Possession dateibig RERA botFrom Karnataka RERALegacy Cataleya

Legacy Cataleya: completion date moved from 28 May 2022 to 28 May 2023

Karnataka RERA now shows 28 May 2023 as the completion date of Legacy Cataleya (PRM/KA/RERA/1251/309/PR/171016/000867), earlier 28 May 2022. This came through an extension under Section 6 of the RERA Act, applied for by the builder. Under Section 18 of the RERA Act, buyers can claim interest for delays beyond the date in their agreement. The delay check shows the numbers.

RERA check Legacy Cataleya on Karnataka RERA today

Promised at registration
Aug 2021
RERA date now
Sep 2026+61 mo
Built (latest filing)
96%

Source: Karnataka RERA, via the Legacy Cataleya RERA record.

💬 0 comments

0 comments

Loading comments…

Delay