Adarsh Stratuss Phase 1
2 & 3 BHK apartments by M/s Adarsh Developers · Sarakkikere, JP Nagar, Bengaluru
Sarakkikere, JP Nagar, BengaluruOpen on Google Maps (opens in a new tab)
- Under construction
- RERA registered
- RERA not updated: completion promised Nov 2025; no extension or completion filed
- residential
Price: Price on request
Bedroom interior Artist’s impression · © M/s Adarsh Developers · Source ↗ (opens in a new tab)
Adarsh Stratuss Phase 1 at a glance
- Possession (RERA)Nov 2025 Date passedWas Feb 2024 · Karnataka RERA
- Construction75% built · on pace for Dec 2027 24 mo after RERA dateRERA filing to 31 Dec 2025; estimate from average pace
- Homes booked50 of 108 (46%)RERA update · as on 31 Dec 2025
- RERA complaints (project)15 complaintsKarnataka RERA · as on 13 Oct 2026
- Approvals filed1 of 9 on RERAKarnataka RERA uploads · 13 Oct 2026
- Nearest metroJaya Prakash Nagar · 1.47 kmstraight line · OpenStreetMap, 5 Oct 2026
- Airport driveapprox. 144 min at peak35.56 km straight line · estimate
- Nearest lakeSarakki Kere · 494 mFrom the RERA map point · OpenStreetMap, 5 Oct 2026
Project summary
Adarsh Stratuss Phase 1 is a residential project by M/s Adarsh Developers in Sarakkikere, Bengaluru with 108 homes, registered with Karnataka RERA. The completion date on RERA is 28 Nov 2025.
Facts collected on 13 Oct 2026 from public records — each linked to its source. Free for buyers. If you book through us, the builder pays us a commission.
Adarsh Stratuss Phase 1 buyers’ group: join to ask for a group price
No one has joined yet. Be one of the first 10 buyers in this group — the founding members.
Join free. When enough buyers have joined, our agent partner asks M/s Adarsh Developers for a group price — for example a lower price, an easier payment plan or waived charges. Nothing is promised: you see what the builder offers and book directly with the builder if you want to. Free for buyers. If you book through us, the builder pays us a commission.
- Gathering buyers
- Talking to the builder
- Group offer
- Group site visit
- Booking
0 buyers have joined · 0 committed
Committed buyers have confirmed their budget, home type and timeline with us on a call; builders negotiate with them. Joining is free and never obliges you to buy.
Join the Adarsh Stratuss Phase 1 buyers’ groupHow group buying works
See it for yourself
Visit the site with our team, or get a call to clear your questions. Free, no obligation.
Key facts: home types, towers, land and possession
- Home types
- 2 BHK, 3 BHK
- Carpet area
- 969 – 1,745 sq ft
- Towers
- 1
- Floors
- 13
- Total homes
- 108
- Land
- 1.7 acres
- Possession (extended)
- Nov 2025
- Built (RERA update)
- 75%
Adarsh Stratuss Phase 1 RERA number and registration details
- RERA number
- PRM/KA/RERA/1251/310/PR/200305/003328
- Registered on
- 5 Mar 2020
- Promised completion
- 28 Feb 2024
- Extended to
- 28 Nov 2025
- RERA status
- New launch
- Homes booked
- 50 of 108 as on
- Price
- Not found in public records yet: price
- Project type
- Residential
Towers and blocks (RERA filing)
| Tower | Floors | Basements | Homes |
|---|---|---|---|
| Adarsh Stratuss Phase 1 | 13 | 2 | 54 |
A dash (—) means the filing did not state that value.
Summary in plain English
Adarsh Stratuss Phase 1 is a residential project by M/s Adarsh Developers in Sarakkikere, Bengaluru South with 108 homes in a single 13-storey tower. The project was registered with RERA on 5 March 2020 and has a completion date of 28 November 2025.
Written by AI from the RERA record above on 13 Oct 2026. Every number in it was checked against that record; if anything differs, the record wins.
Open space, home loans, escrow and other details
- Open space
- 83.9% of land
- Water and power
- Not found in public records yet: water and power
- Home loans: approved banks
- Not found in public records yet: bank approvals
- Payment plans
- Not found in public records yet: payment plans
- Maintenance
- Not found in public records yet: maintenance
- Car parking
- Not found in public records yet: car parking charge
- Escrow bank (RERA)
- HDFC, Richmond Road Branch
- Project cost declared to RERA
- ₹143 Cr
Open area as a share of the land, from the areas filed with RERA (includes driveways and landscaped areas).
Amenities
Adarsh Stratuss Phase 1 location and address
- Address
- Khata NO.1224,Survey no 18 / 2A / 1, Sarakkikere Village, Uttarahalli Hobli , Ward no 187.BANGALORE - 560078
- Village (RERA)
- Sarakkikere
- Locality
- JP NagarAlso known as J P Nagar, Jayaprakash Nagar
- City
- Bengaluru
- State
- Karnataka
- Coordinates
- 12.90255, 77.58572
Distances to landmarks
Not found in public records yet: landmarksAbout JP Nagar
Not found in public records yet: locality factsCommute times to tech parks and the airport
| To | Straight line | Peak-hour drive (estimate) |
|---|---|---|
| KSR Bengaluru City railway station (Majestic)Map point on OpenStreetMap (opens in a new tab) | 8.59 km | approx. 35 min |
| Electronic City Phase 1Map point on OpenStreetMap (opens in a new tab) | 10.41 km | approx. 42 min |
| Outer Ring Road tech corridor (RMZ Ecospace, Bellandur)Map point on OpenStreetMap (opens in a new tab) | 10.62 km | approx. 43 min |
| Manyata Tech ParkMap point on OpenStreetMap (opens in a new tab) | 16.61 km | approx. 67 min |
| ITPL, Whitefield (main gate)Map point on OpenStreetMap (opens in a new tab) | 19 km | approx. 77 min |
| Kempegowda International AirportMap point on OpenStreetMap (opens in a new tab) | 35.56 km | approx. 144 min |
How we calculate
Straight line: from the project’s map point on RERA to the destination’s point on OpenStreetMap.
Peak-hour drive is a rough estimate, not a route: straight line × 1.35 for the road network, at 20 km/h. Real times vary a lot with the route and the hour.
Sources:Source (openstreetmap.org) (opens in a new tab)How we calculate this
Schools and hospitals nearby
Within 2 km
- 70Schools and colleges48 schools, 9 colleges, 13 kindergartens
- 71Hospitals and clinics39 hospitals, 32 clinics
Nearest schools and colleges
- CMS Business School, Jain University · 0.08 km
- Image School J P Nagar, Jaraganahalli 2 · 0.24 km
- Royal High School · 0.29 km
Nearest hospitals and clinics
- M N Speciality Clinic · 0.16 km
- Sri Balaji Speciality Clinic & Diagnostic Center · 0.23 km
- Saphire Heart Care · 0.24 km
Places as mapped on OpenStreetMap (amenity=school, college, kindergarten, university; hospital, clinic), counted within 2 km in a straight line of the RERA map point. Volunteers map these, so some places may be missing or closed. Places data © OpenStreetMap contributors, extract of 5 Oct 2026.
Nearest metro station and railway
- Jaya Prakash Nagar (ಜೆಪಿ ನಗರ)Open now — nearest operating metro station1.47 km
- Krishnadevaraya Halt (ಕೃಷ್ಣದೇವರಾಯ)Nearest railway station7.96 km
Straight-line distances from the RERA map point to the station points mapped on OpenStreetMap; status (open or under construction) as tagged there. Places data © OpenStreetMap contributors, extract of 5 Oct 2026.
Lake and lake-buffer check
The nearest mapped lake is Sarakki Kere, 494 m from the project’s RERA map point.
The site boundary is not published as a shape, so its nearest edge can be closer than this point. Whether any building sits inside a lake buffer can only be checked on the approved plan.
- Sarakki Kere on OpenStreetMap (opens in a new tab) (ಸರಕ್ಕಿ ಕೆರೆ)494 m
- Puttenhalli Lake on OpenStreetMap (opens in a new tab) (ಪುಟ್ಟೇನಹಳ್ಳಿ ಕೆರೆ)1,217 m
- Chunchagatta Lake on OpenStreetMap (opens in a new tab) (ಚುಂಚಘಟ್ಟ ಕೆರೆ)1,677 m
The buffer rule
Bengaluru’s lake buffer rule has changed over time: the National Green Tribunal ordered a 75 m buffer in May 2016; the Supreme Court set that order aside on 5 March 2019, leaving the 30 m buffer of the Revised Master Plan 2015. Check the current rule and the approved plan before relying on either number.
- LiveLaw: SC sets aside NGT order enlarging buffer zones (2019) (livelaw.in) (opens in a new tab)
- Citizen Matters: Shrinking lake buffers (citizenmatters.in) (opens in a new tab)
Shortest distance from the RERA map point to the mapped water edge (OpenStreetMap water polygons tagged lake or reservoir, or named lake/kere/tank). Mapped shorelines can differ from the revenue-record boundary of a lake. Places data © OpenStreetMap contributors, extract of 5 Oct 2026.
Sources:Source (openstreetmap.org) (opens in a new tab)Source (livelaw.in) (opens in a new tab)Source (citizenmatters.in) (opens in a new tab)How we calculate this
Satellite time-lapse of the site
Satellite photos load when you scroll to them.
Photos from Esri World Imagery Wayback, centred on the project’s map point; dates are the capture dates in Esri’s metadata. Loaded from Esri when you scroll here.
Sources:Source (livingatlas.arcgis.com) (opens in a new tab)
Adarsh Stratuss Phase 1 home types and carpet areas
Floor plans and brochure not published? The builder shares them only on request. We’ll get the brochure, floor plans and current price list for you, free.
Get brochure, floor plans & price| Home type | Carpet area | Homes |
|---|---|---|
| 2 BHK | 970 – 1,024 sq ft | 4 |
| 2 BHK type 1 | 969 sq ft | 2 |
| 2 BHK type 2 | 1,023 sq ft | 2 |
| 3 BHK | 1,650 – 1,745 sq ft | 50 |
| 3 BHK type 1 | 1,668 sq ft | 1 |
| 3 BHK type 2 | 1,668 sq ft | 12 |
| 3 BHK type 3 | 1,647 sq ft | 13 |
| 3 BHK type 4 | 1,658 sq ft | 13 |
| 3 BHK type 5 | 1,744 sq ft | 1 |
| 3 BHK type 6 | 1,744 sq ft | 1 |
| 3 BHK type 7 | 1,744 sq ft | 9 |
Home types, counts and carpet areas as filed with Karnataka RERA (carpet area, not super built-up).
We have not collected floor-plan drawings; the builder’s sales team can share them.
Adarsh Stratuss Phase 1 possession date and construction status
Promoter’s quarterly update to RERA for Q3 2025-26, submitted 2026-01-30.
Units sold and unsold, from RERA (Q3 2025-26)
| Type | Homes | Booked | Available |
|---|---|---|---|
| 2 BHK | 4 | 0 | 4 |
| 3 BHK | 50 | 50 | 0 |
As reported by the promoter in the quarterly update to RERA, not verified by us.
Timeline
- 28 Feb 2020Project start date given to RERA
- 5 Mar 2020Registered with Karnataka RERA
- 28 Feb 2024Completion date given at registration
- 28 Nov 2024Covid Extension: completion date moved to this date
- 28 Nov 2025Section 6 Extension: completion date moved to this date
Construction pace from RERA quarterly filings
At the average pace so far, construction would reach 100% around Dec 2027 — about 24 months after the completion date on RERA (28 Nov 2025).
- Filed on RERA
- Average pace since start
- RERA completion date
Quarterly filings
| Quarter | Filed on | Built | Homes booked |
|---|---|---|---|
| Q3 2025-26to 31 Dec 2025 | 30 Jan 2026 | 75% | 50 of 54 |
How we calculate
Average pace = % built ÷ months since the start date in the RERA record. Here: 75% ÷ 70.1 months (28 Feb 2020 to 31 Dec 2025) = 1.1% a month.
Estimated finish = latest filing date + (100 − % built) ÷ pace = 31 Dec 2025 + 25 ÷ 1.1 = 23.4 months → Dec 2027. This is an estimate, not a date from the builder or RERA.
A straight line is a simplification: the builder reports one overall %, which mixes excavation, structure and finishing, and work rarely moves at a constant speed. The % values are the promoter’s own figures filed with RERA, not checked by us. Promoter’s quarterly update to RERA for Q3 2025-26, submitted 2026-01-30.
Sources:Source (rera.karnataka.gov.in) (opens in a new tab)How we calculate this
Approvals and documents checklist
| Approval | Authority | Source |
|---|---|---|
| Building plan | BBMP - Bruhat Bengaluru Mahanagara Palike | Source (rera.karnataka.gov.in) (opens in a new tab) |
Documents uploaded to RERA
- Building or layout plan · Approved drawings from the planning authorityFiled on RERA ✓ — scanned copy uploaded; number and date not read yet
- Commencement certificate · Permission to start buildingNot on RERA yet
- Environment clearance · SEIAA KarnatakaNot on RERA yet
- Fire NOC · Karnataka Fire and Emergency ServicesNot on RERA yet
- Pollution board consent · KSPCBNot on RERA yet
- Water and sewerage · BWSSBNot on RERA yet
- Electricity · BESCOMNot on RERA yet
- Height clearance · Airports Authority of IndiaNot on RERA yet
- Occupancy certificate (OC) · Issued only when the building is finishedNot on RERA yet — expected at completion
From the documents the promoter uploaded to Karnataka RERA, collected 13 Oct 2026. “Filed” means a document is on RERA — we have not checked its contents or validity. Not every approval applies to every project (for example, smaller projects may not need an environment clearance). The project page on RERA lists each upload.
Adarsh Stratuss Phase 1 RERA complaints
15 complaints as on Source (rera.karnataka.gov.in) (opens in a new tab)
15 rows: rera complaints. Scroll inside the table to see them all.
| Complaint ref | Filed | Subject | Status | Source |
|---|---|---|---|---|
| 00921/2026 | 29 Jul 2026 | Delivery of possession and delay period interest for failure to deliver possession as per agreed date in the agreement | Under enquiry | Source (rera.karnataka.gov.in) (opens in a new tab) |
| 00781/2026 | 3 Jul 2026 | Delivery of possession and delay period interest for failure to deliver possession as per agreed date in the agreement | Under enquiry | Source (rera.karnataka.gov.in) (opens in a new tab) |
| 00780/2026 | 3 Jul 2026 | Delivery of possession and delay period interest for failure to deliver possession as per agreed date in the agreement | Under enquiry | Source (rera.karnataka.gov.in) (opens in a new tab) |
| 00773/2026 | 2 Jul 2026 | Delivery of possession and delay period interest for failure to deliver possession as per agreed date in the agreement | Under enquiry | Source (rera.karnataka.gov.in) (opens in a new tab) |
| 00723/2026 | 23 Jun 2026 | Failure to Deliver Possession of the Apartment Within the Agreed Timeline and Non-Payment of Delay Compensation as per RERA Provisions | Under enquiry | Source (rera.karnataka.gov.in) (opens in a new tab) |
| 00681/2026 | 9 Jun 2026 | Delay in handing over possession and compensation | Under enquiry | Source (rera.karnataka.gov.in) (opens in a new tab) |
| 00606/2026 | 27 May 2026 | Delay in handing over possession and compensation | Under enquiry | Source (rera.karnataka.gov.in) (opens in a new tab) |
| 00597/2026 | 26 May 2026 | Deplay Comphensation as per RERA Section 18 for Unit A024-BA-A301 | Under enquiry | Source (rera.karnataka.gov.in) (opens in a new tab) |
| 00602/2026 | 26 May 2026 | Delay in handing over possession and compensation | Under enquiry | Source (rera.karnataka.gov.in) (opens in a new tab) |
| 00576/2026 | 25 May 2026 | Failure to Deliver Possession of the Apartment Within the Agreed Timeline and Non-Payment of Delay Compensation as per RERA Provisions. | Under enquiry | Source (rera.karnataka.gov.in) (opens in a new tab) |
| 00570/2026 | 21 May 2026 | Delay in possession and failure to pay compensation as per the agreement/MoM. | Under enquiry | Source (rera.karnataka.gov.in) (opens in a new tab) |
| 00564/2026 | 20 May 2026 | Failure to Deliver Possession of the Apartment Within the Agreed Timeline and Non-Payment of Delay Compensation as per RERA Provisions. | Under enquiry | Source (rera.karnataka.gov.in) (opens in a new tab) |
| 00567/2026 | 20 May 2026 | Delayed completion of Project and handover and refusal to abide by penalty compensation as per agreement | Under enquiry | Source (rera.karnataka.gov.in) (opens in a new tab) |
| 00566/2026 | 20 May 2026 | Failure to Deliver Possession of the Apartment Within the Agreed Timeline and Non-Payment of Delay Compensation as per RERA Provisions | Under enquiry | Source (rera.karnataka.gov.in) (opens in a new tab) |
| 00563/2026 | 20 May 2026 | Delay in handing over possession and compensation | Under enquiry | Source (rera.karnataka.gov.in) (opens in a new tab) |
Court and consumer cases
We list case numbers, courts and outcomes only — never names of private individuals.
About M/s Adarsh Developers
- Promoter type
- Partnership Firm
- Projects on this site
- 5
- RERA complaints against promoter
- 24
- Company number (CIN)
- Not found in public records yet: CIN
From Karnataka RERA, as collected so far (13 Oct 2026). Complaints are those RERA lists against this promoter across all its projects.
M/s Adarsh Developers’s RERA recordM/s Adarsh Developers delivery record
- 5Projects in Bengaluru on RERA5 approved registrations under M/s Adarsh Developers in Bengaluru Urban and Rural. Source (rera.karnataka.gov.in) (opens in a new tab)
- 929Homes registeredAs stated in each registrations.
- 24RERA complaints17 open, 7 disposed. as on Source (rera.karnataka.gov.in) (opens in a new tab)
- 25.8Complaints per 1,000 homes24 complaints ÷ 929 homes in its 5 registrations on Karnataka RERA in Bengaluru.
What the complaints are about
24 complaint subjects as written on RERA, as on . Each subject is sorted into one group by keywords (first match wins: delay, refund, registration, quality, litigation, association); one complaint often raises several issues. Source (rera.karnataka.gov.in) (opens in a new tab)
Sources:Source (rera.karnataka.gov.in) (opens in a new tab)How we calculate this
What’s changed since Feb 2020
- 29 Jul 2026Complaint 00921/2026 filed with RERA: “Delivery of possession and delay period interest for failure to deliver possession as per agreed date in the agreement” — now under enquiry Source (rera.karnataka.gov.in) (opens in a new tab)
- 3 Jul 2026Complaint 00781/2026 filed with RERA: “Delivery of possession and delay period interest for failure to deliver possession as per agreed date in the agreement” — now under enquiry Source (rera.karnataka.gov.in) (opens in a new tab)
- 3 Jul 2026Complaint 00780/2026 filed with RERA: “Delivery of possession and delay period interest for failure to deliver possession as per agreed date in the agreement” — now under enquiry Source (rera.karnataka.gov.in) (opens in a new tab)
- 2 Jul 2026Complaint 00773/2026 filed with RERA: “Delivery of possession and delay period interest for failure to deliver possession as per agreed date in the agreement” — now under enquiry Source (rera.karnataka.gov.in) (opens in a new tab)
- 23 Jun 2026Complaint 00723/2026 filed with RERA: “Failure to Deliver Possession of the Apartment Within the Agreed Timeline and Non-Payment of Delay Compensation as per RERA Provisions” — now under enquiry Source (rera.karnataka.gov.in) (opens in a new tab)
- 9 Jun 2026Complaint 00681/2026 filed with RERA: “Delay in handing over possession and compensation” — now under enquiry Source (rera.karnataka.gov.in) (opens in a new tab)
- 27 May 2026Complaint 00606/2026 filed with RERA: “Delay in handing over possession and compensation” — now under enquiry Source (rera.karnataka.gov.in) (opens in a new tab)
- 26 May 2026Complaint 00597/2026 filed with RERA: “Deplay Comphensation as per RERA Section 18 for Unit A024-BA-A301” — now under enquiry Source (rera.karnataka.gov.in) (opens in a new tab)
- 26 May 2026Complaint 00602/2026 filed with RERA: “Delay in handing over possession and compensation” — now under enquiry Source (rera.karnataka.gov.in) (opens in a new tab)
- 25 May 2026Complaint 00576/2026 filed with RERA: “Failure to Deliver Possession of the Apartment Within the Agreed Timeline and Non-Payment of Delay Compensation as per RERA Provisions.” — now under enquiry Source (rera.karnataka.gov.in) (opens in a new tab)
- 21 May 2026Complaint 00570/2026 filed with RERA: “Delay in possession and failure to pay compensation as per the agreement/MoM.” — now under enquiry Source (rera.karnataka.gov.in) (opens in a new tab)
- 20 May 2026Complaint 00564/2026 filed with RERA: “Failure to Deliver Possession of the Apartment Within the Agreed Timeline and Non-Payment of Delay Compensation as per RERA Provisions.” — now under enquiry Source (rera.karnataka.gov.in) (opens in a new tab)
- 20 May 2026Complaint 00567/2026 filed with RERA: “Delayed completion of Project and handover and refusal to abide by penalty compensation as per agreement” — now under enquiry Source (rera.karnataka.gov.in) (opens in a new tab)
- 20 May 2026Complaint 00566/2026 filed with RERA: “Failure to Deliver Possession of the Apartment Within the Agreed Timeline and Non-Payment of Delay Compensation as per RERA Provisions” — now under enquiry Source (rera.karnataka.gov.in) (opens in a new tab)
- 20 May 2026Complaint 00563/2026 filed with RERA: “Delay in handing over possession and compensation” — now under enquiry Source (rera.karnataka.gov.in) (opens in a new tab)
- 30 Jan 2026Quarterly update filed for Q3 2025-26: 75% built, 50 of 54 homes booked Source (rera.karnataka.gov.in) (opens in a new tab)
- 28 Nov 2025Completion date extended to 28 Nov 2025 Source (rera.karnataka.gov.in) (opens in a new tab)
- 5 Mar 2020Registered with Karnataka RERA (PRM/KA/RERA/1251/310/PR/200305/003328); completion date 28 Feb 2024 Source (rera.karnataka.gov.in) (opens in a new tab)
- 28 Feb 2020Project start date in the RERA record Source (rera.karnataka.gov.in) (opens in a new tab)
Newest first. When the RERA crawl sees a new filing, complaint or extension, it is added here with its date.
Home loan EMI calculator
- Monthly EMI
- —
- Down payment
- —
- Loan amount
- —
- Total interest
- —
A calculation only, from the numbers you enter — not a loan offer.
All-in cost: GST, registration and other charges
The calculator loads when you scroll to it.
Assumptions
- Base price: the builder’s price is not published in a form we could collect — enter it from the cost sheet.
- GST 5% on the base price and charges — the usual rate for an under-construction home that is not “affordable housing” (1%).
- Stamp duty about 5.6% and registration 2% — the Karnataka rule (registration was raised from 1% to 2% on 31 Aug 2025). Calculated on the agreement value.
- Car parking, other charges and the maintenance deposit are not in the public record we collect; enter them from the builder’s cost sheet.
- Loan on the agreement value (banks usually lend up to 75–90%); EMI is the standard reducing-balance formula. Example rate only — use your bank’s quote.
Adarsh Stratuss Phase 1 FAQs
What is the completion date for Adarsh Stratuss Phase 1?
The current completion date on RERA is 28 November 2025. This date was extended from 28 February 2024 due to Covid Extension and then further extended under Section 6.
What home types are available in Adarsh Stratuss Phase 1?
The project offers 2 BHK and 3 BHK homes with carpet areas ranging from 969 sq ft to 1,744 sq ft.
How many homes are in Adarsh Stratuss Phase 1?
There are 108 homes in total across one tower.
What is the RERA registration number for Adarsh Stratuss Phase 1?
The RERA registration number is PRM/KA/RERA/1251/310/PR/200305/003328.
How many homes have been booked in Adarsh Stratuss Phase 1?
As of Q3 2025-26 (quarter ended 31 December 2025), 50 homes have been booked out of 54 homes in the booking table.
What is the construction progress for Adarsh Stratuss Phase 1?
As of Q3 2025-26, the project is 75% complete.
How many RERA complaints have been filed against Adarsh Stratuss Phase 1?
There are 15 RERA complaints on this project.
Where is Adarsh Stratuss Phase 1 located?
The project is located in Sarakkikere, Bengaluru South taluk, Bengaluru Urban district with PIN code 560001.
What is the builder's record on RERA?
M/s Adarsh Developers has 24 complaints against it across all projects and has 9 projects registered on our Bengaluru records.
When was Adarsh Stratuss Phase 1 registered with RERA?
The project was registered on 5 March 2020.
Written by AI from the RERA record above on 13 Oct 2026. Answers use only that record; check them against the source before you decide.
Questions about Adarsh Stratuss Phase 1
No questions published yet. Ask the first one: you get an instant answer from this page’s public record, and our team follows up on anything the record does not show.
Bought a home from M/s Adarsh Developers? Review the builder.
Reviews of M/s Adarsh Developers by verified buyers
No verified reviews of M/s Adarsh Developers yet. If you bought a home from them, your review helps other buyers.
How reviews work: only buyers and owners can review; we confirm each purchase by phone before publishing, publish positive and negative reviews alike, never accept payment for reviews, and the builder may reply.
Similar projects within 5 km
| Project | Distance | Homes | Possession (RERA) | Built | Complaints | Price |
|---|---|---|---|---|---|---|
| MGR Windsor GardensSri Manjunatha Developers | 0.5 km | 36 | Dec 2025 | — | 0 | Not collected |
| StraatosphereEverfine Buildcon LLP | 0.8 km | 32 | Nov 2028 | 46% | 0 | Not collected |
| ADARSH LAKE RESERVA Phase 1M/s Adarsh Developers | 1.2 km | 162 | Dec 2027 | 0% | 0 | Not collected |
| Shriram Southern CrestShriprop Projects Private Limited | 1.5 km | 826 | Oct 2026extended | — | 20 | Not collected |
| Navin'S Antheia PoetryNavin Housing & Properties Pvt Ltd | 1.7 km | 42 | Jan 2028 | 21% | 0 | Not collected |
| Vaishnavi At-One Krishna BrindavanVaishnavi At-One Infrastructure LLP | 2.1 km | 359 | Jun 2030 | 28% | 0 | Not collected |
Projects of the same kind within 5 km in a straight line of this project’s RERA map point, nearest first. % built is the promoter’s latest quarterly figure on RERA (shown for single-registration projects); prices are from the builder’s own website where we found one.
Sources and last checked dates
Collected on 13 Oct 2026 by AI research agents reading public pages. Facts are written in our own words. Not found yet: price; court cases; landmarks; specifications; news.
How to check on RERA: On rera.karnataka.gov.in/viewAllProjects, type the registration number in 'Registration No', press Search, then click the 'View Project Details' icon. Complaints open from the 'Complaints / Litigation' icon in the same row. Registration number: PRM/KA/RERA/1251/310/PR/200305/003328.
- RERA record last checked: 13 Oct 2026
- Last change in the record (registration, quarterly filing or complaint): 29 Jul 2026
How this page is made: software builds it from public records (Karnataka RERA filings, OpenStreetMap, the builder’s own website). AI is used only to read filings into fields and to write the plain-English summary and FAQ answers, which are checked against the record. Facts are checked automatically against the RERA filing. Methodology · How we earn · Report an error
More new projects in JP Nagar
Jaranganahalli, JP NagarUnder constructionRERA registeredBuyers’ group openShriram Southern Crest
by Shriprop
Price: Price on requestGet brochure & price →
- 1 BHK, 2 BHK, 3 BHK
- 694 – 2,406 sq ft
- Oct 2026 (extended)
RERA not updated since promised Oct 2026 · 2 phases on RERA · 826 homes · 20 RERA complaints
Be one of the first 10 buyers in this groupFounding members — it’s free
Join group for Shriram Southern Crest
Bilekalli, JP NagarUnder constructionRERA registeredBuyers’ group openNavin'S Antheia Poetry
by Navin Housing & Properties
Price: Price on requestGet brochure & price →
- 2 BHK, 3 BHK, 3.5 BHK, 4 BHK
- 1,090 – 2,249 sq ft
- Jan 2028
42 homes
Be one of the first 10 buyers in this groupFounding members — it’s free
Join group for Navin'S Antheia Poetry
Jaraganahalli, JP NagarUnder constructionRERA registeredBuyers’ group openVaishnavi At-One Krishna Brindavan
by Vaishnavi At-One Infrastructure
Price: Price on requestGet brochure & price →
- 2 BHK, 3 BHK, 4 BHK
- 1,007 – 1,663 sq ft
- Jun 2030
359 homes
Be one of the first 10 buyers in this groupFounding members — it’s free
Join group for Vaishnavi At-One Krishna Brindavan