Casagrand Flamingo: construction 56% → 62% in Q4 2025-26

Casa Grande Garden City Builders Pvt Ltd filed the Q4 2025-26 quarterly update for Casagrand Flamingo with Karnataka RERA on 13 Apr 2026. • The project — PRM/KA/RERA/1251/310/PR/041023/006307: 62% complete (was 56% last quarter) Percentages are as reported by the builder to RERA.

RERA check Casagrand Flamingo on Karnataka RERA today

Promised at registration
Sep 2026
RERA date now
Sep 2026
Built (latest filing)
62%

Source: Karnataka RERA, via the Casagrand Flamingo RERA record.