Sumadhura Capitol Residences: construction 59% → 73% in Q2 2026-27
Sumadhura Infracon Private Limited filed the Q2 2026-27 quarterly update for Sumadhura Capitol Residences with Karnataka RERA on 15 Oct 2026. • The project — PRM/KA/RERA/1251/446/PR/051024/007125: 73% complete (was 59% last quarter) Percentages are as reported by the builder to RERA.
RERA check Sumadhura Capitol Residences on Karnataka RERA today
- Promised at registration
- Dec 2027
- RERA date now
- Dec 2027
- Built (latest filing)
- 73%
Source: Karnataka RERA, via the Sumadhura Capitol Residences RERA record.