2026 ExtendedWas Dec 2025 · Karnataka RERA
- Construction55% built · on pace for Feb 2031 50 mo after RERA dateRERA filing to 30 Jun 2026; estimate from average pace
- Homes booked55 of 110 (50%)RERA update · as on 30 Jun 2026
- RERA complaints (project)1 complaintKarnataka RERA · as on 13 Oct 2026
- Approvals filed1 of 9 on RERAKarnataka RERA uploads · 13 Oct 2026
Project summary
In That Quiet Earth Phase-2a is a residential project by Total Environment Constructions Private Limited in Bileshivale, Bengaluru with 110 homes, registered with Karnataka RERA. The completion date on RERA is 31 Dec 2026.
Facts collected on 13 Oct 2026 from public records — each linked to its source. Free for buyers. If you book through us, the builder pays us a commission.
In That Quiet Earth Phase-2a buyers’ group: join to ask for a group price
No one has joined yet. Be one of the first 10 buyers in this group — the founding members.
Join free. When enough buyers have joined, our agent partner asks Total Environment Constructions Private Limited for a group price — for example a lower price, an easier payment plan or waived charges. Nothing is promised: you see what the builder offers and book directly with the builder if you want to. Free for buyers. If you book through us, the builder pays us a commission.
- Gathering buyers
- Talking to the builder
- Group offer
- Group site visit
- Booking
0 buyers have joined · 0 committed
Committed buyers have confirmed their budget, home type and timeline with us on a call; builders negotiate with them. Joining is free and never obliges you to buy.
Join the In That Quiet Earth Phase-2a buyers’ groupHow group buying works
See it for yourself
Visit the site with our team, or get a call to clear your questions. Free, no obligation.
Key facts: home types, towers, land and possession
- Home types
- 3 BHK, Villa
- Carpet area
- 2,768 sq ft
- Towers
- 2
- Floors
- 1
- Total homes
- 110
- Land
- 4.82 acres
- Possession (extended)
- Dec 2026
- Built (RERA update)
- 55%
In That Quiet Earth Phase-2a RERA number and registration details
- RERA number
- PRM/KA/RERA/1251/446/PR/201001/003630
- Registered on
- 1 Oct 2020
- Promised completion
- 31 Dec 2025
- Extended to
- 31 Dec 2026
- RERA status
- New launch
- Homes booked
- 55 of 110 as on
- Price
- Not found in public records yet: price
- Project type
- Residential
Towers and blocks (RERA filing)
| Tower | Floors | Basements | Homes |
|---|---|---|---|
| Block 5 Villas | 1 | 0 | 24 |
| Block 6 Villas | 1 | 0 | 31 |
A dash (—) means the filing did not state that value.
Summary in plain English
In That Quiet Earth Phase-2a is a residential project by Total Environment Constructions Private Limited in Bileshivale, Bengaluru East, with 110 homes across 2 towers. The project was registered with RERA for completion on 31 December 2025, extended to 31 December 2026.
Written by AI from the RERA record above on 13 Oct 2026. Every number in it was checked against that record; if anything differs, the record wins.
Open space, home loans, escrow and other details
- Open space
- 56.9% of land
- Water and power
- Not found in public records yet: water and power
- Home loans: approved banks
- Not found in public records yet: bank approvals
- Payment plans
- Not found in public records yet: payment plans
- Maintenance
- Not found in public records yet: maintenance
- Car parking
- Not found in public records yet: car parking charge
- Escrow bank (RERA)
- Standard Chartered Bank, Koramangala Branch
- Project cost declared to RERA
- ₹182 Cr
Open area as a share of the land, from the areas filed with RERA (includes driveways and landscaped areas).
Amenities
In That Quiet Earth Phase-2a location and address
- Address
- Property Katha No. 28 , 46, 110,111 situated at Bileshivale Village, Bidarahalli Hobli, Bengaluru East Taluk, Bengaluru
- Village (RERA)
- Bileshivale
- Locality
- HoramavuAlso known as Horamavu Agara
- PIN code
- 560066
- City
- Bengaluru
- State
- Karnataka
- Coordinates
- 13.00000, 77.00000
Distances to landmarks
Not found in public records yet: landmarksAbout Horamavu
Not found in public records yet: locality factsIn That Quiet Earth Phase-2a home types and carpet areas
Floor plans and brochure not published? The builder shares them only on request. We’ll get the brochure, floor plans and current price list for you, free.
Get brochure, floor plans & price| Home type | Carpet area | Homes |
|---|---|---|
| 3 BHK | 2,768 sq ft | 55 |
| Residential villas | 2,768 sq ft | 55 |
Home types, counts and carpet areas as filed with Karnataka RERA (carpet area, not super built-up).
We have not collected floor-plan drawings; the builder’s sales team can share them.
In That Quiet Earth Phase-2a possession date and construction status
Promoter’s quarterly update to RERA for Q1 2026-27, submitted 2026-07-15.
By tower (Q1 2026-27)
Units sold and unsold, from RERA (Q1 2026-27)
| Type | Homes | Booked | Available |
|---|---|---|---|
| 3 BHK | 55 | 55 | 0 |
As reported by the promoter in the quarterly update to RERA, not verified by us.
Timeline
- 1 Oct 2020Registered with Karnataka RERA
- 1 Nov 2020Project start date given to RERA
- 31 Dec 2025Completion date given at registration
- 31 Dec 2026Section 6 Extension: completion date moved to this date
Construction pace from RERA quarterly filings
At the average pace so far, construction would reach 100% around Feb 2031 — about 50 months after the completion date on RERA (31 Dec 2026).
- Filed on RERA
- Average pace since start
- RERA completion date
Quarterly filings
| Quarter | Filed on | Built | Homes booked |
|---|---|---|---|
| Q1 2026-27to 30 Jun 2026 | 15 Jul 2026 | 55% | 55 of 55 |
| Q4 2025-26to 31 Mar 2026 | 15 Apr 2026 | 45% | 24 of 24 |
| Q3 2025-26to 31 Dec 2025 | 27 Jan 2026 | 84% | 55 of 55 |
How we calculate
Average pace = % built ÷ months since the start date in the RERA record. Here: 55% ÷ 67.9 months (1 Nov 2020 to 30 Jun 2026) = 0.8% a month.
Estimated finish = latest filing date + (100 − % built) ÷ pace = 30 Jun 2026 + 45 ÷ 0.8 = 55.6 months → Feb 2031. This is an estimate, not a date from the builder or RERA.
Pace between filings = (55% − 84%) ÷ 5.9 months = -4.9% a month.
A straight line is a simplification: the builder reports one overall %, which mixes excavation, structure and finishing, and work rarely moves at a constant speed. The % values are the promoter’s own figures filed with RERA, not checked by us. Promoter’s quarterly update to RERA for Q1 2026-27, submitted 2026-07-15.
Sources:Source (rera.karnataka.gov.in) (opens in a new tab)How we calculate this
Approvals and documents checklist
| Approval | Authority | Source |
|---|---|---|
| Building plan | BBMP - Bruhat Bengaluru Mahanagara Palike | Source (rera.karnataka.gov.in) (opens in a new tab) |
Documents uploaded to RERA
- Building or layout plan · Approved drawings from the planning authorityFiled on RERA ✓ — scanned copy uploaded; number and date not read yet
- Commencement certificate · Permission to start buildingNot on RERA yet
- Environment clearance · SEIAA KarnatakaNot on RERA yet
- Fire NOC · Karnataka Fire and Emergency ServicesNot on RERA yet
- Pollution board consent · KSPCBNot on RERA yet
- Water and sewerage · BWSSBNot on RERA yet
- Electricity · BESCOMNot on RERA yet
- Height clearance · Airports Authority of IndiaNot on RERA yet
- Occupancy certificate (OC) · Issued only when the building is finishedNot on RERA yet — expected at completion
From the documents the promoter uploaded to Karnataka RERA, collected 13 Oct 2026. “Filed” means a document is on RERA — we have not checked its contents or validity. Not every approval applies to every project (for example, smaller projects may not need an environment clearance). The project page on RERA lists each upload.
In That Quiet Earth Phase-2a RERA complaints and orders
1 complaint as on Source (rera.karnataka.gov.in) (opens in a new tab)
| Complaint ref | Filed | Subject | Status | Source |
|---|---|---|---|---|
| 00027/2024 | 8 Jan 2024 | Complaint for return of amount and compensation | Disposed | Source (rera.karnataka.gov.in) (opens in a new tab) |
Court and consumer cases
We list case numbers, courts and outcomes only — never names of private individuals.
About Total Environment Constructions Private Limited
- Promoter type
- Company
- Projects on this site
- 2
- RERA complaints against promoter
- 9
- Company number (CIN)
- U45202KA1985PTC007026
From Karnataka RERA, as collected so far (13 Oct 2026). Complaints are those RERA lists against this promoter across all its projects.
Total Environment Constructions Private Limited’s RERA recordTotal Environment Constructions Private Limited delivery record
- 2Projects in Bengaluru on RERA5 approved registrations under Total Environment Constructions Private Limited in Bengaluru Urban and Rural. Source (rera.karnataka.gov.in) (opens in a new tab)
- 1,854Homes registeredAs stated in each registrations.
- 9RERA complaints6 open, 3 disposed. as on Source (rera.karnataka.gov.in) (opens in a new tab)
- 4.9Complaints per 1,000 homes9 complaints ÷ 1,854 homes in its 5 registrations on Karnataka RERA in Bengaluru.
What the complaints are about
9 complaint subjects as written on RERA, as on . Each subject is sorted into one group by keywords (first match wins: delay, refund, registration, quality, litigation, association); one complaint often raises several issues. Source (rera.karnataka.gov.in) (opens in a new tab)
Sources:Source (rera.karnataka.gov.in) (opens in a new tab)How we calculate this
What’s changed since Oct 2020
- 31 Dec 2026Completion date extended to 31 Dec 2026 Source (rera.karnataka.gov.in) (opens in a new tab)
- 15 Jul 2026Quarterly update filed for Q1 2026-27: 55% built, 55 of 55 homes booked Source (rera.karnataka.gov.in) (opens in a new tab)
- 15 Apr 2026Quarterly update filed for Q4 2025-26: 45% built, 24 of 24 homes booked Source (rera.karnataka.gov.in) (opens in a new tab)
- 27 Jan 2026Quarterly update filed for Q3 2025-26: 84% built, 55 of 55 homes booked Source (rera.karnataka.gov.in) (opens in a new tab)
- 8 Jan 2024Complaint 00027/2024 filed with RERA: “Complaint for return of amount and compensation” — now disposed Source (rera.karnataka.gov.in) (opens in a new tab)
- 1 Nov 2020Project start date in the RERA record Source (rera.karnataka.gov.in) (opens in a new tab)
- 1 Oct 2020Registered with Karnataka RERA (PRM/KA/RERA/1251/446/PR/201001/003630); completion date 31 Dec 2025 Source (rera.karnataka.gov.in) (opens in a new tab)
Newest first. When the RERA crawl sees a new filing, complaint or extension, it is added here with its date.
Home loan EMI calculator
- Monthly EMI
- —
- Down payment
- —
- Loan amount
- —
- Total interest
- —
A calculation only, from the numbers you enter — not a loan offer.
All-in cost: GST, registration and other charges
The calculator loads when you scroll to it.
Assumptions
- Base price: the builder’s price is not published in a form we could collect — enter it from the cost sheet.
- GST 5% on the base price and charges — the usual rate for an under-construction home that is not “affordable housing” (1%).
- Stamp duty about 5.6% and registration 2% — the Karnataka rule (registration was raised from 1% to 2% on 31 Aug 2025). Calculated on the agreement value.
- Car parking, other charges and the maintenance deposit are not in the public record we collect; enter them from the builder’s cost sheet.
- Loan on the agreement value (banks usually lend up to 75–90%); EMI is the standard reducing-balance formula. Example rate only — use your bank’s quote.
In That Quiet Earth Phase-2a FAQs
What is the RERA registration number for In That Quiet Earth Phase-2a?
The project is registered as PRM/KA/RERA/1251/446/PR/201001/003630, registered on 1 October 2020.
When is In That Quiet Earth Phase-2a expected to be completed?
The completion date on RERA is 31 December 2026, extended from the original date of 31 December 2025 under Section 6 Extension.
How many homes are in In That Quiet Earth Phase-2a?
The project has 110 homes across 2 towers.
What types of homes are available in In That Quiet Earth Phase-2a?
The project offers 55 residential villas and 55 three-bedroom homes, each with a carpet area of 2,768 sq ft.
What is the construction progress of In That Quiet Earth Phase-2a?
As of Q4 2025-26 (quarter ended 31 March 2026), the project is 45% complete.
How many homes have been booked in In That Quiet Earth Phase-2a?
As of Q4 2025-26, 24 homes have been booked out of 110.
Where is In That Quiet Earth Phase-2a located?
The project is in Bileshivale, Bengaluru East taluk, Bengaluru Urban district, PIN code 560066.
Are there any RERA complaints against In That Quiet Earth Phase-2a?
There is 1 RERA complaint on this project registration.
How many RERA complaints are there against Total Environment Constructions Private Limited across all projects?
There are 7 RERA complaints against the builder across all projects on record.
How many other projects does Total Environment Constructions have in the RERA records?
The builder has 3 projects in total in our Bengaluru RERA records.
Written by AI from the RERA record above on 13 Oct 2026. Answers use only that record; check them against the source before you decide.
Questions about In That Quiet Earth Phase-2a
No questions published yet. Ask the first one: you get an instant answer from this page’s public record, and our team follows up on anything the record does not show.
Bought a home from Total Environment Constructions Private Limited? Review the builder.
Reviews of Total Environment Constructions Private Limited by verified buyers
No verified reviews of Total Environment Constructions Private Limited yet. If you bought a home from them, your review helps other buyers.
How reviews work: only buyers and owners can review; we confirm each purchase by phone before publishing, publish positive and negative reviews alike, never accept payment for reviews, and the builder may reply.
Similar projects within 5 km
| Project | Distance | Homes | Possession (RERA) | Built | Complaints | Price |
|---|---|---|---|---|---|---|
| Mahaveer NorthscapePragati Corp | 0 km | 476 | Sep 2025extended | — | 3 | Not collected |
| 3 Little BirdsZenso Little Birds Projects LLP | 0 km | 30 | Sep 2026extended | — | 0 | Not collected |
| Aspire Aurum A Sumadhura VentureSumadhura Infracon Private Limited | 0 km | 326 | Sep 2023extended | — | 0 | Not collected |
| V.S.R TranquilV.S.R Ventures | 0 km | 366 | Sep 2025extended | — | 1 | Not collected |
| Kumar ProsperaKumar Properties Pvt Ltd | 0 km | 125 | Jun 2030extended | — | 1 | Not collected |
| The HavenSri Parvata Builders Private Limited | 0 km | 177 | Jun 2025extended | — | 0 | Not collected |
Projects of the same kind within 5 km in a straight line of this project’s RERA map point, nearest first. % built is the promoter’s latest quarterly figure on RERA (shown for single-registration projects); prices are from the builder’s own website where we found one.
Sources and last checked dates
Collected on 13 Oct 2026 by AI research agents reading public pages. Facts are written in our own words. Not found yet: price; court cases; landmarks; specifications; news.
How to check on RERA: On rera.karnataka.gov.in/viewAllProjects, type the registration number in 'Registration No', press Search, then click the 'View Project Details' icon. Complaints open from the 'Complaints / Litigation' icon in the same row. Registration number: PRM/KA/RERA/1251/446/PR/201001/003630.
- RERA record last checked: 13 Oct 2026
- Last change in the record (registration, quarterly filing or complaint): 15 Jul 2026
How this page is made: software builds it from public records (Karnataka RERA filings, OpenStreetMap, the builder’s own website). AI is used only to read filings into fields and to write the plain-English summary and FAQ answers, which are checked against the record. Facts are checked automatically against the RERA filing. Methodology · How we earn · Report an error
More new projects in Horamavu
HoramavuReady to moveRERA registeredBuyers’ group openV.S.R Tranquil
by V.S.R Ventures
Price: Price on requestGet brochure & price →
- 2 BHK, 3 BHK
- 695 – 1,206 sq ft
- Sep 2025 (extended)
366 homes · 1 RERA complaint
Be one of the first 10 buyers in this groupFounding members — it’s free
Join group for V.S.R Tranquil
Horamavu Agara, HoramavuReady to moveRERA registeredBuyers’ group openNava Gokulam
by Navajyothi Constructions
Price: Price on requestGet brochure & price →
- 2 BHK, 3 BHK
- 827 – 1,360 sq ft
- Dec 2025
180 homes
Be one of the first 10 buyers in this groupFounding members — it’s free
Join group for Nava Gokulam
Horamavu Agara, HoramavuUnder constructionRERA registeredBuyers’ group openS K Dwaraka
by S K Builders And
Price: Price on requestGet brochure & price →
- 2 BHK, 3 BHK
- 668 – 1,176 sq ft
- Jun 2026 (extended)
RERA not updated since promised Jun 2026 · 156 homes
Be one of the first 10 buyers in this groupFounding members — it’s free
Join group for S K Dwaraka