Futurity Homes
2 & 3 BHK apartments by Balaji Homes · Bilishivale, Bengaluru
Bilishivale, Bengaluru
- Under construction
- RERA registered
- residential
by Balaji Homes
Price: Price on request
Site photo filed with Karnataka RERA Karnataka RERA filing · Source ↗ (opens in a new tab)
Futurity Homes at a glance
- Possession (RERA)Oct 2026Karnataka RERA
- Construction77% built · on pace for May 2027 6 mo after RERA dateRERA filing to 30 Sep 2026; estimate from average pace
- Homes booked35 of 76 (46%)RERA update · as on 30 Sep 2026
- RERA complaints (project)None listedKarnataka RERA · as on 20 Oct 2026
- Approvals filed5 of 9 on RERAKarnataka RERA uploads · 20 Oct 2026
Project summary
Futurity Homes is a residential project by Balaji Homes in Bilishivale, Bengaluru with 76 homes, registered with Karnataka RERA. The completion date on RERA is 30 Oct 2026.
Not in the RERA record we collected yet: map location. This page fills in as the record is collected.
Facts collected on 20 Oct 2026 from public records — each linked to its source. Free for buyers. If you book through us, the builder pays us a commission.
Futurity Homes buyers’ group: join to ask for a group price
No one has joined yet. Be one of the first 10 buyers in this group — the founding members.
Join free. When enough buyers have joined, our agent partner asks Balaji Homes for a group price — for example a lower price, an easier payment plan or waived charges. Nothing is promised: you see what the builder offers and book directly with the builder if you want to. Free for buyers. If you book through us, the builder pays us a commission.
- Gathering buyers
- Talking to the builder
- Group offer
- Group site visit
- Booking
0 buyers have joined · 0 committed
Committed buyers have confirmed their budget, home type and timeline with us on a call; builders negotiate with them. Joining is free and never obliges you to buy.
Join the Futurity Homes buyers’ groupHow group buying works
See it for yourself
Visit the site with our team, or get a call to clear your questions. Free, no obligation.
Key facts: home types, towers, land and possession
- Home types
- 2 BHK, 3 BHK
- Carpet area
- 479 – 1,116 sq ft
- Towers
- 1
- Floors
- 3
- Total homes
- 76
- Land
- 0.97 acres
- Possession (RERA)
- Oct 2026
- Built (RERA update)
- 77%
Futurity Homes RERA number and registration details
- RERA number
- PRM/KA/RERA/1251/446/PR/080125/007363
- Registered on
- 8 Jan 2025
- Promised completion
- 30 Oct 2026
- Extended to
- No extension recorded
- RERA status
- New launch
- Homes booked
- 35 of 76 as on
- Price
- Not found in public records yet: price
- Project type
- Residential
Towers and blocks (RERA filing)
| Tower | Floors | Basements | Homes |
|---|---|---|---|
| FUTURITY HOMES | 3 | 1 | 76 |
A dash (—) means the filing did not state that value.
Summary in plain English
Futurity Homes is a residential project by Balaji Homes in Bilishivale, Bengaluru East with 76 homes in 1 tower. The project is registered with RERA and is expected to be completed on 30 October 2026.
Written by AI from the RERA record above on 20 Oct 2026. Every number in it was checked against that record; if anything differs, the record wins.
Open space, home loans, escrow and other details
- Open space
- 48.6% of land
- Water and power
- Water source filed with RERA: BoreWell,BWSSB
- Home loans: approved banks
- Not found in public records yet: bank approvals
- Payment plans
- Not found in public records yet: payment plans
- Maintenance
- Not found in public records yet: maintenance
- Car parking
- Not found in public records yet: car parking charge
- Escrow bank (RERA)
- IDFC FIRST BANK, BANNERHATTA ROAD
- Building plan (RERA)
- BBMP - Bruhat Bengaluru Mahanagara Palike · No. BBMP/AD.COM/MDP/0154/24-25 · dated 17 Aug 2024
- Project cost declared to RERA
- ₹42.36 Cr
Open area as a share of the land, from the areas filed with RERA (includes driveways and landscaped areas).
Amenities
- Electricity
Amenities and internal works as filed by the promoter with Karnataka RERA; we have not visited the site.
Futurity Homes location and address
- Address
- Survey No.76/5 , BILISHIVALE VILLAGE, Bidarahalli Hobli, Bangalore East Taluk, Bangalore , Bengaluru East , Bengaluru Urban, Karnataka - 560077
- Village (RERA)
- Bilishivale
- PIN code
- 560077
- City
- Bengaluru
- State
- Karnataka
- Coordinates
- Not found in public records yet: coordinates
Distances to landmarks
Not found in public records yet: landmarksAbout Bilishivale
Not found in public records yet: locality factsFuturity Homes home types and carpet areas
Documents the builder uploaded to Karnataka RERA, shown as filed. Tap a page to see it full size; the full PDF opens on the RERA website.
Approved building plan2 pages

Approved planFiled 5 Nov 2024 · Full PDF on RERA
Floor plans and brochure not published? The builder shares them only on request. We’ll get the brochure, floor plans and current price list for you, free.
Get brochure, floor plans & price| Home type | Carpet area | Homes |
|---|---|---|
| 2 BHK | 479 – 803 sq ft | 24 |
| 2 BHK and 3 BHK | 875 sq ft | 76 |
| 3 BHK | 790 – 1,116 sq ft | 52 |
Home types, counts and carpet areas as filed with Karnataka RERA (carpet area, not super built-up).
We have not collected floor-plan drawings; the builder’s sales team can share them.
Futurity Homes possession date and construction status
Promoter’s quarterly update to RERA for Q2 2026-27, submitted 2026-10-15.
Units sold and unsold, from RERA (Q2 2026-27)
| Type | Homes | Booked | Available |
|---|---|---|---|
| 2 BHK | 24 | 12 | 12 |
| 3 BHK | 52 | 23 | 29 |
As reported by the promoter in the quarterly update to RERA, not verified by us.
Timeline
- 10 Oct 2024Project start date given to RERA
- 8 Jan 2025Registered with Karnataka RERA
- 30 Oct 2026Completion date given at registration
Construction pace from RERA quarterly filings
At the average pace so far, construction would reach 100% around May 2027 — about 6 months after the completion date on RERA (30 Oct 2026).
At the pace between the 4 quarterly filings we have (58% → 77% in 9 months), it would be around Aug 2027 — about 10 months after the RERA date.
- Filed on RERA
- Average pace since start
- Pace between filings (and 0% assumed at the start date)
- RERA completion date
Quarterly filings
| Quarter | Filed on | Built | Homes booked |
|---|---|---|---|
| Q2 2026-27to 30 Sep 2026 | 15 Oct 2026 | 77% | 35 of 76 |
| Q1 2026-27to 30 Jun 2026 | 15 Oct 2026 | 71% | 30 of 76 |
| Q4 2025-26to 31 Mar 2026 | 25 Apr 2026 | 66% | 24 of 76 |
| Q3 2025-26to 31 Dec 2025 | 23 Apr 2026 | 58% | 15 of 76 |
How we calculate
Average pace = % built ÷ months since the start date in the RERA record. Here: 77% ÷ 23.7 months (10 Oct 2024 to 30 Sep 2026) = 3.3% a month.
Estimated finish = latest filing date + (100 − % built) ÷ pace = 30 Sep 2026 + 23 ÷ 3.3 = 7.1 months → May 2027. This is an estimate, not a date from the builder or RERA.
Pace between filings = (77% − 58%) ÷ 9 months = 2.1% a month.
A straight line is a simplification: the builder reports one overall %, which mixes excavation, structure and finishing, and work rarely moves at a constant speed. The % values are the promoter’s own figures filed with RERA, not checked by us. Promoter’s quarterly update to RERA for Q2 2026-27, submitted 2026-10-15.
Sources:Source (rera.karnataka.gov.in) (opens in a new tab)How we calculate this
Approvals and documents checklist
13 rows: approvals. Scroll inside the table to see them all.
| Approval | Authority | Source |
|---|---|---|
| Building plan | BBMP - Bruhat Bengaluru Mahanagara Palike · No. BBMP/AD.COM/MDP/0154/24-25 · dated 2024-08-17 | Source (rera.karnataka.gov.in) (opens in a new tab) |
| Land conversion | Deputy Commissioner · No. ALN (EBB) SR 234/2022-23 · dated 2023-01-31 | Source (rera.karnataka.gov.in) (opens in a new tab) |
| Commencement Certificate | scan uploaded to RERA | Source (rera.karnataka.gov.in) (opens in a new tab) |
| Electricity Permission Letter | scan uploaded to RERA | Source (rera.karnataka.gov.in) (opens in a new tab) |
| Water Permission Letter | scan uploaded to RERA | Source (rera.karnataka.gov.in) (opens in a new tab) |
| Approved Layout Plan | scan uploaded to RERA | Source (rera.karnataka.gov.in) (opens in a new tab) |
| Approved Building/Plotting Plan | scan uploaded to RERA | Source (rera.karnataka.gov.in) (opens in a new tab) |
| Approved Section Of Building/Infrastructure Plan of Plotting | scan uploaded to RERA | Source (rera.karnataka.gov.in) (opens in a new tab) |
| District Magistrate | scan uploaded to RERA | Source (rera.karnataka.gov.in) (opens in a new tab) |
| Conversion Certificate under section 95 of the KLR Act 1964 | scan uploaded to RERA | Source (rera.karnataka.gov.in) (opens in a new tab) |
| ESCOM/Electricity | scan uploaded to RERA | Source (rera.karnataka.gov.in) (opens in a new tab) |
| KWSSB/Water | scan uploaded to RERA | Source (rera.karnataka.gov.in) (opens in a new tab) |
| KSPCB | scan uploaded to RERA | Source (rera.karnataka.gov.in) (opens in a new tab) |
Documents uploaded to RERA
- Building or layout plan · Approved drawings from the planning authorityFiled on RERA ✓ — BBMP - Bruhat Bengaluru Mahanagara Palike · No. BBMP/AD.COM/MDP/0154/24-25 · dated 17 Aug 2024
- Commencement certificate · Permission to start buildingFiled on RERA ✓ — scanned copy uploaded; number and date not read yet
- Environment clearance · SEIAA KarnatakaNot on RERA yet
- Fire NOC · Karnataka Fire and Emergency ServicesNot on RERA yet
- Pollution board consent · KSPCBFiled on RERA ✓ — scanned copy uploaded; number and date not read yet
- Water and sewerage · BWSSBFiled on RERA ✓ — scanned copy uploaded; number and date not read yet
- Electricity · BESCOMFiled on RERA ✓ — scanned copy uploaded; number and date not read yet
- Height clearance · Airports Authority of IndiaNot on RERA yet
- Occupancy certificate (OC) · Issued only when the building is finishedNot on RERA yet — expected at completion
From the documents the promoter uploaded to Karnataka RERA, collected 20 Oct 2026. “Filed” means a document is on RERA — we have not checked its contents or validity. Not every approval applies to every project (for example, smaller projects may not need an environment clearance). The project page on RERA lists each upload.
Futurity Homes RERA complaints
No complaints listed on Karnataka RERA for this registration as on Source (rera.karnataka.gov.in) (opens in a new tab)
Court and consumer cases
We list case numbers, courts and outcomes only — never names of private individuals.
About Balaji Homes
- Promoter type
- Partnership Firm
- Projects on this site
- 1
- RERA complaints against promoter
- 0
- Company number (CIN)
- Not found in public records yet: CIN
From Karnataka RERA, as collected so far (20 Oct 2026). Complaints are those RERA lists against this promoter across all its projects.
Balaji Homes’s RERA recordBalaji Homes delivery record
- 1Projects in Bengaluru on RERA1 approved registration under Balaji Homes in Bengaluru Urban and Rural. Source (rera.karnataka.gov.in) (opens in a new tab)
- 76Homes registeredAs stated in each registrations.
- 0RERA complaintsas on Source (rera.karnataka.gov.in) (opens in a new tab)
- 0Complaints per 1,000 homes0 complaints ÷ 76 homes in its 1 registration on Karnataka RERA in Bengaluru.
Sources:Source (rera.karnataka.gov.in) (opens in a new tab)How we calculate this
What’s changed since Aug 2024
- 15 Oct 2026Quarterly update filed for Q1 2026-27: 71% built, 30 of 76 homes booked Source (rera.karnataka.gov.in) (opens in a new tab)
- 15 Oct 2026Quarterly update filed for Q2 2026-27: 77% built, 35 of 76 homes booked Source (rera.karnataka.gov.in) (opens in a new tab)
- 25 Apr 2026Quarterly update filed for Q4 2025-26: 66% built, 24 of 76 homes booked Source (rera.karnataka.gov.in) (opens in a new tab)
- 23 Apr 2026Quarterly update filed for Q3 2025-26: 58% built, 15 of 76 homes booked Source (rera.karnataka.gov.in) (opens in a new tab)
- 8 Jan 2025Registered with Karnataka RERA (PRM/KA/RERA/1251/446/PR/080125/007363); completion date 30 Oct 2026 Source (rera.karnataka.gov.in) (opens in a new tab)
- 10 Oct 2024Project start date in the RERA record Source (rera.karnataka.gov.in) (opens in a new tab)
- 17 Aug 2024Building plan approved by BBMP - Bruhat Bengaluru Mahanagara Palike (No. BBMP/AD.COM/MDP/0154/24-25) Source (rera.karnataka.gov.in) (opens in a new tab)
Newest first. No extension of the completion date is recorded on RERA. When the RERA crawl sees a new filing, complaint or extension, it is added here with its date.
Home loan EMI calculator
- Monthly EMI
- —
- Down payment
- —
- Loan amount
- —
- Total interest
- —
A calculation only, from the numbers you enter — not a loan offer.
All-in cost: GST, registration and other charges
The calculator loads when you scroll to it.
Assumptions
- Base price: the builder’s price is not published in a form we could collect — enter it from the cost sheet.
- GST 5% on the base price and charges — the usual rate for an under-construction home that is not “affordable housing” (1%).
- Stamp duty about 5.6% and registration 2% — the Karnataka rule (registration was raised from 1% to 2% on 31 Aug 2025). Calculated on the agreement value.
- Car parking, other charges and the maintenance deposit are not in the public record we collect; enter them from the builder’s cost sheet.
- Loan on the agreement value (banks usually lend up to 75–90%); EMI is the standard reducing-balance formula. Example rate only — use your bank’s quote.
Futurity Homes FAQs
What is Futurity Homes?
Futurity Homes is a residential project by Balaji Homes located in Bilishivale, Bengaluru East, PIN code 560077.
How many homes are in Futurity Homes?
The project has 76 homes in 1 tower with a maximum of 3 floors.
What home types are available in Futurity Homes?
The project offers 2 BHK and 3 BHK homes. There are 24 two-bedroom homes and 52 three-bedroom homes.
What is the carpet area range in Futurity Homes?
2 BHK homes have carpet area from 479 to 803 sq ft, and 3 BHK homes have carpet area from 790 to 1,116 sq ft.
When will Futurity Homes be completed?
The project is expected to be completed on 30 October 2026 as per RERA records.
What is the RERA registration number for Futurity Homes?
The project is registered with RERA registration number PRM/KA/RERA/1251/446/PR/080125/007363, registered on 8 January 2025.
How many homes are booked in Futurity Homes?
As of the latest quarterly update for Q2 2026-27, 35 homes have been booked out of 76 homes.
What is the construction status of Futurity Homes?
As of Q2 2026-27 (quarter ended 30 September 2026), the project is 77% complete.
Are there any RERA complaints against Futurity Homes?
There are no RERA complaints filed against this project as per RERA records.
What is Balaji Homes' record with other projects?
Balaji Homes has 1 project in the Karnataka RERA Bengaluru records and no complaints filed against the builder.
Written by AI from the RERA record above on 20 Oct 2026. Answers use only that record; check them against the source before you decide.
Questions about Futurity Homes
No questions published yet. Ask the first one: you get an instant answer from this page’s public record, and our team follows up on anything the record does not show.
Bought a home from Balaji Homes? Review the builder.
Reviews of Balaji Homes by verified buyers
No verified reviews of Balaji Homes yet. If you bought a home from them, your review helps other buyers.
How reviews work: only buyers and owners can review; we confirm each purchase by phone before publishing, publish positive and negative reviews alike, never accept payment for reviews, and the builder may reply.
Sources and last checked dates
Collected on 20 Oct 2026 by AI research agents reading public pages. Facts are written in our own words. Not found yet: price; court cases; landmarks; specifications; news.
How to check on RERA: On rera.karnataka.gov.in/viewAllProjects, type the registration number in 'Registration No', press Search, then click the 'View Project Details' icon. Complaints open from the 'Complaints / Litigation' icon in the same row. Registration number: PRM/KA/RERA/1251/446/PR/080125/007363.
- RERA record last checked: 20 Oct 2026
- Last change in the record (registration, quarterly filing or complaint): 20 Oct 2026
How this page is made: software builds it from public records (Karnataka RERA filings, OpenStreetMap, the builder’s own website). AI is used only to read filings into fields and to write the plain-English summary and FAQ answers, which are checked against the record. Facts are checked automatically against the RERA filing. Methodology · How we earn · Report an error
More new projects nearby
Hosakerehalli, Rajarajeshwari NagarArtist’s impressionUnder constructionRERA registeredBuyers’ group openSobha Valley View - Heritage
by Sobha
Price: Price on requestGet brochure & price →
- 2 BHK, 3 BHK
- 917 – 1,267 sq ft
- Feb 2019
RERA not updated since promised Feb 2019 · 624 homes · 19 RERA complaints
Be one of the first 10 buyers in this groupFounding members — it’s free
Join group for Sobha Valley View - Heritage
Agara, HSR LayoutArtist’s impressionUnder constructionRERA registeredBuyers’ group openSterling Infinia
by Sterling
Price: Price on requestGet brochure & price →
- 1 BHK, 2 BHK, 3 BHK, 4 BHK
- 904 – 2,336 sq ft
- Sep 2026 (extended)
RERA not updated since promised Sep 2026 · 344 homes · 4 RERA complaints
Be one of the first 10 buyers in this groupFounding members — it’s free
Join group for Sterling Infinia
Kammanahalli, near Begur RoadUnder constructionRERA registeredBuyers’ group openSound of Water Phase 3
by Puravankara
Price: Price on requestGet brochure & price →
- 3 BHK, 4 BHK
- 1,787 – 2,749 sq ft
- Jun 2027
60 homes
Be one of the first 10 buyers in this groupFounding members — it’s free
Join group for Sound of Water Phase 3