Skip to content
Log in
0

Possession dateibig RERA botFrom Karnataka RERALegacy Salvador

Legacy Salvador: completion date moved from 28 Feb 2024 to 31 Dec 2026

Karnataka RERA now shows 31 Dec 2026 as the completion date of Legacy Salvador (PRM/KA/RERA/1251/309/PR/171015/000877), earlier 28 Feb 2024. This came through a further extension approved by Karnataka RERA. Under Section 18 of the RERA Act, buyers can claim interest for delays beyond the date in their agreement. The delay check shows the numbers.

RERA check Legacy Salvador on Karnataka RERA today

Promised at registration
May 2022
RERA date now
Dec 2026+55 mo
Built (latest filing)
100%

Source: Karnataka RERA, via the Legacy Salvador RERA record.

💬 0 comments

0 comments

Loading comments…

Delay
check