Provident Equinox 3: construction 61% → 79% in Q2 2026-27
Puravankara Limited filed the Q2 2026-27 quarterly update for Provident Equinox 3 with Karnataka RERA on 15 Oct 2026. • The project — PRM/KA/RERA/1251/310/PR/180724/006944: 79% complete (was 61% last quarter) Percentages are as reported by the builder to RERA.
RERA check Provident Equinox 3 on Karnataka RERA today
- Promised at registration
- Mar 2028
- RERA date now
- Mar 2028
- Built (latest filing)
- 79%
Source: Karnataka RERA, via the Provident Equinox 3 RERA record.