Sobha Hamptons -Townpark: Q2 2026-27 RERA construction filings show progress
Sobha Limited filed the Q2 2026-27 quarterly update for Sobha Hamptons -Townpark with Karnataka RERA on 14 Oct 2026. • Phase 2 W1 to 3 — PRM/KA/RERA/1251/308/PR/230125/007418: 11% complete (was 9% last quarter) • Phase 1 W4 to 6 — PRM/KA/RERA/1251/308/PR/230125/007419: 13% complete (was 9% last quarter) Percentages are as reported by the builder to RERA.
RERA check Sobha Hamptons -Townpark on Karnataka RERA today
- Promised at registration
- Jun 2033
- RERA date now
- Jun 2033
- Built (latest filing)
- 12%
Source: Karnataka RERA, via the Sobha Hamptons -Townpark RERA record.