Provident Deansgate: Q4 2025-26 RERA construction filings show progress

Puravankara Limited filed the Q4 2025-26 quarterly update for Provident Deansgate with Karnataka RERA on 20 Jul 2026. • Phase 2 — PRM/KA/RERA/1250/303/PR/170325/007590: 24% complete (was 18% last quarter) • Main registration — PRM/KA/RERA/1250/303/PR/041123/006373: 76% complete (was 56% last quarter) Percentages are as reported by the builder to RERA.

RERA check Provident Deansgate on Karnataka RERA today

Promised at registration
Mar 2028
RERA date now
Mar 2028
Built (latest filing)
50%

Source: Karnataka RERA, via the Provident Deansgate RERA record.