Embassy Springs - Phase 2A, Apartments
Apartments by Embassy Developments Limited · Bengaluru
BengaluruOpen on Google Maps (opens in a new tab)
- Under construction
- RERA registered
- residential
by Embassy Developments Limited
Price: Price on request
Site photo filed with Karnataka RERA Karnataka RERA filing · Source ↗ (opens in a new tab)
Embassy Springs - Phase 2A, Apartments at a glance
- Possession (RERA)Dec 2027 ExtendedWas Feb 2023 · Karnataka RERA
- Construction72% built · on pace for Sep 2029 21 mo after RERA dateRERA filing to 30 Jun 2026; estimate from average pace
- Homes booked673 of 826 (81%)RERA update · as on 30 Jun 2026
- RERA complaints (project)5 complaintsKarnataka RERA · as on 14 Oct 2026
- Approvals filed1 of 9 on RERAKarnataka RERA uploads · 14 Oct 2026
Project summary
Embassy Springs - Phase 2A, Apartments is a residential project by Embassy Developments Limited in Bengaluru with 826 homes, registered with Karnataka RERA. The completion date on RERA is 31 Dec 2027.
Not in the RERA record we collected yet: locality. This page fills in as the record is collected.
Facts collected on 14 Oct 2026 from public records — each linked to its source. Free for buyers. If you book through us, the builder pays us a commission.
Embassy Springs - Phase 2A, Apartments buyers’ group: join to ask for a group price
No one has joined yet. Be one of the first 10 buyers in this group — the founding members.
Join free. When enough buyers have joined, our agent partner asks Embassy Developments Limited for a group price — for example a lower price, an easier payment plan or waived charges. Nothing is promised: you see what the builder offers and book directly with the builder if you want to. Free for buyers. If you book through us, the builder pays us a commission.
- Gathering buyers
- Talking to the builder
- Group offer
- Group site visit
- Booking
0 buyers have joined · 0 committed
Committed buyers have confirmed their budget, home type and timeline with us on a call; builders negotiate with them. Joining is free and never obliges you to buy.
Join the Embassy Springs - Phase 2A, Apartments buyers’ groupHow group buying works
See it for yourself
Visit the site with our team, or get a call to clear your questions. Free, no obligation.
Key facts: home types, towers, land and possession
- Home types
- Not found in public records yet: home types
- Carpet area
- 411 – 912 sq ft
- Towers
- 5
- Floors
- 14
- Total homes
- 826
- Land
- 7.77 acres
- Possession (extended)
- Dec 2027
- Built (RERA update)
- 72%
Embassy Springs - Phase 2A, Apartments RERA number and registration details
- RERA number
- PRM/KA/RERA/1250/303/PR/180526/001825
- Registered on
- 26 May 2018
- Promised completion
- 28 Feb 2023
- Extended to
- 31 Dec 2027
- RERA status
- New launch
- Homes booked
- 673 of 826 as on
- Price
- Not found in public records yet: price
- Project type
- Residential
Towers and blocks (RERA filing)
| Tower | Floors | Basements | Homes |
|---|---|---|---|
| Gardenia | 14 | 0 | 252 |
| Hibiscus | 14 | 0 | 112 |
| Fucshia | 14 | 0 | 112 |
| Daisy | 14 | 0 | 196 |
| Elderberry | 14 | 0 | 154 |
A dash (—) means the filing did not state that value.
Summary in plain English
Embassy Springs - Phase 2A is a residential apartment project by Embassy Developments Limited in Devanahalli, Bengaluru Rural, with 826 homes across 5 towers. The project was registered with RERA on 26 May 2018 and has a current completion date of 31 December 2027.
Written by AI from the RERA record above on 5 Oct 2026. Every number in it was checked against that record; if anything differs, the record wins.
Open space, home loans, escrow and other details
- Open space
- 82% of land
- Water and power
- Not found in public records yet: water and power
- Home loans: approved banks
- Not found in public records yet: bank approvals
- Payment plans
- Not found in public records yet: payment plans
- Maintenance
- Not found in public records yet: maintenance
- Car parking
- Not found in public records yet: car parking charge
- Escrow bank (RERA)
- KOTAK MAHINDRA BANK, MG Road
- Project cost declared to RERA
- ₹414 Cr
Open area as a share of the land, from the areas filed with RERA (includes driveways and landscaped areas).
Amenities
Embassy Springs - Phase 2A, Apartments location and address
- Address
- Embassy Springs, Embassy Springs, Nagamangala and Hegganalli Villages, Kundana Hobli, Devanahalli Taluk, , Kundana Hobli, Devanahalli Taluk
- Village (RERA)
- Not found in public records yet: village
- PIN code
- 560071
- City
- Bengaluru
- State
- Karnataka
- Coordinates
- 13.00000, 77.00000
Distances to landmarks
Not found in public records yet: landmarksAbout the locality
Not found in public records yet: locality factsEmbassy Springs - Phase 2A, Apartments home types and carpet areas
Floor plans and brochure not published? The builder shares them only on request. We’ll get the brochure, floor plans and current price list for you, free.
Get brochure, floor plans & price| Home type | Carpet area | Homes |
|---|---|---|
| Other | 411 – 912 sq ft | 630 |
| Others | 411 – 912 sq ft | 196 |
Home types, counts and carpet areas as filed with Karnataka RERA (carpet area, not super built-up).
We have not collected floor-plan drawings; the builder’s sales team can share them.
Embassy Springs - Phase 2A, Apartments possession date and construction status
Promoter’s quarterly update to RERA for Q1 2026-27, submitted 2026-07-15.
By tower (Q1 2026-27)
Units sold and unsold, from RERA (Q1 2026-27)
| Type | Homes | Booked | Available |
|---|---|---|---|
| OTHER | 630 | 506 | 124 |
| OTHERS | 196 | 167 | 29 |
As reported by the promoter in the quarterly update to RERA, not verified by us.
Timeline
- 20 Feb 2018Project start date given to RERA
- 26 May 2018Registered with Karnataka RERA
- 28 Feb 2023Completion date given at registration
- 28 Nov 2023Covid Extension: completion date moved to this date
- 28 Nov 2024Section 6 Extension: completion date moved to this date
- 31 Dec 2027Further Extension: completion date moved to this date
Construction pace from RERA quarterly filings
At the average pace so far, construction would reach 100% around Sep 2029 — about 21 months after the completion date on RERA (31 Dec 2027).
At the pace between the 3 quarterly filings we have (61% → 72% in 6 months), it would be around Oct 2027 — about 3 months before the RERA date.
- Filed on RERA
- Average pace since start
- Pace between filings (and 0% assumed at the start date)
- RERA completion date
Quarterly filings
| Quarter | Filed on | Built | Homes booked |
|---|---|---|---|
| Q1 2026-27to 30 Jun 2026 | 15 Jul 2026 | 72% | 673 of 826 |
| Q4 2025-26to 31 Mar 2026 | 14 Apr 2026 | 66% | 624 of 826 |
| Q3 2025-26to 31 Dec 2025 | 14 Jan 2026 | 61% | 610 of 826 |
How we calculate
Average pace = % built ÷ months since the start date in the RERA record. Here: 72% ÷ 100.3 months (20 Feb 2018 to 30 Jun 2026) = 0.7% a month.
Estimated finish = latest filing date + (100 − % built) ÷ pace = 30 Jun 2026 + 28 ÷ 0.7 = 39 months → Sep 2029. This is an estimate, not a date from the builder or RERA.
Pace between filings = (72% − 61%) ÷ 5.9 months = 1.8% a month.
A straight line is a simplification: the builder reports one overall %, which mixes excavation, structure and finishing, and work rarely moves at a constant speed. The % values are the promoter’s own figures filed with RERA, not checked by us. Promoter’s quarterly update to RERA for Q1 2026-27, submitted 2026-07-15.
Sources:Source (rera.karnataka.gov.in) (opens in a new tab)How we calculate this
Approvals and documents checklist
| Approval | Authority | Source |
|---|---|---|
| Building plan | BIAPPA - Bangalore Airport Area Planning Authority | Source (rera.karnataka.gov.in) (opens in a new tab) |
Documents uploaded to RERA
- Building or layout plan · Approved drawings from the planning authorityFiled on RERA ✓ — scanned copy uploaded; number and date not read yet
- Commencement certificate · Permission to start buildingNot on RERA yet
- Environment clearance · SEIAA KarnatakaNot on RERA yet
- Fire NOC · Karnataka Fire and Emergency ServicesNot on RERA yet
- Pollution board consent · KSPCBNot on RERA yet
- Water and sewerage · BWSSBNot on RERA yet
- Electricity · BESCOMNot on RERA yet
- Height clearance · Airports Authority of IndiaNot on RERA yet
- Occupancy certificate (OC) · Issued only when the building is finishedNot on RERA yet — expected at completion
From the documents the promoter uploaded to Karnataka RERA, collected 14 Oct 2026. “Filed” means a document is on RERA — we have not checked its contents or validity. Not every approval applies to every project (for example, smaller projects may not need an environment clearance). The project page on RERA lists each upload.
Embassy Springs - Phase 2A, Apartments RERA complaints and orders
5 complaints as on Source (rera.karnataka.gov.in) (opens in a new tab)
| Complaint ref | Filed | Subject | Status | Source |
|---|---|---|---|---|
| 01228/2024 | 20 Nov 2024 | Refund of paid advance amount of Rs. 8, 52,334/- to the Respondent along with interest | Disposed | Source (rera.karnataka.gov.in) (opens in a new tab) |
| 00607/2024 | 18 Jun 2024 | Promoter delaying/not refunding amount charged - Inordinate delay/profiteering | Disposed | Source (rera.karnataka.gov.in) (opens in a new tab) |
| 00320/2024 | 26 Mar 2024 | Delay in project and delay in refund | Disposed | Source (rera.karnataka.gov.in) (opens in a new tab) |
| CMP/221014/0010102 | 14 Oct 2022 | The total flat in booking from is higher than what was agreed | Disposed | Source (rera.karnataka.gov.in) (opens in a new tab) |
| CMP/211206/0008692 | 6 Dec 2021 | Request Refund of Rs.30000/- forfeited amount | Disposed | Source (rera.karnataka.gov.in) (opens in a new tab) |
Court and consumer cases
We list case numbers, courts and outcomes only — never names of private individuals.
About Embassy Developments Limited
- Promoter type
- Company
- Projects on this site
- 4
- RERA complaints against promoter
- 7
- Company number (CIN)
- U85110KA1995PTC017950
From Karnataka RERA, as collected so far (14 Oct 2026). Complaints are those RERA lists against this promoter across all its projects.
Embassy Developments Limited’s RERA recordEmbassy Developments Limited delivery record
- 4Projects in Bengaluru on RERA5 approved registrations under Embassy Developments Limited in Bengaluru Urban and Rural. Source (rera.karnataka.gov.in) (opens in a new tab)
- 3,498Homes and plots registeredAs stated in each registrations.
- 7RERA complaints0 open, 7 disposed. as on Source (rera.karnataka.gov.in) (opens in a new tab)
- 2Complaints per 1,000 homes and plots7 complaints ÷ 3,498 homes and plots in its 5 registrations on Karnataka RERA in Bengaluru.
What the complaints are about
7 complaint subjects as written on RERA, as on . Each subject is sorted into one group by keywords (first match wins: delay, refund, registration, quality, litigation, association); one complaint often raises several issues. Source (rera.karnataka.gov.in) (opens in a new tab)
Sources:Source (rera.karnataka.gov.in) (opens in a new tab)How we calculate this
What’s changed since Feb 2018
- 31 Dec 2027Completion date extended to 31 Dec 2027 Source (rera.karnataka.gov.in) (opens in a new tab)
- 15 Jul 2026Quarterly update filed for Q1 2026-27: 72% built, 673 of 826 homes booked Source (rera.karnataka.gov.in) (opens in a new tab)
- 14 Apr 2026Quarterly update filed for Q4 2025-26: 66% built, 624 of 826 homes booked Source (rera.karnataka.gov.in) (opens in a new tab)
- 14 Jan 2026Quarterly update filed for Q3 2025-26: 61% built, 610 of 826 homes booked Source (rera.karnataka.gov.in) (opens in a new tab)
- 20 Nov 2024Complaint 01228/2024 filed with RERA: “Refund of paid advance amount of Rs. 8, 52,334/- to the Respondent along with interest” — now disposed Source (rera.karnataka.gov.in) (opens in a new tab)
- 18 Jun 2024Complaint 00607/2024 filed with RERA: “Promoter delaying/not refunding amount charged - Inordinate delay/profiteering” — now disposed Source (rera.karnataka.gov.in) (opens in a new tab)
- 26 Mar 2024Complaint 00320/2024 filed with RERA: “Delay in project and delay in refund” — now disposed Source (rera.karnataka.gov.in) (opens in a new tab)
- 14 Oct 2022Complaint CMP/221014/0010102 filed with RERA: “The total flat in booking from is higher than what was agreed” — now disposed Source (rera.karnataka.gov.in) (opens in a new tab)
- 6 Dec 2021Complaint CMP/211206/0008692 filed with RERA: “Request Refund of Rs.30000/- forfeited amount” — now disposed Source (rera.karnataka.gov.in) (opens in a new tab)
- 26 May 2018Registered with Karnataka RERA (PRM/KA/RERA/1250/303/PR/180526/001825); completion date 28 Feb 2023 Source (rera.karnataka.gov.in) (opens in a new tab)
- 20 Feb 2018Project start date in the RERA record Source (rera.karnataka.gov.in) (opens in a new tab)
Newest first. When the RERA crawl sees a new filing, complaint or extension, it is added here with its date.
Home loan EMI calculator
- Monthly EMI
- —
- Down payment
- —
- Loan amount
- —
- Total interest
- —
A calculation only, from the numbers you enter — not a loan offer.
All-in cost: GST, registration and other charges
The calculator loads when you scroll to it.
Assumptions
- Base price: the builder’s price is not published in a form we could collect — enter it from the cost sheet.
- GST 5% on the base price and charges — the usual rate for an under-construction home that is not “affordable housing” (1%).
- Stamp duty about 5.6% and registration 2% — the Karnataka rule (registration was raised from 1% to 2% on 31 Aug 2025). Calculated on the agreement value.
- Car parking, other charges and the maintenance deposit are not in the public record we collect; enter them from the builder’s cost sheet.
- Loan on the agreement value (banks usually lend up to 75–90%); EMI is the standard reducing-balance formula. Example rate only — use your bank’s quote.
Embassy Springs - Phase 2A, Apartments FAQs
What is the completion date for Embassy Springs - Phase 2A?
The current completion date on RERA is 31 December 2027. The project has received three extensions: a Covid Extension to 28 November 2023, a Section 6 Extension to 28 November 2024, and a Further Extension to 31 December 2027.
What is the RERA registration number for Embassy Springs - Phase 2A?
The RERA registration number is PRM/KA/RERA/1250/303/PR/180526/001825, registered on 26 May 2018.
How many homes are in Embassy Springs - Phase 2A and what are the carpet areas?
The project has 826 homes across 5 towers with a maximum of 14 floors. Carpet areas range from 411 sq ft to 912 sq ft.
What is the construction progress of Embassy Springs - Phase 2A?
As of Q1 2026-27 (ended 30 June 2026), the project is 72% complete with 673 homes booked out of 826 homes in the booking table.
Where is Embassy Springs - Phase 2A located?
The project is located in Devanahalli taluk, Bengaluru Rural district, with PIN code 560071.
How many RERA complaints have been filed against Embassy Springs - Phase 2A?
There are 5 RERA complaints on this project registration.
What is the escrow bank for Embassy Springs - Phase 2A?
The escrow bank for the project is Kotak Mahindra Bank.
How many other projects does Embassy Developments Limited have on RERA record?
Embassy Developments Limited has 4 projects in the Bengaluru records and 7 total RERA complaints across all its projects.
What home types are available in Embassy Springs - Phase 2A?
The project has 630 homes of one type and 196 homes of another type, all with carpet areas between 411 sq ft and 912 sq ft; home type names are not specified in the RERA record.
Written by AI from the RERA record above on 5 Oct 2026. Answers use only that record; check them against the source before you decide.
Questions about Embassy Springs - Phase 2A, Apartments
No questions published yet. Ask the first one: you get an instant answer from this page’s public record, and our team follows up on anything the record does not show.
Bought a home from Embassy Developments Limited? Review the builder.
Reviews of Embassy Developments Limited by verified buyers
No verified reviews of Embassy Developments Limited yet. If you bought a home from them, your review helps other buyers.
How reviews work: only buyers and owners can review; we confirm each purchase by phone before publishing, publish positive and negative reviews alike, never accept payment for reviews, and the builder may reply.
Similar projects within 5 km
| Project | Distance | Homes | Possession (RERA) | Built | Complaints | Price |
|---|---|---|---|---|---|---|
| In That Quiet Earth Phase-2aTotal Environment Constructions Private Limited | 0 km | 110 | Dec 2026extended | 45% | 1 | Not collected |
| Mahaveer NorthscapePragati Corp | 0 km | 476 | Sep 2025extended | — | 3 | Not collected |
| 3 Little BirdsZenso Little Birds Projects LLP | 0 km | 30 | Sep 2026extended | — | 0 | Not collected |
| Aspire Aurum A Sumadhura VentureSumadhura Infracon Private Limited | 0 km | 326 | Sep 2023extended | — | 0 | Not collected |
| V.S.R TranquilV.S.R Ventures | 0 km | 366 | Sep 2025extended | — | 1 | Not collected |
| Kumar ProsperaKumar Properties Pvt Ltd | 0 km | 125 | Jun 2030extended | — | 1 | Not collected |
Projects of the same kind within 5 km in a straight line of this project’s RERA map point, nearest first. % built is the promoter’s latest quarterly figure on RERA (shown for single-registration projects); prices are from the builder’s own website where we found one.
Sources and last checked dates
Collected on 14 Oct 2026 by AI research agents reading public pages. Facts are written in our own words. Not found yet: price; court cases; landmarks; specifications; news.
How to check on RERA: On rera.karnataka.gov.in/viewAllProjects, type the registration number in 'Registration No', press Search, then click the 'View Project Details' icon. Complaints open from the 'Complaints / Litigation' icon in the same row. Registration number: PRM/KA/RERA/1250/303/PR/180526/001825.
- RERA record last checked: 14 Oct 2026
- Last change in the record (registration, quarterly filing or complaint): 15 Jul 2026
How this page is made: software builds it from public records (Karnataka RERA filings, OpenStreetMap, the builder’s own website). AI is used only to read filings into fields and to write the plain-English summary and FAQ answers, which are checked against the record. Facts are checked automatically against the RERA filing. Methodology · How we earn · Report an error
More new projects nearby
Bileshivale, HoramavuUnder constructionRERA registeredBuyers’ group openIn That Quiet Earth Phase-2a
by Total Environment Constructions
Price: Price on requestGet brochure & price →
- 3 BHK, Villa
- 2,768 sq ft
- Dec 2026 (extended)
110 homes · 1 RERA complaint
Be one of the first 10 buyers in this groupFounding members — it’s free
Join group for In That Quiet Earth Phase-2a
Navarathna AgaraharaUnder constructionRERA registeredBuyers’ group openMahaveer Northscape
by Pragati Corp
Price: Price on requestGet brochure & price →
- 1 BHK, 2 BHK, 3 BHK
- 453 – 991 sq ft
- Sep 2025 (extended)
RERA not updated since promised Sep 2025 · 476 homes · 3 RERA complaints
Be one of the first 10 buyers in this groupFounding members — it’s free
Join group for Mahaveer Northscape
Byrathi, Hennur RoadUnder constructionRERA registeredBuyers’ group open3 Little Birds
by Zenso Little Birds
Price: Price on requestGet brochure & price →
- 2 BHK
- 673 – 766 sq ft
- Sep 2026 (extended)
RERA not updated since promised Sep 2026 · 30 homes
Be one of the first 10 buyers in this groupFounding members — it’s free
Join group for 3 Little Birds