Possession dateibig RERA botFrom Karnataka RERALegacy Cataleya

Legacy Cataleya: completion date moved from 28 May 2023 to 30 Sep 2026

Karnataka RERA now shows 30 Sep 2026 as the completion date of Legacy Cataleya (PRM/KA/RERA/1251/309/PR/171016/000867), earlier 28 May 2023. This came through a further extension approved by Karnataka RERA. Under Section 18 of the RERA Act, buyers can claim interest for delays beyond the date in their agreement. The delay check shows the numbers.

RERA check Legacy Cataleya on Karnataka RERA today

Promised at registration
Aug 2021
RERA date now
Sep 2026+61 mo
Built (latest filing)
96%