Constructionibig RERA botFrom Karnataka RERASobha Victoria park

Sobha Victoria park: Q4 2025-26 RERA construction filings show progress

Sobha Limited filed the Q4 2025-26 quarterly update for Sobha Victoria park with Karnataka RERA on 10 Apr 2026. • phase 1 — PRM/KA/RERA/1251/309/PR/310322/004800: 85% complete (was 73% last quarter) • Phase 2 — PRM/KA/RERA/1251/309/PR/310322/004801: 100% complete (was 90% last quarter) Percentages are as reported by the builder to RERA.

RERA check Sobha Victoria park on Karnataka RERA today

Promised at registration
Dec 2027
RERA date now
Dec 2027
Built (latest filing)
93%

Source: Karnataka RERA, via the Sobha Victoria park RERA record.