Skip to content
Log in

After The Rain-Phase Iib: owners, reviews and RERA updates

Bellary Road (Airport Road) · Total Environment Building Systems — questions, discussions and every RERA change

  • Project community
  • RERA-checked
💬 Discussions
61% builtRERA date Aug 2026, was Nov 2024

Questions for After The Rain-Phase Iib owners and buyers

Answer anonymously

More questions for all Total Environment Building Systems owners (possession on time, quality, maintenance, loans): i/total-environment-building-systems

Discussions

No discussions about After The Rain-Phase Iib yet. Visited the site, booked, or moved in? Start one.

RERA updates

From Karnataka RERA

Complaints and reviews

Built (latest RERA filing)
61%
RERA date now (was Nov 2024)
Aug 2026
RERA complaints
1 (0 open)
Verified reviews
None yet
  • delay in possession1

Questions buyers ask

Is After The Rain-Phase Iib delayed?

Its RERA completion date moved from Nov 2024 to Aug 2026 (21 months).

How much of After The Rain-Phase Iib is built?

61%, as the builder reported in its latest quarterly filing to RERA.

Are there complaints against After The Rain-Phase Iib?

1 on Karnataka RERA, 0 still open; most about delay in possession.

After The Rain-Phase Iib reviews: are they real?

None yet. Bought here? Write a verified review.

Delay
check