Blue Meadows
2 & 3 BHK apartments by Yuva Infinity Developers · Varthur, Bengaluru
Varthur, BengaluruOpen on Google Maps (opens in a new tab)
- Under construction
- RERA registered
- residential
Price: Price on request
Site photo filed with Karnataka RERA Karnataka RERA filing · Source ↗ (opens in a new tab)
Blue Meadows at a glance
- Possession (RERA)Dec 2025 Date passedWas Dec 2027 · Karnataka RERA
- Construction75% built · on pace for May 2027RERA filing to 30 Sep 2026 (Phase 2); estimate from average pace
- RERA complaints (project)None listedKarnataka RERA · as on 20 Oct 2026
- Approvals filed4 of 9 on RERAKarnataka RERA uploads · 4 Oct 2026
- Nearest metroNallurahalli · 4.56 kmstraight line · OpenStreetMap, 5 Oct 2026
- Airport driveapprox. 119 min at peak29.39 km straight line · estimate
- Nearest lakeVarthur Lake · 651 mFrom the RERA map point · OpenStreetMap, 5 Oct 2026
Project summary
Blue Meadows is a residential project by Yuva Infinity Developers in Varthur, Bengaluru with 304 homes, registered with Karnataka RERA. The completion date on RERA is 31 Dec 2025. It is registered in 2 phases.
Facts collected on 20 Oct 2026 from public records — each linked to its source. Free for buyers. If you book through us, the builder pays us a commission.
Blue Meadows buyers’ group: join to ask for a group price
No one has joined yet. Be one of the first 10 buyers in this group — the founding members.
Join free. When enough buyers have joined, our agent partner asks Yuva Infinity Developers for a group price — for example a lower price, an easier payment plan or waived charges. Nothing is promised: you see what the builder offers and book directly with the builder if you want to. Free for buyers. If you book through us, the builder pays us a commission.
- Gathering buyers
- Talking to the builder
- Group offer
- Group site visit
- Booking
0 buyers have joined · 0 committed
Committed buyers have confirmed their budget, home type and timeline with us on a call; builders negotiate with them. Joining is free and never obliges you to buy.
Join the Blue Meadows buyers’ groupHow group buying works
See it for yourself
Visit the site with our team, or get a call to clear your questions. Free, no obligation.
Key facts: home types, towers, land and possession
- Home types
- 2 BHK, 2.5 BHK, 3 BHK
- Carpet area
- 717 – 1,115 sq ft
- Towers
- 2
- Floors
- 3
- Total homes
- 304
- Land
- 4.26 acres
- Possession (extended)
- Dec 2025
- Built (RERA update)
- Not found in public records yet: construction progress
Blue Meadows RERA number and registration details
- RERA number
- PRM/KA/RERA/1251/446/PR/150323/005798
- Registered on
- 15 Mar 2023
- Promised completion
- 31 Dec 2027
- Extended to
- 31 Dec 2025
- RERA status
- Under construction
- Homes booked
- Not found in public records yet: homes booked
- Price
- Not found in public records yet: price
- Project type
- Residential
2 RERA registrations (one per phase) are shown together on this page; dates above are the latest across phases.
Phases and RERA numbers
| Phase | RERA number | Promised completion | Homes | Status | Source |
|---|---|---|---|---|---|
| Main registration | PRM/KA/RERA/1251/446/PR/150323/005798 | 31 Dec 2024Extended to 31 Dec 2025 | 120 | Completed | Source (rera.karnataka.gov.in) (opens in a new tab) |
| Phase 2 | PRM/KA/RERA/1251/446/PR/280225/007531 | 31 Dec 2027 | 184 | Under construction | Source (rera.karnataka.gov.in) (opens in a new tab) |
Towers and blocks (RERA filing)
| Tower | Phase | Floors | Basements | Homes |
|---|---|---|---|---|
| BLUE MEADOWS | Main registration | 3 | 0 | 120 |
| C | Phase 2 | 3 | 1 | 184 |
A dash (—) means the filing did not state that value.
Summary in plain English
Blue Meadows is a residential project by Yuva Infinity Developers in Varthur, Bengaluru East. The project has 304 homes across 2 phases in 2 towers, with completion dates of 31 December 2025 for Phase 1 and 31 December 2027 for Phase 2.
Written by AI from the RERA record above on 20 Oct 2026. Every number in it was checked against that record; if anything differs, the record wins.
Open space, home loans, escrow and other details
- Open space
- Not found in public records yet: open space
- Water and power
- Water source filed with RERA: Local Authority, BoreWell,BWSSB
- Home loans: approved banks
- Not found in public records yet: bank approvals
- Payment plans
- Not found in public records yet: payment plans
- Maintenance
- Not found in public records yet: maintenance
- Car parking
- Not found in public records yet: car parking charge
- Escrow bank (RERA) · Main registration
- Axis Bank, Whitefield
- Escrow bank (RERA) · Phase 2
- Axis Bank, Whitefield
Amenities
- Electricity
- Club House
- Swimming Pool
- Gym
- Parks
- CCTV Surveillance
- Community Hall
- Indoor Sports facility
- Power Backup
- Water and Sanitation
Amenities and internal works as filed by the promoter with Karnataka RERA; we have not visited the site.
Blue Meadows location and address
- Address
- Sy. No's-12/9, 12/13, 12/14, 12/15, Katha No - 4044 , Muncipal No - 327, Varthur Village, Varthur Hobli, Ward No-149, Bangalore , Bengaluru East , Bengaluru Urban, Karnataka - 560087
- Village (RERA)
- Varthur
- Locality
- Varthur
- PIN code
- 560087
- City
- Bengaluru
- State
- Karnataka
- Coordinates
- 12.93888, 77.74120
Distances to landmarks
Not found in public records yet: landmarksAbout Varthur
Not found in public records yet: locality factsCommute times to tech parks and the airport
| To | Straight line | Peak-hour drive (estimate) |
|---|---|---|
| ITPL, Whitefield (main gate)Map point on OpenStreetMap (opens in a new tab) | 5.43 km | approx. 22 min |
| Outer Ring Road tech corridor (RMZ Ecospace, Bellandur)Map point on OpenStreetMap (opens in a new tab) | 6.72 km | approx. 27 min |
| Electronic City Phase 1Map point on OpenStreetMap (opens in a new tab) | 12.91 km | approx. 52 min |
| Manyata Tech ParkMap point on OpenStreetMap (opens in a new tab) | 17.9 km | approx. 72 min |
| KSR Bengaluru City railway station (Majestic)Map point on OpenStreetMap (opens in a new tab) | 19.11 km | approx. 77 min |
| Kempegowda International AirportMap point on OpenStreetMap (opens in a new tab) | 29.39 km | approx. 119 min |
How we calculate
Straight line: from the project’s map point on RERA to the destination’s point on OpenStreetMap.
Peak-hour drive is a rough estimate, not a route: straight line × 1.35 for the road network, at 20 km/h. Real times vary a lot with the route and the hour.
Sources:Source (openstreetmap.org) (opens in a new tab)How we calculate this
Schools and hospitals nearby
Within 2 km
- 16Schools and colleges14 schools, 0 colleges, 2 kindergartens
- 22Hospitals and clinics8 hospitals, 14 clinics
Nearest schools and colleges
- Sri Chaitanya Techno School · 0.54 km
- Sri Chaitanya Future Pathways Global School Varthur · 0.58 km
- Government Urdu High School · 0.64 km
Nearest hospitals and clinics
- Urban PHC Varthuru · 0.59 km
- Sahasra Hospital · 0.61 km
- Suraksha Hospitsls · 0.61 km
Places as mapped on OpenStreetMap (amenity=school, college, kindergarten, university; hospital, clinic), counted within 2 km in a straight line of the RERA map point. Volunteers map these, so some places may be missing or closed. Places data © OpenStreetMap contributors, extract of 5 Oct 2026.
Nearest metro station and railway
- Nallurahalli (ನಲ್ಲೂರಹಳ್ಳಿ)Open now — nearest operating metro station4.56 km
- Belandur Road (ಬೆಳಂದೂರು ರಸ್ತೆ)Nearest railway station3.69 km
Straight-line distances from the RERA map point to the station points mapped on OpenStreetMap; status (open or under construction) as tagged there. Places data © OpenStreetMap contributors, extract of 5 Oct 2026.
Lake and lake-buffer check
The nearest mapped lake is Varthur Lake, 651 m from the project’s RERA map point.
The site boundary is not published as a shape, so its nearest edge can be closer than this point. Whether any building sits inside a lake buffer can only be checked on the approved plan.
- Varthur Lake on OpenStreetMap (opens in a new tab) (ವರ್ತೂರು ಕೆರೆ)651 m
- Unnamed lake (mapped on OpenStreetMap) on OpenStreetMap (opens in a new tab) 1,104 m
The buffer rule
Bengaluru’s lake buffer rule has changed over time: the National Green Tribunal ordered a 75 m buffer in May 2016; the Supreme Court set that order aside on 5 March 2019, leaving the 30 m buffer of the Revised Master Plan 2015. Check the current rule and the approved plan before relying on either number.
- LiveLaw: SC sets aside NGT order enlarging buffer zones (2019) (livelaw.in) (opens in a new tab)
- Citizen Matters: Shrinking lake buffers (citizenmatters.in) (opens in a new tab)
Shortest distance from the RERA map point to the mapped water edge (OpenStreetMap water polygons tagged lake or reservoir, or named lake/kere/tank). Mapped shorelines can differ from the revenue-record boundary of a lake. Places data © OpenStreetMap contributors, extract of 5 Oct 2026.
Sources:Source (openstreetmap.org) (opens in a new tab)Source (livelaw.in) (opens in a new tab)Source (citizenmatters.in) (opens in a new tab)How we calculate this
Satellite time-lapse of the site
Satellite photos load when you scroll to them.
Photos from Esri World Imagery Wayback, centred on the project’s map point; dates are the capture dates in Esri’s metadata. Loaded from Esri when you scroll here.
Sources:Source (livingatlas.arcgis.com) (opens in a new tab)
Blue Meadows home types and carpet areas
Documents the builder uploaded to Karnataka RERA, shown as filed. Tap a page to see it full size; the full PDF opens on the RERA website.
Approved building plan5 pages

Phase 2: Approved Building PlanFull PDF on RERA
Approved layout plan3 files

Phase 2: CDP Demarcation.pdfFull PDF on RERA 
Phase 2: SITE DEMARCATION.pdfFull PDF on RERA 
Phase 2: VILLAGE MAP Demarcation.pdfFull PDF on RERA
Floor plans and brochure not published? The builder shares them only on request. We’ll get the brochure, floor plans and current price list for you, free.
Get brochure, floor plans & price| Home type | Carpet area | Homes |
|---|---|---|
| 2 BHK | 717 – 803 sq ft | 151 |
| 2.5 BHK | 818 – 1,031 sq ft | 67 |
| 3 BHK | 723 – 1,115 sq ft | 86 |
Home types, counts and carpet areas as filed with Karnataka RERA (carpet area, not super built-up).
We have not collected floor-plan drawings; the builder’s sales team can share them.
Blue Meadows possession date and construction status
Timeline
- 1 Dec 2022Main registration: Project start date given to RERA
- 15 Mar 2023Main registration: Registered with Karnataka RERA
- 1 Nov 2024Phase 2: Project start date given to RERA
- 31 Dec 2024Main registration: Completion date given at registration
- 28 Feb 2025Phase 2: Registered with Karnataka RERA
- 31 Dec 2025Main registration: Section 6 Extension: completion date moved to this date
- 12 Feb 2026Main registration: Promoter applied to RERA for completion
- 31 Dec 2027Phase 2: Completion date given at registration
Construction pace from RERA quarterly filings (Phase 2)
At the average pace so far, construction would reach 100% around May 2027 — about 7 months before the completion date on RERA (31 Dec 2027).
At the pace between the 4 quarterly filings we have (39% → 75% in 9 months), it would be around Apr 2027 — about 9 months before the RERA date.
This project has 2 RERA registrations; the chart uses Phase 2, the one with the most quarterly filings.
- Filed on RERA
- Average pace since start
- Pace between filings (and 0% assumed at the start date)
- RERA completion date
Quarterly filings
| Quarter | Filed on | Built | Homes booked |
|---|---|---|---|
| Q2 2026-27to 30 Sep 2026 | 15 Oct 2026 | 75% | 60 of 184 |
| Q1 2026-27to 30 Jun 2026 | 15 Jul 2026 | 57% | 54 of 184 |
| Q4 2025-26to 31 Mar 2026 | 15 Apr 2026 | 50% | 43 of 184 |
| Q3 2025-26to 31 Dec 2025 | 17 Feb 2026 | 39% | 34 of 184 |
How we calculate
Average pace = % built ÷ months since the start date in the RERA record. Here: 75% ÷ 22.9 months (1 Nov 2024 to 30 Sep 2026) = 3.3% a month.
Estimated finish = latest filing date + (100 − % built) ÷ pace = 30 Sep 2026 + 25 ÷ 3.3 = 7.6 months → May 2027. This is an estimate, not a date from the builder or RERA.
Pace between filings = (75% − 39%) ÷ 9 months = 4% a month.
A straight line is a simplification: the builder reports one overall %, which mixes excavation, structure and finishing, and work rarely moves at a constant speed. The % values are the promoter’s own figures filed with RERA, not checked by us.
Sources:Source (rera.karnataka.gov.in) (opens in a new tab)How we calculate this
Approvals and documents checklist
21 rows: approvals. Scroll inside the table to see them all.
| Approval | Authority | Source |
|---|---|---|
| Building plan (Main registration) | BBMP - Bruhat Bengaluru Mahanagara Palike · No. PRJ/6739/22-23IN · dated 2022-11-05 | Source (rera.karnataka.gov.in) (opens in a new tab) |
| Land conversion (4 orders) (Main registration) | DC, Bangalore Urban · No. 334861 and 3 more · dated 2022-04-22 | Source (rera.karnataka.gov.in) (opens in a new tab) |
| Commencement Certificate (Main registration) | scan uploaded to RERA | Source (rera.karnataka.gov.in) (opens in a new tab) |
| Electricity Permission Letter (Main registration) | scan uploaded to RERA | Source (rera.karnataka.gov.in) (opens in a new tab) |
| Water Permission Letter (Main registration) | scan uploaded to RERA | Source (rera.karnataka.gov.in) (opens in a new tab) |
| Approved Layout Plan (Main registration) | scan uploaded to RERA | Source (rera.karnataka.gov.in) (opens in a new tab) |
| Approved Building/Plotting Plan (Main registration) | scan uploaded to RERA | Source (rera.karnataka.gov.in) (opens in a new tab) |
| Approved Section Of Building/Infrastructure Plan of Plotting (Main registration) | scan uploaded to RERA | Source (rera.karnataka.gov.in) (opens in a new tab) |
| Change of Land Use (Main registration) | scan uploaded to RERA | Source (rera.karnataka.gov.in) (opens in a new tab) |
| District Magistrate (Main registration) | scan uploaded to RERA | Source (rera.karnataka.gov.in) (opens in a new tab) |
| Conversion Certificate under section 95 of the KLR Act 1964 (Main registration) | scan uploaded to RERA | Source (rera.karnataka.gov.in) (opens in a new tab) |
| ESCOM/Electricity (Main registration) | scan uploaded to RERA | Source (rera.karnataka.gov.in) (opens in a new tab) |
| KWSSB/Water (Main registration) | scan uploaded to RERA | Source (rera.karnataka.gov.in) (opens in a new tab) |
| Building plan (Phase 2) | BBMP - Bruhat Bengaluru Mahanagara Palike · No. BBMP/Ad.com./MDP/0189/24-25 · dated 2024-06-07 | Source (rera.karnataka.gov.in) (opens in a new tab) |
| Land conversion (3 orders) (Phase 2) | DC Office, Bangalore · No. 576391 and 2 more · dated 2023-12-16 | Source (rera.karnataka.gov.in) (opens in a new tab) |
| Commencement Certificate (Phase 2) | scan uploaded to RERA | Source (rera.karnataka.gov.in) (opens in a new tab) |
| Approved Building Plan (Phase 2) | scan uploaded to RERA | Source (rera.karnataka.gov.in) (opens in a new tab) |
| ESCOM/Electricity (Phase 2) | scan uploaded to RERA | Source (rera.karnataka.gov.in) (opens in a new tab) |
| KWSSB/Water (Phase 2) | scan uploaded to RERA | Source (rera.karnataka.gov.in) (opens in a new tab) |
| KSPCB (Phase 2) | scan uploaded to RERA | Source (rera.karnataka.gov.in) (opens in a new tab) |
| SEIAA (Phase 2) | scan uploaded to RERA | Source (rera.karnataka.gov.in) (opens in a new tab) |
Documents uploaded to RERA (Main registration)
- Building or layout plan · Approved drawings from the planning authorityFiled on RERA ✓ — BBMP - Bruhat Bengaluru Mahanagara Palike · No. PRJ/6739/22-23IN · dated 5 Nov 2022
- Commencement certificate · Permission to start buildingFiled on RERA ✓ — scanned copy uploaded; number and date not read yet
- Environment clearance · SEIAA KarnatakaNot on RERA yet
- Fire NOC · Karnataka Fire and Emergency ServicesNot on RERA yet
- Pollution board consent · KSPCBNot on RERA yet
- Water and sewerage · BWSSBFiled on RERA ✓ — scanned copy uploaded; number and date not read yet
- Electricity · BESCOMFiled on RERA ✓ — scanned copy uploaded; number and date not read yet
- Height clearance · Airports Authority of IndiaNot on RERA yet
- Occupancy certificate (OC) · Issued only when the building is finishedNot on RERA yet
From the documents the promoter uploaded to Karnataka RERA, collected 4 Oct 2026. “Filed” means a document is on RERA — we have not checked its contents or validity. Not every approval applies to every project (for example, smaller projects may not need an environment clearance). Each phase is registered separately; this list is for the phase named above. The project page on RERA lists each upload.
Blue Meadows RERA complaints
No complaints listed on Karnataka RERA for these registrations as on Source (rera.karnataka.gov.in) (opens in a new tab)
Court and consumer cases
We list case numbers, courts and outcomes only — never names of private individuals.
About Yuva Infinity Developers
- Promoter type
- Partnership Firm
- Projects on this site
- 1
- RERA complaints against promoter
- 0
- Company number (CIN)
- Not found in public records yet: CIN
From Karnataka RERA, as collected so far (20 Oct 2026). Complaints are those RERA lists against this promoter across all its projects.
Yuva Infinity Developers’s RERA recordYuva Infinity Developers delivery record
- 1Projects in Bengaluru on RERA2 approved registrations under Yuva Infinity Developers in Bengaluru Urban and Rural. Source (rera.karnataka.gov.in) (opens in a new tab)
- 304Homes registeredAs stated in each registrations.
- 0RERA complaintsas on Source (rera.karnataka.gov.in) (opens in a new tab)
- 0Complaints per 1,000 homes0 complaints ÷ 304 homes in its 2 registrations on Karnataka RERA in Bengaluru.
- 1Completion filed on RERARegistrations where the promoter applied to RERA for completion; 1 with an occupancy certificate on RERA.
- 0 of 1Filed by the date given at registrationMedian gap 13.4 months (on-time ones count as 0). The completion application can come after handover, so this is an upper bound on lateness.
Completion filed on RERA
| Project | Date at registration | Completion filed | Gap |
|---|---|---|---|
| Blue MeadowsOC on RERA | 31 Dec 2024extended to 31 Dec 2025 | 12 Feb 2026 | 13 months after |
Measured against the completion date given at registration; many projects had RERA extensions (including the COVID-period extension), shown under the date.
Sources:Source (rera.karnataka.gov.in) (opens in a new tab)How we calculate this
What’s changed since Nov 2022
- 15 Oct 2026Phase 2: Quarterly update filed for Q2 2026-27: 75% built, 60 of 184 homes booked Source (rera.karnataka.gov.in) (opens in a new tab)
- 15 Jul 2026Phase 2: Quarterly update filed for Q1 2026-27: 57% built, 54 of 184 homes booked Source (rera.karnataka.gov.in) (opens in a new tab)
- 15 Apr 2026Phase 2: Quarterly update filed for Q4 2025-26: 50% built, 43 of 184 homes booked Source (rera.karnataka.gov.in) (opens in a new tab)
- 17 Feb 2026Phase 2: Quarterly update filed for Q3 2025-26: 39% built, 34 of 184 homes booked Source (rera.karnataka.gov.in) (opens in a new tab)
- 12 Feb 2026Main registration: Promoter applied to RERA for completion (occupancy certificate on RERA) Source (rera.karnataka.gov.in) (opens in a new tab)
- 31 Dec 2025Main registration: Completion date extended to 31 Dec 2025 Source (rera.karnataka.gov.in) (opens in a new tab)
- 28 Feb 2025Phase 2: Registered with Karnataka RERA (PRM/KA/RERA/1251/446/PR/280225/007531); completion date 31 Dec 2027 Source (rera.karnataka.gov.in) (opens in a new tab)
- 1 Nov 2024Phase 2: Project start date in the RERA record Source (rera.karnataka.gov.in) (opens in a new tab)
- 7 Jun 2024Phase 2: Building plan approved by BBMP - Bruhat Bengaluru Mahanagara Palike (No. BBMP/Ad.com./MDP/0189/24-25) Source (rera.karnataka.gov.in) (opens in a new tab)
- 15 Mar 2023Main registration: Registered with Karnataka RERA (PRM/KA/RERA/1251/446/PR/150323/005798); completion date 31 Dec 2024 Source (rera.karnataka.gov.in) (opens in a new tab)
- 1 Dec 2022Main registration: Project start date in the RERA record Source (rera.karnataka.gov.in) (opens in a new tab)
- 5 Nov 2022Main registration: Building plan approved by BBMP - Bruhat Bengaluru Mahanagara Palike (No. PRJ/6739/22-23IN) Source (rera.karnataka.gov.in) (opens in a new tab)
Newest first. When the RERA crawl sees a new filing, complaint or extension, it is added here with its date.
Home loan EMI calculator
- Monthly EMI
- —
- Down payment
- —
- Loan amount
- —
- Total interest
- —
A calculation only, from the numbers you enter — not a loan offer.
All-in cost: GST, registration and other charges
The calculator loads when you scroll to it.
Assumptions
- Base price: the builder’s price is not published in a form we could collect — enter it from the cost sheet.
- GST 5% on the base price and charges — the usual rate for an under-construction home that is not “affordable housing” (1%).
- Stamp duty about 5.6% and registration 2% — the Karnataka rule (registration was raised from 1% to 2% on 31 Aug 2025). Calculated on the agreement value.
- Car parking, other charges and the maintenance deposit are not in the public record we collect; enter them from the builder’s cost sheet.
- Loan on the agreement value (banks usually lend up to 75–90%); EMI is the standard reducing-balance formula. Example rate only — use your bank’s quote.
Blue Meadows FAQs
What is Blue Meadows and where is it located?
Blue Meadows is a residential project by Yuva Infinity Developers in Varthur, Bengaluru East, PIN code 560087.
How many homes are in Blue Meadows?
The project has 304 homes: Phase 1 has 120 homes and Phase 2 has 184 homes.
What home types are available in Blue Meadows?
Phase 1 offers 3 BHK (50 homes), 2 BHK (63 homes), and 2.5 BHK (7 homes). Phase 2 offers 2.5 BHK (60 homes), 2 BHK (88 homes), and 3 BHK (36 homes).
What is the carpet area range in Blue Meadows?
Phase 1: 2 BHK ranges from 717 to 803 sq ft, 2.5 BHK from 818 to 1,031 sq ft, and 3 BHK from 723 to 1,115 sq ft. Phase 2: 2 BHK ranges from 721 to 789 sq ft, 2.5 BHK from 860 to 891 sq ft, and 3 BHK from 952 to 960 sq ft.
When will Blue Meadows be completed?
Phase 1 is expected to be completed on 31 December 2025. Phase 2 is expected to be completed on 31 December 2027.
What are the RERA registration numbers for Blue Meadows?
Phase 1 (Main registration) is registered as PRM/KA/RERA/1251/446/PR/150323/005798 since 15 March 2023. Phase 2 is registered as PRM/KA/RERA/1251/446/PR/280225/007531 since 28 February 2025.
What is the construction progress of Blue Meadows Phase 2?
As of Q2 2026-27, Phase 2 is 75% complete with 60 homes booked out of 184 homes in the booking table.
Are there any RERA complaints for Blue Meadows?
There are no RERA complaints on this project or against the builder.
Who is the builder of Blue Meadows?
Yuva Infinity Developers is a partnership firm and has this as their only project in the Bengaluru RERA records.
What bank holds the escrow for Blue Meadows?
Axis Bank holds the escrow for both phases of Blue Meadows.
Written by AI from the RERA record above on 20 Oct 2026. Answers use only that record; check them against the source before you decide.
Questions about Blue Meadows
No questions published yet. Ask the first one: you get an instant answer from this page’s public record, and our team follows up on anything the record does not show.
Bought a home from Yuva Infinity Developers? Review the builder.
Reviews of Yuva Infinity Developers by verified buyers
No verified reviews of Yuva Infinity Developers yet. If you bought a home from them, your review helps other buyers.
How reviews work: only buyers and owners can review; we confirm each purchase by phone before publishing, publish positive and negative reviews alike, never accept payment for reviews, and the builder may reply.
Similar projects within 5 km
| Project | Distance | Homes | Possession (RERA) | Built | Complaints | Price |
|---|---|---|---|---|---|---|
| Nature ElationSTSK Builders And Developers | 0.1 km | 112 | Mar 2027 | — | 0 | Not collected |
| Neeladri SarovaramNeeladri Properties | 0.2 km | 321 | Oct 2026 | — | 0 | Not collected |
| Desire TreePrithvi Developers | 0.3 km | 272 | Jan 2027extended | 83% | 0 | Not collected |
| PSR Serene SpringsPSR Projects and Constructions INDIA Pvt Ltd | 0.4 km | 100 | Dec 2025extended | — | 0 | Not collected |
| Poetry Of EarthUrban Excellence LLP | 0.4 km | 312 | Dec 2028 | 48% | 0 | Not collected |
| Disha Pursuit of RadianceDishahabitat Homes LLP | 0.4 km | 336 | Dec 2030 | 3% | 0 | Not collected |
Projects of the same kind within 5 km in a straight line of this project’s RERA map point, nearest first. % built is the promoter’s latest quarterly figure on RERA (shown for single-registration projects); prices are from the builder’s own website where we found one.
Sources and last checked dates
Collected on 20 Oct 2026 by AI research agents reading public pages. Facts are written in our own words. Not found yet: price; court cases; landmarks; specifications; news.
How to check on RERA: On rera.karnataka.gov.in/viewAllProjects, type the registration number in 'Registration No', press Search, then click the 'View Project Details' icon. Complaints open from the 'Complaints / Litigation' icon in the same row. Registration numbers: PRM/KA/RERA/1251/446/PR/150323/005798, PRM/KA/RERA/1251/446/PR/280225/007531.
- RERA record last checked: 20 Oct 2026
- Last change in the record (registration, quarterly filing or complaint): 20 Oct 2026
How this page is made: software builds it from public records (Karnataka RERA filings, OpenStreetMap, the builder’s own website). AI is used only to read filings into fields and to write the plain-English summary and FAQ answers, which are checked against the record. Facts are checked automatically against the RERA filing. Methodology · How we earn · Report an error
More new projects in Varthur
VarthurUnder constructionRERA registeredBuyers’ group openNature Elation
by STSK Builders And
Price: Price on requestGet brochure & price →
- 2 BHK, 3 BHK
- 664 – 813 sq ft
- Mar 2027
112 homes
Be one of the first 10 buyers in this groupFounding members — it’s free
Join group for Nature Elation
VarthurUnder constructionRERA registeredBuyers’ group openNeeladri Sarovaram
by Neeladri Properties
Price: Price on requestGet brochure & price →
- 1 BHK, 2 BHK, 3 BHK, 4 BHK
- 331 – 1,037 sq ft
- Oct 2026
321 homes
Be one of the first 10 buyers in this groupFounding members — it’s free
Join group for Neeladri Sarovaram
VarthurUnder constructionRERA registeredBuyers’ group openDesire Tree
by Prithvi
Price: Price on requestGet brochure & price →
- 2 BHK, 3 BHK
- 640 – 1,185 sq ft
- Jan 2027 (extended)
272 homes
Be one of the first 10 buyers in this groupFounding members — it’s free
Join group for Desire Tree