Provident Equinox 5: no construction progress reported in Q1 2026-27 (still 1%)

Puravankara Limited filed the Q1 2026-27 quarterly update for Provident Equinox 5 with Karnataka RERA on 28 Sep 2026. • The project — PRM/KA/RERA/1251/310/PR/170126/008410: 1% complete (same as last quarter) Percentages are as reported by the builder to RERA.

RERA check Provident Equinox 5 on Karnataka RERA today

Promised at registration
Mar 2030
RERA date now
Mar 2030
Built (latest filing)
1%

Source: Karnataka RERA, via the Provident Equinox 5 RERA record.