Century Mirai Ph1 at a glance
- Possession (RERA)Oct 2030Karnataka RERA
- Construction11% built · on pace for Oct 2034 48 mo after RERA dateRERA filing to 30 Sep 2026; estimate from average pace
- Homes booked215 of 475 (45%)RERA update · as on 30 Sep 2026
- RERA complaints (project)None listedKarnataka RERA · as on 19 Oct 2026
- Approvals filed8 of 9 on RERAKarnataka RERA uploads · 19 Oct 2026
Project summary
Century Mirai Ph1 is a residential project by Century Silicon City Private Limited in Munnekolalu, Bengaluru with 475 homes, registered with Karnataka RERA. The completion date on RERA is 30 Oct 2030.
Not in the RERA record we collected yet: map location. This page fills in as the record is collected.
Facts collected on 19 Oct 2026 from public records — each linked to its source. Free for buyers. If you book through us, the builder pays us a commission.
Century Mirai Ph1 buyers’ group: join to ask for a group price
No one has joined yet. Be one of the first 10 buyers in this group — the founding members.
Join free. When enough buyers have joined, our agent partner asks Century Silicon City Private Limited for a group price — for example a lower price, an easier payment plan or waived charges. Nothing is promised: you see what the builder offers and book directly with the builder if you want to. Free for buyers. If you book through us, the builder pays us a commission.
- Gathering buyers
- Talking to the builder
- Group offer
- Group site visit
- Booking
0 buyers have joined · 0 committed
Committed buyers have confirmed their budget, home type and timeline with us on a call; builders negotiate with them. Joining is free and never obliges you to buy.
Join the Century Mirai Ph1 buyers’ groupHow group buying works
See it for yourself
Visit the site with our team, or get a call to clear your questions. Free, no obligation.
Key facts: home types, towers, land and possession
- Home types
- 1 BHK, 2 BHK, 3 BHK, 4 BHK, +2 more
- Carpet area
- 750 – 4,118 sq ft
- Towers
- 5
- Floors
- 13
- Total homes
- 475
- Land
- 9.4 acres
- Possession (RERA)
- Oct 2030
- Built (RERA update)
- 11%
Century Mirai Ph1 RERA number and registration details
- RERA number
- PRM/KA/RERA/1251/446/PR/181025/008182
- Registered on
- 18 Oct 2025
- Promised completion
- 30 Oct 2030
- Extended to
- No extension recorded
- RERA status
- New launch
- Homes booked
- 215 of 475 as on
- Price
- Not found in public records yet: price
- Project type
- Residential
Towers and blocks (RERA filing)
| Tower | Floors | Basements | Homes |
|---|---|---|---|
| Tower 01 | 13 | 3 | 89 |
| Tower 02 | 13 | 3 | 102 |
| Tower 03 | 13 | 3 | 102 |
| Tower 04 | 13 | 3 | 91 |
| 5 | 13 | 3 | 91 |
A dash (—) means the filing did not state that value.
Summary in plain English
Century Mirai Ph1 is a residential project by Century Silicon City Private Limited in Munnekolalu, Bengaluru East. The project has 475 homes across 5 towers, with homes ranging from 1 BHK to 6 BHK. The completion date on RERA is 30 October 2030.
Written by AI from the RERA record above on 19 Oct 2026. Every number in it was checked against that record; if anything differs, the record wins.
Open space, home loans, escrow and other details
- Open space
- 80.1% of land
- Water and power
- Water source filed with RERA: BWSSB
- Home loans: approved banks
- Not found in public records yet: bank approvals
- Payment plans
- Not found in public records yet: payment plans
- Maintenance
- Not found in public records yet: maintenance
- Car parking
- Not found in public records yet: car parking charge
- Escrow bank (RERA)
- HDFC, VASANTH NAGAR BRANCH
- Building plan (RERA)
- BBMP - Bruhat Bengaluru Mahanagara Palike · No. BBMP/Addl.Dir/JDNORTH/0009/25-26 · dated 29 Aug 2025
- Project cost declared to RERA
- ₹1189 Cr
Open area as a share of the land, from the areas filed with RERA (includes driveways and landscaped areas).
Amenities
- Electricity
- Smart Home Automation
- CCTV Surveillance
- Club House
- Community Hall
- Outdoor Sports facility
- Indoor Sports facility
- Swimming Pool
- Gym
- Parks
- Power Backup
- Water and Sanitation
Amenities and internal works as filed by the promoter with Karnataka RERA; we have not visited the site.
Century Mirai Ph1 location and address
- Address
- Sy. No. 42P, 43, 44, 45, 127P, 128P, 129P , Munnekolalu Village, Varthur Hobli , Bengaluru East , Bengaluru Urban, Karnataka - 560037
- Village (RERA)
- Munnekolalu
- Locality
- MarathahalliAlso known as Marthahalli
- PIN code
- 560037
- City
- Bengaluru
- State
- Karnataka
- Coordinates
- Not found in public records yet: coordinates
Distances to landmarks
Not found in public records yet: landmarksAbout Marathahalli
Not found in public records yet: locality factsCentury Mirai Ph1 home types and carpet areas
Documents the builder uploaded to Karnataka RERA, shown as filed. Tap a page to see it full size; the full PDF opens on the RERA website.
Approved building plan10 pages

Approved Building PlanFull PDF on RERA
Floor plans and brochure not published? The builder shares them only on request. We’ll get the brochure, floor plans and current price list for you, free.
Get brochure, floor plans & price| Home type | Carpet area | Homes |
|---|---|---|
| 1 BHK | 750 – 802 sq ft | 2 |
| 2 BHK | 832 sq ft | 66 |
| 3 BHK | 1,014 – 1,509 sq ft | 346 |
| 4 BHK | 1,844 – 3,302 sq ft | 53 |
| 5 BHK | 2,464 – 3,302 sq ft | 6 |
| 6 BHK | 3,947 – 4,118 sq ft | 2 |
Home types, counts and carpet areas as filed with Karnataka RERA (carpet area, not super built-up).
We have not collected floor-plan drawings; the builder’s sales team can share them.
Century Mirai Ph1 possession date and construction status
Promoter’s quarterly update to RERA for Q2 2026-27, submitted 2026-10-14.
By tower (Q2 2026-27)
Units sold and unsold, from RERA (Q2 2026-27)
| Type | Homes | Booked | Available |
|---|---|---|---|
| 2 BHK | 66 | 49 | 17 |
| 3 BHK | 346 | 148 | 198 |
| 4 BHK | 53 | 17 | 36 |
| 5 BHK | 6 | 0 | 6 |
| 1 BHK | 2 | 0 | 2 |
| 6 BHK | 2 | 1 | 1 |
As reported by the promoter in the quarterly update to RERA, not verified by us.
Timeline
- 1 Oct 2025Project start date given to RERA
- 18 Oct 2025Registered with Karnataka RERA
- 30 Oct 2030Completion date given at registration
Construction pace from RERA quarterly filings
At the average pace so far, construction would reach 100% around Oct 2034 — about 48 months after the completion date on RERA (30 Oct 2030).
At the pace between the 4 quarterly filings we have (4% → 11% in 9 months), it would be around Apr 2036 — about 65 months after the RERA date.
- Filed on RERA
- Average pace since start
- Pace between filings (and 0% assumed at the start date)
- RERA completion date
Quarterly filings
| Quarter | Filed on | Built | Homes booked |
|---|---|---|---|
| Q2 2026-27to 30 Sep 2026 | 14 Oct 2026 | 11% | 215 of 475 |
| Q1 2026-27to 30 Jun 2026 | 14 Jul 2026 | 9% | 180 of 475 |
| Q4 2025-26to 31 Mar 2026 | 5 May 2026 | 6% | 138 of 475 |
| Q3 2025-26to 31 Dec 2025 | 20 Feb 2026 | 4% | 84 of 475 |
How we calculate
Average pace = % built ÷ months since the start date in the RERA record. Here: 11% ÷ 12 months (1 Oct 2025 to 30 Sep 2026) = 0.9% a month.
Estimated finish = latest filing date + (100 − % built) ÷ pace = 30 Sep 2026 + 89 ÷ 0.9 = 96.8 months → Oct 2034. This is an estimate, not a date from the builder or RERA.
Pace between filings = (11% − 4%) ÷ 9 months = 0.8% a month.
A straight line is a simplification: the builder reports one overall %, which mixes excavation, structure and finishing, and work rarely moves at a constant speed. The % values are the promoter’s own figures filed with RERA, not checked by us. Promoter’s quarterly update to RERA for Q2 2026-27, submitted 2026-10-14.
Sources:Source (rera.karnataka.gov.in) (opens in a new tab)How we calculate this
Approvals and documents checklist
11 rows: approvals. Scroll inside the table to see them all.
| Approval | Authority | Source |
|---|---|---|
| Building plan | BBMP - Bruhat Bengaluru Mahanagara Palike · No. BBMP/Addl.Dir/JDNORTH/0009/25-26 · dated 2025-08-29 | Source (rera.karnataka.gov.in) (opens in a new tab) |
| Land conversion (9 orders) | Special Deputy Commissioner · No. B:DS:ALN:SR (SA) /425/1996-97 and 8 more · dated 2024-08-23 | Source (rera.karnataka.gov.in) (opens in a new tab) |
| Commencement Certificate | scan uploaded to RERA | Source (rera.karnataka.gov.in) (opens in a new tab) |
| Approved Building Plan | scan uploaded to RERA | Source (rera.karnataka.gov.in) (opens in a new tab) |
| ESCOM/Electricity | scan uploaded to RERA | Source (rera.karnataka.gov.in) (opens in a new tab) |
| KWSSB/Water | scan uploaded to RERA | Source (rera.karnataka.gov.in) (opens in a new tab) |
| KSPCB | scan uploaded to RERA | Source (rera.karnataka.gov.in) (opens in a new tab) |
| SEIAA | scan uploaded to RERA | Source (rera.karnataka.gov.in) (opens in a new tab) |
| Fire Force Department | scan uploaded to RERA | Source (rera.karnataka.gov.in) (opens in a new tab) |
| Airport Authority of India | scan uploaded to RERA | Source (rera.karnataka.gov.in) (opens in a new tab) |
| NOC in case of building proposals abutting to neighbouring properties | scan uploaded to RERA | Source (rera.karnataka.gov.in) (opens in a new tab) |
Documents uploaded to RERA
- Building or layout plan · Approved drawings from the planning authorityFiled on RERA ✓ — BBMP - Bruhat Bengaluru Mahanagara Palike · No. BBMP/Addl.Dir/JDNORTH/0009/25-26 · dated 29 Aug 2025
- Commencement certificate · Permission to start buildingFiled on RERA ✓ — scanned copy uploaded; number and date not read yet
- Environment clearance · SEIAA KarnatakaFiled on RERA ✓ — scanned copy uploaded; number and date not read yet
- Fire NOC · Karnataka Fire and Emergency ServicesFiled on RERA ✓ — scanned copy uploaded; number and date not read yet
- Pollution board consent · KSPCBFiled on RERA ✓ — scanned copy uploaded; number and date not read yet
- Water and sewerage · BWSSBFiled on RERA ✓ — scanned copy uploaded; number and date not read yet
- Electricity · BESCOMFiled on RERA ✓ — scanned copy uploaded; number and date not read yet
- Height clearance · Airports Authority of IndiaFiled on RERA ✓ — scanned copy uploaded; number and date not read yet
- Occupancy certificate (OC) · Issued only when the building is finishedNot on RERA yet — expected at completion
From the documents the promoter uploaded to Karnataka RERA, collected 19 Oct 2026. “Filed” means a document is on RERA — we have not checked its contents or validity. Not every approval applies to every project (for example, smaller projects may not need an environment clearance). The project page on RERA lists each upload.
Century Mirai Ph1 RERA complaints
No complaints listed on Karnataka RERA for this registration as on Source (rera.karnataka.gov.in) (opens in a new tab)
Court and consumer cases
We list case numbers, courts and outcomes only — never names of private individuals.
About Century Silicon City Private Limited
- Promoter type
- Company
- Projects on this site
- 1
- RERA complaints against promoter
- 0
- Company number (CIN)
- U68100KA2023PTC173682
From Karnataka RERA, as collected so far (19 Oct 2026). Complaints are those RERA lists against this promoter across all its projects.
Century Silicon City Private Limited’s RERA recordCentury Silicon City Private Limited delivery record
- 1Projects in Bengaluru on RERA1 approved registration under Century Silicon City Private Limited in Bengaluru Urban and Rural. Source (rera.karnataka.gov.in) (opens in a new tab)
- 475Homes registeredAs stated in each registrations.
- 0RERA complaintsas on Source (rera.karnataka.gov.in) (opens in a new tab)
- 0Complaints per 1,000 homes0 complaints ÷ 475 homes in its 1 registration on Karnataka RERA in Bengaluru.
Sources:Source (rera.karnataka.gov.in) (opens in a new tab)How we calculate this
What’s changed since Aug 2025
- 14 Oct 2026Quarterly update filed for Q2 2026-27: 11% built, 215 of 475 homes booked Source (rera.karnataka.gov.in) (opens in a new tab)
- 14 Jul 2026Quarterly update filed for Q1 2026-27: 9% built, 180 of 475 homes booked Source (rera.karnataka.gov.in) (opens in a new tab)
- 5 May 2026Quarterly update filed for Q4 2025-26: 6% built, 138 of 475 homes booked Source (rera.karnataka.gov.in) (opens in a new tab)
- 20 Feb 2026Quarterly update filed for Q3 2025-26: 4% built, 84 of 475 homes booked Source (rera.karnataka.gov.in) (opens in a new tab)
- 18 Oct 2025Registered with Karnataka RERA (PRM/KA/RERA/1251/446/PR/181025/008182); completion date 30 Oct 2030 Source (rera.karnataka.gov.in) (opens in a new tab)
- 1 Oct 2025Project start date in the RERA record Source (rera.karnataka.gov.in) (opens in a new tab)
- 29 Aug 2025Building plan approved by BBMP - Bruhat Bengaluru Mahanagara Palike (No. BBMP/Addl.Dir/JDNORTH/0009/25-26) Source (rera.karnataka.gov.in) (opens in a new tab)
Newest first. No extension of the completion date is recorded on RERA. When the RERA crawl sees a new filing, complaint or extension, it is added here with its date.
Home loan EMI calculator
- Monthly EMI
- —
- Down payment
- —
- Loan amount
- —
- Total interest
- —
A calculation only, from the numbers you enter — not a loan offer.
All-in cost: GST, registration and other charges
The calculator loads when you scroll to it.
Assumptions
- Base price: the builder’s price is not published in a form we could collect — enter it from the cost sheet.
- GST 5% on the base price and charges — the usual rate for an under-construction home that is not “affordable housing” (1%).
- Stamp duty about 5.6% and registration 2% — the Karnataka rule (registration was raised from 1% to 2% on 31 Aug 2025). Calculated on the agreement value.
- Car parking, other charges and the maintenance deposit are not in the public record we collect; enter them from the builder’s cost sheet.
- Loan on the agreement value (banks usually lend up to 75–90%); EMI is the standard reducing-balance formula. Example rate only — use your bank’s quote.
Century Mirai Ph1 FAQs
What is the RERA registration number for Century Mirai Ph1?
The RERA registration number is PRM/KA/RERA/1251/446/PR/181025/008182, registered on 18 October 2025.
How many homes are in Century Mirai Ph1?
The project has 475 homes across 5 towers.
What home types are available in Century Mirai Ph1?
The project offers 1 BHK (2 homes), 2 BHK (66 homes), 3 BHK (346 homes), 4 BHK (53 homes), 5 BHK (6 homes), and 6 BHK (2 homes).
What is the carpet area range for homes in Century Mirai Ph1?
Carpet area ranges from 750 sq ft for 1 BHK homes to 4,118 sq ft for 6 BHK homes.
When will Century Mirai Ph1 be completed?
The completion date on RERA is 30 October 2030.
What is the current construction progress of Century Mirai Ph1?
As of the quarter ended 30 September 2026, construction is 11% complete with 215 homes booked out of 475 homes in the booking table.
Where is Century Mirai Ph1 located?
The project is in Munnekolalu, Bengaluru East taluk, Bengaluru Urban district, with PIN code 560037.
Are there any RERA complaints against Century Mirai Ph1?
There are no RERA complaints on this project.
What is the builder's track record?
Century Silicon City Private Limited has no RERA complaints against the builder across all projects on record and this is the builder's only project in the RERA records.
How many towers are in Century Mirai Ph1?
The project has 5 towers with a maximum of 13 floors.
Written by AI from the RERA record above on 19 Oct 2026. Answers use only that record; check them against the source before you decide.
Questions about Century Mirai Ph1
No questions published yet. Ask the first one: you get an instant answer from this page’s public record, and our team follows up on anything the record does not show.
Bought a home from Century Silicon City Private Limited? Review the builder.
Reviews of Century Silicon City Private Limited by verified buyers
No verified reviews of Century Silicon City Private Limited yet. If you bought a home from them, your review helps other buyers.
How reviews work: only buyers and owners can review; we confirm each purchase by phone before publishing, publish positive and negative reviews alike, never accept payment for reviews, and the builder may reply.
Sources and last checked dates
Collected on 19 Oct 2026 by AI research agents reading public pages. Facts are written in our own words. Not found yet: price; court cases; landmarks; specifications; news.
How to check on RERA: On rera.karnataka.gov.in/viewAllProjects, type the registration number in 'Registration No', press Search, then click the 'View Project Details' icon. Complaints open from the 'Complaints / Litigation' icon in the same row. Registration number: PRM/KA/RERA/1251/446/PR/181025/008182.
- RERA record last checked: 19 Oct 2026
- Last change in the record (registration, quarterly filing or complaint): 19 Oct 2026
How this page is made: software builds it from public records (Karnataka RERA filings, OpenStreetMap, the builder’s own website). AI is used only to read filings into fields and to write the plain-English summary and FAQ answers, which are checked against the record. Facts are checked automatically against the RERA filing. Methodology · How we earn · Report an error
More new projects in Marathahalli
Chinnappanahalli, MarathahalliUnder constructionRERA registeredBuyers’ group openVaishnavi Harmony
by Affinity
Price: Price on requestGet brochure & price →
- 2 BHK, 3 BHK
- up to 1,243 sq ft
- Dec 2027
48 homes
Be one of the first 10 buyers in this groupFounding members — it’s free
Join group for Vaishnavi Harmony
Hosakerehalli, Rajarajeshwari NagarArtist’s impressionUnder constructionRERA registeredBuyers’ group openSobha Valley View - Heritage
by Sobha
Price: Price on requestGet brochure & price →
- 2 BHK, 3 BHK
- 917 – 1,267 sq ft
- Feb 2019
RERA not updated since promised Feb 2019 · 624 homes · 19 RERA complaints
Be one of the first 10 buyers in this groupFounding members — it’s free
Join group for Sobha Valley View - Heritage
Agara, HSR LayoutArtist’s impressionUnder constructionRERA registeredBuyers’ group openSterling Infinia
by Sterling
Price: Price on requestGet brochure & price →
- 1 BHK, 2 BHK, 3 BHK, 4 BHK
- 904 – 2,336 sq ft
- Sep 2026 (extended)
RERA not updated since promised Sep 2026 · 344 homes · 4 RERA complaints
Be one of the first 10 buyers in this groupFounding members — it’s free
Join group for Sterling Infinia