Icon Micasa at a glance
- Possession (RERA)Dec 2026 ExtendedWas Dec 2024 · Karnataka RERA
- Construction80% built · on pace for Aug 2027 7 mo after RERA dateRERA filing to 30 Jun 2026; estimate from average pace
- Homes booked163 of 170 (96%)RERA update · as on 30 Jun 2026
- RERA complaints (project)None listedKarnataka RERA · as on 12 Oct 2026
- Approvals filed7 of 9 on RERAKarnataka RERA uploads · 12 Oct 2026
- Nearest metroDelta Electronics Bommasandra · 5.14 kmstraight line · OpenStreetMap, 5 Oct 2026
- Airport driveapprox. 186 min at peak46.01 km straight line · estimate
- Nearest lakeKyalasanahalli Lake · 1,405 mFrom the RERA map point · OpenStreetMap, 5 Oct 2026
Project summary
Icon Micasa is a residential project by Icon Infra Shelters India Private Limited in Bandenallasandra, Bengaluru with 170 homes, registered with Karnataka RERA. The completion date on RERA is 31 Dec 2026.
Facts collected on 12 Oct 2026 from public records — each linked to its source. Free for buyers. If you book through us, the builder pays us a commission.
Icon Micasa buyers’ group: join to ask for a group price
No one has joined yet. Be one of the first 10 buyers in this group — the founding members.
Join free. When enough buyers have joined, our agent partner asks Icon Infra Shelters India Private Limited for a group price — for example a lower price, an easier payment plan or waived charges. Nothing is promised: you see what the builder offers and book directly with the builder if you want to. Free for buyers. If you book through us, the builder pays us a commission.
- Gathering buyers
- Talking to the builder
- Group offer
- Group site visit
- Booking
0 buyers have joined · 0 committed
Committed buyers have confirmed their budget, home type and timeline with us on a call; builders negotiate with them. Joining is free and never obliges you to buy.
Join the Icon Micasa buyers’ groupHow group buying works
See it for yourself
Visit the site with our team, or get a call to clear your questions. Free, no obligation.
Key facts: home types, towers, land and possession
- Home types
- 3 BHK
- Carpet area
- 606 sq ft
- Towers
- 1
- Floors
- 8
- Total homes
- 170
- Land
- 1.88 acres
- Possession (extended)
- Dec 2026
- Built (RERA update)
- 80%
Icon Micasa RERA number and registration details
- RERA number
- PRM/KA/RERA/1251/310/PR/110422/004823
- Registered on
- 11 Apr 2022
- Promised completion
- 30 Dec 2024
- Extended to
- 31 Dec 2026
- RERA status
- New launch
- Homes booked
- 163 of 170 as on
- Price
- Not found in public records yet: price
- Project type
- Residential
Towers and blocks (RERA filing)
| Tower | Floors | Basements | Homes |
|---|---|---|---|
| ICONEST 7 | 8 | 0 | 170 |
A dash (—) means the filing did not state that value.
Summary in plain English
Icon Micasa is a residential project by Icon Infra Shelters India Private Limited in Bandenallasandra, Bengaluru South. It has 170 three-bedroom flats across one 8-storey tower, with a RERA completion date of 31 December 2026.
Written by AI from the RERA record above on 5 Oct 2026. Every number in it was checked against that record; if anything differs, the record wins.
Open space, home loans, escrow and other details
- Open space
- 74.4% of land
- Water and power
- Water source filed with RERA: BoreWell
- Home loans: approved banks
- Not found in public records yet: bank approvals
- Payment plans
- Not found in public records yet: payment plans
- Maintenance
- Not found in public records yet: maintenance
- Car parking
- Not found in public records yet: car parking charge
- Escrow bank (RERA)
- Axis Bank, HSR LAYOUT SECTOR IV
- Building plan (RERA)
- BMRDA - Bangalore Metropolitan Region Development Authority · No. APA/LAO/265/2021-22 · dated 28 Oct 2021
- Project cost declared to RERA
- ₹75.55 Cr
Open area as a share of the land, from the areas filed with RERA (includes driveways and landscaped areas).
Amenities
- Electricity
- CCTV Surveillance
- Community Hall
- Outdoor Sports facility
- Swimming Pool
- Gym
- Power Backup
- Water and Sanitation
Amenities and internal works as filed by the promoter with Karnataka RERA; we have not visited the site.
Icon Micasa location and address
- Address
- Survey Number 11, Bandenallasandra Village, , Jigani Hobli, Anekal Taluk, Bangalore , Bengaluru South , Bengaluru Urban, Karnataka - 560105
- Village (RERA)
- Bandenallasandra
- Locality
- Near Electronic City Phase 2Also known as Electronics City Phase 2, E-City Phase 2
- PIN code
- 560105
- City
- Bengaluru
- State
- Karnataka
- Coordinates
- 12.79019, 77.65162
Distances to landmarks
Not found in public records yet: landmarksAbout Bandenallasandra
Not found in public records yet: locality factsCommute times to tech parks and the airport
| To | Straight line | Peak-hour drive (estimate) |
|---|---|---|
| Electronic City Phase 1Map point on OpenStreetMap (opens in a new tab) | 6.77 km | approx. 27 min |
| Outer Ring Road tech corridor (RMZ Ecospace, Bellandur)Map point on OpenStreetMap (opens in a new tab) | 15.19 km | approx. 62 min |
| KSR Bengaluru City railway station (Majestic)Map point on OpenStreetMap (opens in a new tab) | 22.72 km | approx. 92 min |
| ITPL, Whitefield (main gate)Map point on OpenStreetMap (opens in a new tab) | 23.86 km | approx. 97 min |
| Manyata Tech ParkMap point on OpenStreetMap (opens in a new tab) | 28.89 km | approx. 117 min |
| Kempegowda International AirportMap point on OpenStreetMap (opens in a new tab) | 46.01 km | approx. 186 min |
How we calculate
Straight line: from the project’s map point on RERA to the destination’s point on OpenStreetMap.
Peak-hour drive is a rough estimate, not a route: straight line × 1.35 for the road network, at 20 km/h. Real times vary a lot with the route and the hour.
Sources:Source (openstreetmap.org) (opens in a new tab)How we calculate this
Schools and hospitals nearby
Within 2 km
- 1Schools and colleges1 schools, 0 colleges, 0 kindergartens
- 0Hospitals and clinics0 hospitals, 0 clinics
Nearest schools and colleges
- Achiever's Academy · 1.95 km
Places as mapped on OpenStreetMap (amenity=school, college, kindergarten, university; hospital, clinic), counted within 2 km in a straight line of the RERA map point. Volunteers map these, so some places may be missing or closed. Places data © OpenStreetMap contributors, extract of 5 Oct 2026.
Nearest metro station and railway
- Delta Electronics Bommasandra (ಡೆಲ್ಟಾ ಎಲೆಕ್ಟ್ರಾನಿಕ್ಸ್ ಬೊಮ್ಮಸಂದ್ರ)Open now — nearest operating metro station5.14 km
- Heelalige (ಹೀಲಲಿಗೆ ರೈಲು ನಿಲ್ದಾಣ)Nearest railway station6.94 km
Straight-line distances from the RERA map point to the station points mapped on OpenStreetMap; status (open or under construction) as tagged there. Places data © OpenStreetMap contributors, extract of 5 Oct 2026.
Lake and lake-buffer check
The nearest mapped lake is Kyalasanahalli Lake, 1,405 m from the project’s RERA map point.
The site boundary is not published as a shape, so its nearest edge can be closer than this point. Whether any building sits inside a lake buffer can only be checked on the approved plan.
- Kyalasanahalli Lake on OpenStreetMap (opens in a new tab) 1,405 m
- Nanjapura Lake on OpenStreetMap (opens in a new tab) 1,609 m
The buffer rule
Bengaluru’s lake buffer rule has changed over time: the National Green Tribunal ordered a 75 m buffer in May 2016; the Supreme Court set that order aside on 5 March 2019, leaving the 30 m buffer of the Revised Master Plan 2015. Check the current rule and the approved plan before relying on either number.
- LiveLaw: SC sets aside NGT order enlarging buffer zones (2019) (livelaw.in) (opens in a new tab)
- Citizen Matters: Shrinking lake buffers (citizenmatters.in) (opens in a new tab)
Shortest distance from the RERA map point to the mapped water edge (OpenStreetMap water polygons tagged lake or reservoir, or named lake/kere/tank). Mapped shorelines can differ from the revenue-record boundary of a lake. Places data © OpenStreetMap contributors, extract of 5 Oct 2026.
Sources:Source (openstreetmap.org) (opens in a new tab)Source (livelaw.in) (opens in a new tab)Source (citizenmatters.in) (opens in a new tab)How we calculate this
Satellite time-lapse of the site
Satellite photos load when you scroll to them.
Photos from Esri World Imagery Wayback, centred on the project’s map point; dates are the capture dates in Esri’s metadata. Loaded from Esri when you scroll here.
Sources:Source (livingatlas.arcgis.com) (opens in a new tab)
Icon Micasa floor plans, brochure and elevations
Documents the builder uploaded to Karnataka RERA, shown as filed. Tap a page to see it full size; the full PDF opens on the RERA website.
Brochure3 pages

BrochureFull PDF on RERA 

Floor plans2 files

Approved Building/Plotting PlanFull PDF on RERA 
GROUND FLOOR PLANFiled 13 Jan 2022 · Full PDF on RERA
Approved layout plan2 files

Approved Layout PlanFull PDF on RERA 
Existing Layout PlanFull PDF on RERA
| Home type | Carpet area | Homes |
|---|---|---|
| 3 BHK | 606 sq ft | 170 |
| 3 BHK flats | 606 sq ft | 170 |
Home types, counts and carpet areas as filed with Karnataka RERA (carpet area, not super built-up).
We have not collected floor-plan drawings; the builder’s sales team can share them.
Icon Micasa possession date and construction status
Promoter’s quarterly update to RERA for Q1 2026-27, submitted 2026-07-15.
Units sold and unsold, from RERA (Q1 2026-27)
| Type | Homes | Booked | Available |
|---|---|---|---|
| 3 BHK | 170 | 163 | 7 |
As reported by the promoter in the quarterly update to RERA, not verified by us.
Timeline
- 31 Jan 2022Project start date given to RERA
- 11 Apr 2022Registered with Karnataka RERA
- 30 Dec 2024Completion date given at registration
- 30 Dec 2025Section 6 Extension: completion date moved to this date
- 31 Dec 2026Further Extension: completion date moved to this date
Construction pace from RERA quarterly filings
At the average pace so far, construction would reach 100% around Aug 2027 — about 7 months after the completion date on RERA (31 Dec 2026).
At the pace between the 3 quarterly filings we have (65% → 80% in 6 months), it would be around Feb 2027 — about 2 months after the RERA date.
- Filed on RERA
- Average pace since start
- Pace between filings (and 0% assumed at the start date)
- RERA completion date
Quarterly filings
| Quarter | Filed on | Built | Homes booked |
|---|---|---|---|
| Q1 2026-27to 30 Jun 2026 | 15 Jul 2026 | 80% | 163 of 170 |
| Q4 2025-26to 31 Mar 2026 | 15 Apr 2026 | 70% | 155 of 170 |
| Q3 2025-26to 31 Dec 2025 | 15 Jan 2026 | 65% | 151 of 170 |
How we calculate
Average pace = % built ÷ months since the start date in the RERA record. Here: 80% ÷ 52.9 months (31 Jan 2022 to 30 Jun 2026) = 1.5% a month.
Estimated finish = latest filing date + (100 − % built) ÷ pace = 30 Jun 2026 + 20 ÷ 1.5 = 13.2 months → Aug 2027. This is an estimate, not a date from the builder or RERA.
Pace between filings = (80% − 65%) ÷ 5.9 months = 2.5% a month.
A straight line is a simplification: the builder reports one overall %, which mixes excavation, structure and finishing, and work rarely moves at a constant speed. The % values are the promoter’s own figures filed with RERA, not checked by us. Promoter’s quarterly update to RERA for Q1 2026-27, submitted 2026-07-15.
Sources:Source (rera.karnataka.gov.in) (opens in a new tab)How we calculate this
Approvals and documents checklist
15 rows: approvals. Scroll inside the table to see them all.
| Approval | Authority | Source |
|---|---|---|
| Building plan | BMRDA - Bangalore Metropolitan Region Development Authority · No. APA/LAO/265/2021-22 · dated 2021-10-28 | Source (rera.karnataka.gov.in) (opens in a new tab) |
| Land conversion | Deputy Commissioner, Bangalore · No. ALN(AJ)SR 205/2014-15 · dated 2015-06-04 | Source (rera.karnataka.gov.in) (opens in a new tab) |
| Commencement Certificate | scan uploaded to RERA | Source (rera.karnataka.gov.in) (opens in a new tab) |
| Electricity Permission Letter | scan uploaded to RERA | Source (rera.karnataka.gov.in) (opens in a new tab) |
| Water Permission Letter | scan uploaded to RERA | Source (rera.karnataka.gov.in) (opens in a new tab) |
| Approved Layout Plan | scan uploaded to RERA | Source (rera.karnataka.gov.in) (opens in a new tab) |
| Approved Building/Plotting Plan | scan uploaded to RERA | Source (rera.karnataka.gov.in) (opens in a new tab) |
| Approved Section Of Building/Infrastructure Plan of Plotting | scan uploaded to RERA | Source (rera.karnataka.gov.in) (opens in a new tab) |
| Conversion Certificate under section 95 of the KLR Act 1964 | scan uploaded to RERA | Source (rera.karnataka.gov.in) (opens in a new tab) |
| ESCOM/Electricity | scan uploaded to RERA | Source (rera.karnataka.gov.in) (opens in a new tab) |
| KWSSB/Water | scan uploaded to RERA | Source (rera.karnataka.gov.in) (opens in a new tab) |
| Approval/NOC under section 109 of KLR Act 1961 | scan uploaded to RERA | Source (rera.karnataka.gov.in) (opens in a new tab) |
| Fire Force Department | scan uploaded to RERA | Source (rera.karnataka.gov.in) (opens in a new tab) |
| Airport Authority of India | scan uploaded to RERA | Source (rera.karnataka.gov.in) (opens in a new tab) |
| KSPCB | scan uploaded to RERA | Source (rera.karnataka.gov.in) (opens in a new tab) |
Documents uploaded to RERA
- Building or layout plan · Approved drawings from the planning authorityFiled on RERA ✓ — BMRDA - Bangalore Metropolitan Region Development Authority · No. APA/LAO/265/2021-22 · dated 28 Oct 2021
- Commencement certificate · Permission to start buildingFiled on RERA ✓ — scanned copy uploaded; number and date not read yet
- Environment clearance · SEIAA KarnatakaNot on RERA yet
- Fire NOC · Karnataka Fire and Emergency ServicesFiled on RERA ✓ — scanned copy uploaded; number and date not read yet
- Pollution board consent · KSPCBFiled on RERA ✓ — scanned copy uploaded; number and date not read yet
- Water and sewerage · BWSSBFiled on RERA ✓ — scanned copy uploaded; number and date not read yet
- Electricity · BESCOMFiled on RERA ✓ — scanned copy uploaded; number and date not read yet
- Height clearance · Airports Authority of IndiaFiled on RERA ✓ — scanned copy uploaded; number and date not read yet
- Occupancy certificate (OC) · Issued only when the building is finishedNot on RERA yet — expected at completion
From the documents the promoter uploaded to Karnataka RERA, collected 12 Oct 2026. “Filed” means a document is on RERA — we have not checked its contents or validity. Not every approval applies to every project (for example, smaller projects may not need an environment clearance). The project page on RERA lists each upload.
Icon Micasa RERA complaints
No complaints listed on Karnataka RERA for this registration as on Source (rera.karnataka.gov.in) (opens in a new tab)
Court and consumer cases
We list case numbers, courts and outcomes only — never names of private individuals.
About Icon Infra Shelters India Private Limited
- Promoter type
- Company
- Projects on this site
- 2
- RERA complaints against promoter
- 0
- Company number (CIN)
- U45202KA2012PTC064358
From Karnataka RERA, as collected so far (12 Oct 2026). Complaints are those RERA lists against this promoter across all its projects.
Icon Infra Shelters India Private Limited’s RERA recordIcon Infra Shelters India Private Limited delivery record
- 2Projects in Bengaluru on RERA2 approved registrations under Icon Infra Shelters India Private Limited in Bengaluru Urban and Rural. Source (rera.karnataka.gov.in) (opens in a new tab)
- 250Homes and plots registeredAs stated in each registrations.
- 0RERA complaintsas on Source (rera.karnataka.gov.in) (opens in a new tab)
- 0Complaints per 1,000 homes and plots0 complaints ÷ 250 homes and plots in its 2 registrations on Karnataka RERA in Bengaluru.
- 1Completion filed on RERARegistrations where the promoter applied to RERA for completion; 0 with an occupancy certificate on RERA.
- 0 of 1Filed by the date given at registrationMedian gap 0.5 months (on-time ones count as 0). The completion application can come after handover, so this is an upper bound on lateness.
Completion filed on RERA
| Project | Date at registration | Completion filed | Gap |
|---|---|---|---|
| Grand Icon 3 | 30 Apr 2026 | 16 May 2026 | 1 months after |
Measured against the completion date given at registration; many projects had RERA extensions (including the COVID-period extension), shown under the date.
Sources:Source (rera.karnataka.gov.in) (opens in a new tab)How we calculate this
What’s changed since Oct 2021
- 31 Dec 2026Completion date extended to 31 Dec 2026 Source (rera.karnataka.gov.in) (opens in a new tab)
- 15 Jul 2026Quarterly update filed for Q1 2026-27: 80% built, 163 of 170 homes booked Source (rera.karnataka.gov.in) (opens in a new tab)
- 15 Apr 2026Quarterly update filed for Q4 2025-26: 70% built, 155 of 170 homes booked Source (rera.karnataka.gov.in) (opens in a new tab)
- 15 Jan 2026Quarterly update filed for Q3 2025-26: 65% built, 151 of 170 homes booked Source (rera.karnataka.gov.in) (opens in a new tab)
- 11 Apr 2022Registered with Karnataka RERA (PRM/KA/RERA/1251/310/PR/110422/004823); completion date 30 Dec 2024 Source (rera.karnataka.gov.in) (opens in a new tab)
- 31 Jan 2022Project start date in the RERA record Source (rera.karnataka.gov.in) (opens in a new tab)
- 28 Oct 2021Building plan approved by BMRDA - Bangalore Metropolitan Region Development Authority (No. APA/LAO/265/2021-22) Source (rera.karnataka.gov.in) (opens in a new tab)
Newest first. When the RERA crawl sees a new filing, complaint or extension, it is added here with its date.
Home loan EMI calculator
- Monthly EMI
- —
- Down payment
- —
- Loan amount
- —
- Total interest
- —
A calculation only, from the numbers you enter — not a loan offer.
All-in cost: GST, registration and other charges
The calculator loads when you scroll to it.
Assumptions
- Base price: the builder’s price is not published in a form we could collect — enter it from the cost sheet.
- GST 5% on the base price and charges — the usual rate for an under-construction home that is not “affordable housing” (1%).
- Stamp duty about 5.6% and registration 2% — the Karnataka rule (registration was raised from 1% to 2% on 31 Aug 2025). Calculated on the agreement value.
- Car parking, other charges and the maintenance deposit are not in the public record we collect; enter them from the builder’s cost sheet.
- Loan on the agreement value (banks usually lend up to 75–90%); EMI is the standard reducing-balance formula. Example rate only — use your bank’s quote.
Icon Micasa FAQs
What is the RERA registration number for Icon Micasa?
The RERA registration number is PRM/KA/RERA/1251/310/PR/110422/004823, registered on 11 April 2022.
How many homes are in Icon Micasa and what are the carpet areas?
Icon Micasa has 170 homes, all 3 BHK flats with a carpet area of 606 sq ft.
What is the completion date for Icon Micasa?
According to RERA, the completion date is 31 December 2026.
What is the construction progress of Icon Micasa?
As of Q1 2026-27 (quarter ended 30 June 2026), the project is 80% complete.
How many homes have been booked in Icon Micasa?
As of Q1 2026-27, 163 homes have been booked out of 170.
Where is Icon Micasa located?
Icon Micasa is located in Bandenallasandra, Bengaluru South, PIN code 560105.
Are there any RERA complaints against Icon Micasa?
There are no RERA complaints on record for this project.
Does the builder have complaints on other projects?
No RERA complaints are on record against Icon Infra Shelters India Private Limited across all their projects.
How many projects does the builder have in Bengaluru?
Icon Infra Shelters India Private Limited has 5 projects in the Bengaluru RERA records.
What bank is handling the escrow for Icon Micasa?
Axis Bank is the escrow bank for this project.
Written by AI from the RERA record above on 5 Oct 2026. Answers use only that record; check them against the source before you decide.
Questions about Icon Micasa
No questions published yet. Ask the first one: you get an instant answer from this page’s public record, and our team follows up on anything the record does not show.
Bought a home from Icon Infra Shelters India Private Limited? Review the builder.
Reviews of Icon Infra Shelters India Private Limited by verified buyers
No verified reviews of Icon Infra Shelters India Private Limited yet. If you bought a home from them, your review helps other buyers.
How reviews work: only buyers and owners can review; we confirm each purchase by phone before publishing, publish positive and negative reviews alike, never accept payment for reviews, and the builder may reply.
Similar projects within 5 km
| Project | Distance | Homes | Possession (RERA) | Built | Complaints | Price |
|---|---|---|---|---|---|---|
| Skyline Havensv infra homes | 0.1 km | 88 | Jan 2028 | 97% | 0 | Not collected |
| Sri Sai Nandana RegalSri Sai Nandana Builders | 0.9 km | 108 | Dec 2030 | 37% | 0 | Not collected |
| Gina ArtizeGina Engineering Company Private Limited | 1.5 km | 134 | Nov 2025 | 100% | 0 | Not collected |
| SimhadriM/s.SIGNIFA SIMHADRI PROJECTS | 1.8 km | 190 | Sep 2029 | 15% | 0 | Not collected |
| Evershine StoneParkEvershine Dwellings Pvt Ltd | 2.6 km | 117 | Sep 2030 | 18% | 0 | Not collected |
| Villa BellissimoUrbanize Land Holdings Private Limited | 2.7 km | 103 | Dec 2028 | 50% | 0 | Not collected |
Projects of the same kind within 5 km in a straight line of this project’s RERA map point, nearest first. % built is the promoter’s latest quarterly figure on RERA (shown for single-registration projects); prices are from the builder’s own website where we found one.
Sources and last checked dates
Collected on 12 Oct 2026 by AI research agents reading public pages. Facts are written in our own words. Not found yet: price; court cases; landmarks; specifications; news.
How to check on RERA: On rera.karnataka.gov.in/viewAllProjects, type the registration number in 'Registration No', press Search, then click the 'View Project Details' icon. Complaints open from the 'Complaints / Litigation' icon in the same row. Registration number: PRM/KA/RERA/1251/310/PR/110422/004823.
- RERA record last checked: 12 Oct 2026
- Last change in the record (registration, quarterly filing or complaint): 15 Jul 2026
How this page is made: software builds it from public records (Karnataka RERA filings, OpenStreetMap, the builder’s own website). AI is used only to read filings into fields and to write the plain-English summary and FAQ answers, which are checked against the record. Facts are checked automatically against the RERA filing. Methodology · How we earn · Report an error
More new projects nearby
Bandenallasandra, near Electronic City Phase 2Under constructionRERA registeredBuyers’ group openSkyline Haven
by sv infra homes
Price: Price on requestGet brochure & price →
- 2 BHK, 3 BHK
- 583 – 770 sq ft
- Jan 2028
88 homes
Be one of the first 10 buyers in this groupFounding members — it’s free
Join group for Skyline Haven
BandenallasandraUnder constructionRERA registeredBuyers’ group openSri Sai Nandana Regal
by Sri Sai Nandana Builders
Price: Price on requestGet brochure & price →
- 2 BHK, 3 BHK
- 718 – 1,140 sq ft
- Dec 2030
108 homes
Be one of the first 10 buyers in this groupFounding members — it’s free
Join group for Sri Sai Nandana Regal
YarandahalliReady to moveRERA registeredBuyers’ group openGina Artize
by Gina Engineering Company
Price: Price on requestGet brochure & price →
- 1 BHK, 2 BHK, 3 BHK
- 495 – 947 sq ft
- Nov 2025
134 homes
Be one of the first 10 buyers in this groupFounding members — it’s free
Join group for Gina Artize