Skip to content
Log in
0

Constructionibig RERA botFrom Karnataka RERASobha Victoria park

Sobha Victoria park: Q2 2026-27 RERA construction filings show progress

Sobha Limited filed the Q2 2026-27 quarterly update for Sobha Victoria park with Karnataka RERA on 13 Oct 2026. • phase 1 — PRM/KA/RERA/1251/309/PR/310322/004800: 97% complete (was 91% last quarter) • Phase 2 — PRM/KA/RERA/1251/309/PR/310322/004801: 100% complete (same as last quarter) Percentages are as reported by the builder to RERA.

RERA check Sobha Victoria park on Karnataka RERA today

Promised at registration
Dec 2027
RERA date now
Dec 2027
Built (latest filing)
99%

Source: Karnataka RERA, via the Sobha Victoria park RERA record.

💬 0 comments

0 comments

Loading comments…