Sobha Neopolis: Q2 2026-27 RERA construction filings show progress
Sobha Limited filed the Q2 2026-27 quarterly update for Sobha Neopolis with Karnataka RERA on 14 Oct 2026. • Phase 1 - W 14, 15, 16, 17, 18 &19 — PRM/KA/RERA/1251/446/PR/200923/006269: 64% complete (was 58% last quarter) • Phase 2 - W 12 & 13 — PRM/KA/RERA/1251/446/PR/200923/006270: 47% complete (was 45% last quarter) • Phase 3 - W 1, 2, 10 & 11 — PRM/KA/RERA/1251/446/PR/220923/006282: 37% complete (was 27% last quarter) • Phase 5 - W 5, 6 & 7 — PRM/KA/RERA/1251/446/PR/200923/006271: 73% complete (same as last quarter) • Phase 4 - 3, 4, 8 & 9 — PRM/KA/RERA/1251/446/PR/220923/006283: 39% complete (was 37% last quarter) Percentages are as reported by the builder to RERA.
RERA check Sobha Neopolis on Karnataka RERA today
- Promised at registration
- Dec 2031
- RERA date now
- Dec 2031
- Built (latest filing)
- 52%
Source: Karnataka RERA, via the Sobha Neopolis RERA record.
0 comments
Loading comments…