Shantivan at a glance
- Completion (RERA)Oct 2028Karnataka RERA
- Construction35% built · on pace for Aug 2029 9 mo after RERA dateRERA filing to 30 Jun 2026; estimate from average pace
- RERA complaints (project)None listedKarnataka RERA · as on 16 Oct 2026
- Approvals filed4 of 9 on RERAKarnataka RERA uploads · 16 Oct 2026
- Nearest metroAirport City · 8.9 km (under construction)Open now: Krishnarajapura, 30.85 km · straight line · OpenStreetMap, 5 Oct 2026
- Airport driveapprox. 37 min at peak9.14 km straight line · estimate
Project summary
Shantivan is a plotted development by Sidharth Madhuban in Bidaluru, Bengaluru with 80 plots, registered with Karnataka RERA. The completion date on RERA is 31 Oct 2028.
Facts collected on 16 Oct 2026 from public records — each linked to its source. Free for buyers. If you book through us, the developer pays us a commission.
Shantivan buyers’ group: join to ask for a group price
No one has joined yet. Be one of the first 10 buyers in this group — the founding members.
Join free. When enough buyers have joined, our agent partner asks Sidharth Madhuban for a group price — for example a lower price, an easier payment plan or waived charges. Nothing is promised: you see what the developer offers and book directly with the developer if you want to. Free for buyers. If you book through us, the developer pays us a commission.
- Gathering buyers
- Talking to the developer
- Group offer
- Group site visit
- Booking
0 buyers have joined · 0 committed
Committed buyers have confirmed their budget, plot size and timeline with us on a call; developers negotiate with them. Joining is free and never obliges you to buy.
Join the Shantivan buyers’ groupHow group buying works
See it for yourself
Visit the site with our team, or get a call to clear your questions. Free, no obligation.
Key facts: plot sizes, approval, land and completion
- Plot sizes (feet)
- 30×40, 30×45, 30×50
- Plot area
- 1,199 – 2,285 sq ft
- Total plots
- 80
- Layout approved by
- STRR Planning Authority
- Land
- Not found in public records yet: land area
- Land conversion orders
- 2
- Completion (RERA)
- Oct 2028
- Development (RERA update)
- 35%
Plot sizes (RERA filing)
| Size (feet) | Area | Plots |
|---|---|---|
| 30×40 | 1,200 sq ft | 9 |
| 30×45 | 1,350 sq ft | 20 |
| 30×50 | 1,500 sq ft | 32 |
| Odd-sized (irregular) | varies | 19 |
Sizes as filed with RERA, converted from metres to feet (9.14 m = 30 ft, 12.19 m = 40 ft). Ask the developer which plots are still unsold.
Approving authority as filed: Satellite Town Ring Road Planning Authority.
Land conversion orders (RERA filing)
| Survey no. | Converted for | Order | By |
|---|---|---|---|
| 269 | Residential | No. 490886, 25 Apr 2023 | Deputy commissioner Banglore rural |
| 270/1 | Residential | No. 531176, 30 Aug 2023 | Deputy commissioner banglore rural |
RERA does not cover each plot’s khata. Ask the developer for the khata and title documents and have a lawyer check them before paying an advance.
Shantivan RERA number and registration details
- RERA number
- PRM/KA/RERA/1250/303/PR/160725/007932
- Registered on
- 16 Jul 2025
- Promised completion
- 31 Oct 2028
- Extended to
- No extension recorded
- RERA status
- Under construction
- Plots booked
- Not found in public records yet: plots booked
- Price
- Not found in public records yet: price
- Project type
- Plotted
Summary in plain English
Shantivan is a plotted layout by Sidharth Madhuban in Bidaluru, Devanahalli taluk, with 80 plots across various sizes. The layout was approved by STRR Planning Authority and is registered with RERA. Completion is planned for 31 October 2028.
Written by AI from the RERA record above on 7 Oct 2026. Every number in it was checked against that record; if anything differs, the record wins.
Open space, loans, escrow and other details
- Open space
- Not found in public records yet: open space
- Water and power
- Water source filed with RERA: Local Authority
- Plot loans: approved banks
- Not found in public records yet: bank approvals
- Payment plans
- Not found in public records yet: payment plans
- Maintenance
- Not found in public records yet: maintenance
- Car parking
- Not found in public records yet: car parking charge
- Escrow bank (RERA)
- Karnataka Bank Ltd., NTI Layout ,Bengaluru
- Building plan (RERA)
- Satellite Town Ring Road Planning Authority · No. STRRPA/TP/LAO/12/23-24 · dated 23 Oct 2024
- Project cost declared to RERA
- ₹7.14 Cr
Amenities
Shantivan location and address
- Address
- SY NO 269 AND 270/1 OF BIDALURU VILLAGE, KASABA HOBLI , Devanahalli, Bengaluru , Devanahalli , Bengaluru Rural, Karnataka - 562110
- Village (RERA)
- Bidaluru
- Locality
- Near Devanahalli
- PIN code
- 562110
- City
- Bengaluru
- State
- Karnataka
- Coordinates
- 13.27734, 77.67375
Distances to landmarks
Not found in public records yet: landmarksAbout Bidaluru
Not found in public records yet: locality factsCommute times to tech parks and the airport
| To | Straight line | Peak-hour drive (estimate) |
|---|---|---|
| Kempegowda International AirportMap point on OpenStreetMap (opens in a new tab) | 9.14 km | approx. 37 min |
| Manyata Tech ParkMap point on OpenStreetMap (opens in a new tab) | 26.15 km | approx. 106 min |
| ITPL, Whitefield (main gate)Map point on OpenStreetMap (opens in a new tab) | 32.95 km | approx. 133 min |
| KSR Bengaluru City railway station (Majestic)Map point on OpenStreetMap (opens in a new tab) | 35.13 km | approx. 142 min |
| Outer Ring Road tech corridor (RMZ Ecospace, Bellandur)Map point on OpenStreetMap (opens in a new tab) | 39.33 km | approx. 159 min |
| Electronic City Phase 1Map point on OpenStreetMap (opens in a new tab) | 47.56 km | approx. 193 min |
How we calculate
Straight line: from the project’s map point on RERA to the destination’s point on OpenStreetMap.
Peak-hour drive is a rough estimate, not a route: straight line × 1.35 for the road network, at 20 km/h. Real times vary a lot with the route and the hour.
Sources:Source (openstreetmap.org) (opens in a new tab)How we calculate this
Nearest metro station and railway
- Airport City (ವಿಮಾನ ನಿಲ್ದಾಣ ನಗರ)Blue Line metro, under construction8.9 km
- KIAL Terminals (ಕೆಐಎಬಿ ವಿಮಾನ ನಿಲ್ದಾಣ ಟರ್ಮಿನಲ್ಸ್)Blue Line metro, under construction9.77 km
- Doddajala (ದೊಡ್ಡಜಾಲ)Blue Line metro, under construction10.38 km
- Krishnarajapura (ಕೃಷ್ಣರಾಜಪುರ (ಕೆ.ಆರ್.ಪುರ))Open now — nearest operating metro station30.85 km
- Devanahalli (ದೇವನಹಳ್ಳಿ)Nearest railway station4.77 km
Straight-line distances from the RERA map point to the station points mapped on OpenStreetMap; status (open or under construction) as tagged there. Places data © OpenStreetMap contributors, extract of 5 Oct 2026.
Satellite time-lapse of the site
Satellite photos load when you scroll to them.
Photos from Esri World Imagery Wayback, centred on the project’s map point; dates are the capture dates in Esri’s metadata. Loaded from Esri when you scroll here.
Sources:Source (livingatlas.arcgis.com) (opens in a new tab)
Shantivan layout plan and plot types as filed
Documents the developer uploaded to Karnataka RERA, shown as filed. Tap a page to see it full size; the full PDF opens on the RERA website.
Brochure3 pages

BrochureFull PDF on RERA 

Approved layout plan2 files

Approved Layout Plan/Demarcation PlanFull PDF on RERA 
Provisional Layout PlanFiled 8 May 2025 · Full PDF on RERA
| Plot type (as filed) | Area | Plots |
|---|---|---|
| Plot 9.14 m × 12.19 m | — | 9 |
| Plot 9.14 m × 13.71 m | — | 20 |
| Plot 9.14 m × 15.24 m | — | 32 |
| Odd-shaped plots | — | 19 |
Plot types and counts as filed with Karnataka RERA.
We have not collected the layout plan drawing; the developer’s sales team can share it.
Shantivan completion date and development status
Promoter’s quarterly update to RERA for Q1 2026-27, submitted 2026-07-15.
Timeline
- 23 Oct 2024Project start date given to RERA
- 16 Jul 2025Registered with Karnataka RERA
- 31 Oct 2028Completion date given at registration
Construction pace from RERA quarterly filings
At the average pace so far, construction would reach 100% around Aug 2029 — about 9 months after the completion date on RERA (31 Oct 2028).
At the pace between the 3 quarterly filings we have (30% → 35% in 6 months), it would be around Dec 2032 — about 49 months after the RERA date.
- Filed on RERA
- Average pace since start
- Pace between filings (and 0% assumed at the start date)
- RERA completion date
Quarterly filings
| Quarter | Filed on | Developed | Plots booked |
|---|---|---|---|
| Q1 2026-27to 30 Jun 2026 | 15 Jul 2026 | 35% | — |
| Q4 2025-26to 31 Mar 2026 | 14 Apr 2026 | 35% | — |
| Q3 2025-26to 31 Dec 2025 | 23 Jan 2026 | 30% | — |
How we calculate
Average pace = % built ÷ months since the start date in the RERA record. Here: 35% ÷ 20.2 months (23 Oct 2024 to 30 Jun 2026) = 1.7% a month.
Estimated finish = latest filing date + (100 − % built) ÷ pace = 30 Jun 2026 + 65 ÷ 1.7 = 37.5 months → Aug 2029. This is an estimate, not a date from the builder or RERA.
Pace between filings = (35% − 30%) ÷ 5.9 months = 0.8% a month.
A straight line is a simplification: the builder reports one overall %, which mixes excavation, structure and finishing, and work rarely moves at a constant speed. The % values are the promoter’s own figures filed with RERA, not checked by us. Promoter’s quarterly update to RERA for Q1 2026-27, submitted 2026-07-15.
Sources:Source (rera.karnataka.gov.in) (opens in a new tab)How we calculate this
Approvals and documents checklist
| Approval | Authority | Source |
|---|---|---|
| Layout plan | Satellite Town Ring Road Planning Authority · No. STRRPA/TP/LAO/12/23-24 · dated 2024-10-23 | Source (rera.karnataka.gov.in) (opens in a new tab) |
| Land conversion (2 orders) | Deputy commissioner Banglore rural · No. 490886 and 1 more · dated 2023-08-30 | Source (rera.karnataka.gov.in) (opens in a new tab) |
| Approved Layout Plan/Demarcation Plan | scan uploaded to RERA | Source (rera.karnataka.gov.in) (opens in a new tab) |
| NOC from ESCOMs | scan uploaded to RERA | Source (rera.karnataka.gov.in) (opens in a new tab) |
| NOC for Water | scan uploaded to RERA | Source (rera.karnataka.gov.in) (opens in a new tab) |
| KSPCB (If Applicable) | scan uploaded to RERA | Source (rera.karnataka.gov.in) (opens in a new tab) |
Documents uploaded to RERA
- Building or layout plan · Approved drawings from the planning authorityFiled on RERA ✓ — Satellite Town Ring Road Planning Authority · No. STRRPA/TP/LAO/12/23-24 · dated 23 Oct 2024
- Commencement certificate · Permission to start buildingNot on RERA yet
- Environment clearance · SEIAA KarnatakaNot on RERA yet
- Fire NOC · Karnataka Fire and Emergency ServicesNot on RERA yet
- Pollution board consent · KSPCBFiled on RERA ✓ — scanned copy uploaded; number and date not read yet
- Water and sewerage · BWSSBFiled on RERA ✓ — scanned copy uploaded; number and date not read yet
- Electricity · BESCOMFiled on RERA ✓ — scanned copy uploaded; number and date not read yet
- Height clearance · Airports Authority of IndiaNot on RERA yet
- Occupancy certificate (OC) · Issued only when the building is finishedNot on RERA yet — expected at completion
From the documents the promoter uploaded to Karnataka RERA, collected 16 Oct 2026. “Filed” means a document is on RERA — we have not checked its contents or validity. Not every approval applies to every project (for example, smaller projects may not need an environment clearance). The project page on RERA lists each upload.
Shantivan RERA complaints
No complaints listed on Karnataka RERA for this registration as on Source (rera.karnataka.gov.in) (opens in a new tab)
Court and consumer cases
We list case numbers, courts and outcomes only — never names of private individuals.
About Sidharth Madhuban
- Promoter type
- Partnership Firm
- Projects on this site
- 2
- RERA complaints against promoter
- 0
- Company number (CIN)
- Not found in public records yet: CIN
From Karnataka RERA, as collected so far (16 Oct 2026). Complaints are those RERA lists against this promoter across all its projects.
Sidharth Madhuban’s RERA recordSidharth Madhuban delivery record
- 2Projects in Bengaluru on RERA2 approved registrations under Sidharth Madhuban in Bengaluru Urban and Rural. Source (rera.karnataka.gov.in) (opens in a new tab)
- 208Plots registeredAs stated in each registrations.
- 0RERA complaintsas on Source (rera.karnataka.gov.in) (opens in a new tab)
- 0Complaints per 1,000 plots0 complaints ÷ 208 plots in its 2 registrations on Karnataka RERA in Bengaluru.
Sources:Source (rera.karnataka.gov.in) (opens in a new tab)How we calculate this
What’s changed since Oct 2024
- 15 Jul 2026Quarterly update filed for Q1 2026-27: 35% built Source (rera.karnataka.gov.in) (opens in a new tab)
- 14 Apr 2026Quarterly update filed for Q4 2025-26: 35% built Source (rera.karnataka.gov.in) (opens in a new tab)
- 23 Jan 2026Quarterly update filed for Q3 2025-26: 30% built Source (rera.karnataka.gov.in) (opens in a new tab)
- 16 Jul 2025Registered with Karnataka RERA (PRM/KA/RERA/1250/303/PR/160725/007932); completion date 31 Oct 2028 Source (rera.karnataka.gov.in) (opens in a new tab)
- 23 Oct 2024Building plan approved by Satellite Town Ring Road Planning Authority (No. STRRPA/TP/LAO/12/23-24) Source (rera.karnataka.gov.in) (opens in a new tab)
- 23 Oct 2024Project start date in the RERA record Source (rera.karnataka.gov.in) (opens in a new tab)
Newest first. No extension of the completion date is recorded on RERA. When the RERA crawl sees a new filing, complaint or extension, it is added here with its date.
Plot loan EMI calculator
- Monthly EMI
- —
- Down payment
- —
- Loan amount
- —
- Total interest
- —
A calculation only, from the numbers you enter — not a loan offer.
Shantivan FAQs
What plot sizes are available at Shantivan?
Plots come in three standard sizes: 30×50 feet (1,500 sq ft), 30×45 feet (1,350 sq ft), and 30×40 feet (1,200 sq ft), with 19 odd-sized plots also available. In total, there are 80 plots: 32 of 30×50 feet, 20 of 30×45 feet, and 9 of 30×40 feet.
How many plots are there in Shantivan?
There are 80 plots in total, including 32 plots of 30×50 feet, 20 plots of 30×45 feet, 9 plots of 30×40 feet, and 19 odd-sized plots.
What is the RERA registration number for Shantivan?
The RERA registration number is PRM/KA/RERA/1250/303/PR/160725/007932, registered on 16 July 2025.
When is Shantivan expected to be completed?
The project completion date on RERA is 31 October 2028.
What is the current development status of Shantivan?
As of Q1 2026-27 (ended 30 June 2026), the layout development was 35 percent complete.
Which authority approved the layout for Shantivan?
The layout was approved by STRR Planning Authority.
How many land conversion orders are on record for Shantivan?
There are 2 land conversion orders on record for this project.
Are there any RERA complaints against Shantivan or the developer?
There are no RERA complaints on this project or against the developer Sidharth Madhuban across their projects on our record.
Where is Shantivan located?
Shantivan is located in Bidaluru, Devanahalli taluk, Bengaluru Rural district, with postal code 562110.
How many projects does the developer have on RERA record?
Sidharth Madhuban has 2 projects on RERA record in the Bengaluru area.
Written by AI from the RERA record above on 7 Oct 2026. Answers use only that record; check them against the source before you decide.
Questions about Shantivan
No questions published yet. Ask the first one: you get an instant answer from this page’s public record, and our team follows up on anything the record does not show.
Bought a plot from Sidharth Madhuban? Review the developer.
Reviews of Sidharth Madhuban by verified buyers
No verified reviews of Sidharth Madhuban yet. If you bought a plot from them, your review helps other buyers.
How reviews work: only buyers and owners can review; we confirm each purchase by phone before publishing, publish positive and negative reviews alike, never accept payment for reviews, and the developer may reply.
Similar projects within 5 km
| Project | Distance | Plots | Completion (RERA) | Developed | Complaints | Price |
|---|---|---|---|---|---|---|
| Legacy MihiraLegacy Global Projects Pvt Ltd | 0.1 km | 279 | Dec 2030 | 25% | 0 | Not collected |
| MadhubanSidharth Madhuban | 0.8 km | 128 | Mar 2028 | 95% | 0 | Not collected |
| Century TrailsCentury Prime Properties Private Limited | 0.9 km | 346 | Mar 2027 | — | 0 | Not collected |
| Prestige Gardenia EstatePrestige Estates Projects Ltd | 1.2 km | 711 | Oct 2027 | — | 0 | Not collected |
| Brigade OasisBrigade Enterprises Ltd | 1.2 km | 988 | Jun 2026extended | — | 6 | Not collected |
| Hillcrest HavenM/s Chhabindra Kumar Pradhan | 1.9 km | 38 | May 2028 | 80% | 0 | Not collected |
Projects of the same kind within 5 km in a straight line of this project’s RERA map point, nearest first. % built is the promoter’s latest quarterly figure on RERA (shown for single-registration projects); prices are from the developer’s own website where we found one.
Sources and last checked dates
Collected on 16 Oct 2026 by AI research agents reading public pages. Facts are written in our own words. Not found yet: price; court cases; landmarks; specifications; news.
How to check on RERA: On rera.karnataka.gov.in/viewAllProjects, type the registration number in 'Registration No', press Search, then click the 'View Project Details' icon. Complaints open from the 'Complaints / Litigation' icon in the same row. Registration number: PRM/KA/RERA/1250/303/PR/160725/007932.
- RERA record last checked: 16 Oct 2026
- Last change in the record (registration, quarterly filing or complaint): 15 Jul 2026
How this page is made: software builds it from public records (Karnataka RERA filings, OpenStreetMap, the developer’s own website). AI is used only to read filings into fields and to write the plain-English summary and FAQ answers, which are checked against the record. Facts are checked automatically against the RERA filing. Methodology · How we earn · Report an error
More new projects nearby
Bidalur, near DevanahalliUnder constructionRERA registeredBuyers’ group openLegacy Mihira
by Legacy Global
Price: Price on requestGet brochure & price →
- 33×60, 40×60
- 1,200 – 3,970 sq ft plots
- Approved by STRR Planning Authority
- Dec 2030
279 plots
Be one of the first 10 buyers in this groupFounding members — it’s free
Join group for Legacy Mihira
Savakanahalli, DevanahalliUnder constructionRERA registeredBuyers’ group openMadhuban
by Sidharth Madhuban
Price: Price on requestGet brochure & price →
- 30×40, 30×50, 40×60
- 12,917 – 94,841 sq ft plots
- Approved by Local Planning Authority
- Mar 2028
128 plots
Be one of the first 10 buyers in this groupFounding members — it’s free
Join group for Madhuban- Bidalur, near Devanahalli© Esri, Maxar, Earthstar GeographicsReady to moveRERA registeredBuyers’ group open
Century Trails
by Century Prime Properties
Price: Price on requestGet brochure & price →
- 30×40, 30×50, 40×60
- 1,199 – 16,173 sq ft plots
- Approved by Local Planning Authority
- Mar 2027
346 plots
Be one of the first 10 buyers in this groupFounding members — it’s free
Join group for Century Trails