The Presidential Tower
3, 4 & 5 BHK apartments by Best Golden Developers Pvt Ltd · Yeshwanthpur, Bengaluru
Yeshwanthpur, Bengaluru
- Under construction
- RERA registered
- residential
by Best Golden Developers Pvt Ltd
Price: Price on request
Site photo filed with Karnataka RERA Karnataka RERA filing · Source ↗ (opens in a new tab)
The Presidential Tower at a glance
- Possession (RERA)Jun 2027 ExtendedWas Jun 2021 · Karnataka RERA
- Construction91% built · on pace for May 2027RERA filing to 31 Mar 2026; estimate from average pace
- Homes booked268 of 538 (50%)RERA update · as on 31 Mar 2026
- RERA complaints (project)11 complaintsKarnataka RERA · as on 15 Oct 2026
- Approvals filed1 of 9 on RERAKarnataka RERA uploads · 15 Oct 2026
Project summary
The Presidential Tower is a residential project by Best Golden Developers Pvt Ltd in Bengaluru with 538 homes, registered with Karnataka RERA. The completion date on RERA is 30 Jun 2027.
Not in the RERA record we collected yet: locality, map location. This page fills in as the record is collected.
Facts collected on 15 Oct 2026 from public records — each linked to its source. Free for buyers. If you book through us, the builder pays us a commission.
The Presidential Tower buyers’ group: join to ask for a group price
No one has joined yet. Be one of the first 10 buyers in this group — the founding members.
Join free. When enough buyers have joined, our agent partner asks Best Golden Developers Pvt Ltd for a group price — for example a lower price, an easier payment plan or waived charges. Nothing is promised: you see what the builder offers and book directly with the builder if you want to. Free for buyers. If you book through us, the builder pays us a commission.
- Gathering buyers
- Talking to the builder
- Group offer
- Group site visit
- Booking
0 buyers have joined · 0 committed
Committed buyers have confirmed their budget, home type and timeline with us on a call; builders negotiate with them. Joining is free and never obliges you to buy.
Join the The Presidential Tower buyers’ groupHow group buying works
See it for yourself
Visit the site with our team, or get a call to clear your questions. Free, no obligation.
Key facts: home types, towers, land and possession
- Home types
- 3 BHK, 4 BHK, 5 BHK
- Carpet area
- 1,086 – 53,820 sq ft
- Towers
- 1
- Floors
- 49
- Total homes
- 538
- Land
- 5 acres
- Possession (extended)
- Jun 2027
- Built (RERA update)
- 91%
The Presidential Tower RERA number and registration details
- RERA number
- PRM/KA/RERA/1251/309/PR/171014/000565
- Registered on
- 14 Oct 2017
- Promised completion
- 30 Jun 2021
- Extended to
- 30 Jun 2027
- RERA status
- Under construction
- Homes booked
- 268 of 538 as on
- Price
- Not found in public records yet: price
- Project type
- Residential
Towers and blocks (RERA filing)
| Tower | Floors | Basements | Homes |
|---|---|---|---|
| The Presidential Tower | 49 | 3 | 368 |
A dash (—) means the filing did not state that value.
Summary in plain English
The Presidential Tower is a residential project by Golden Developers Pvt Ltd in Bengaluru North with 538 homes across 1 tower of 49 floors. The project was registered with RERA on 14 October 2017 with a current completion date of 30 June 2027.
Written by AI from the RERA record above on 15 Oct 2026. Every number in it was checked against that record; if anything differs, the record wins.
Open space, home loans, escrow and other details
- Open space
- 88.8% of land
- Water and power
- Not found in public records yet: water and power
- Home loans: approved banks
- Not found in public records yet: bank approvals
- Payment plans
- Not found in public records yet: payment plans
- Maintenance
- Not found in public records yet: maintenance
- Car parking
- Not found in public records yet: car parking charge
- Escrow bank (RERA)
- Axis Bank, YELAHANKA
- Project cost declared to RERA
- ₹666 Cr
Open area as a share of the land, from the areas filed with RERA (includes driveways and landscaped areas).
Amenities
The Presidential Tower location and address
- Address
- NO 8 tumkur road, yeshwantpur
- Village (RERA)
- Not found in public records yet: village
- Locality
- YeshwanthpurAlso known as Yeshwantpur, Yeshwanthapura
- PIN code
- 560043
- City
- Bengaluru
- State
- Karnataka
- Coordinates
- Not found in public records yet: coordinates
Distances to landmarks
Not found in public records yet: landmarksAbout Yeshwanthpur
Not found in public records yet: locality factsThe Presidential Tower home types and carpet areas
Floor plans and brochure not published? The builder shares them only on request. We’ll get the brochure, floor plans and current price list for you, free.
Get brochure, floor plans & price| Home type | Carpet area | Homes |
|---|---|---|
| 3 BHK | 1,086 – 1,624 sq ft | 132 |
| 3 BHK 148 | 1,130 sq ft | 88 |
| 3 BHK with servent | 1,607 – 1,673 sq ft | 132 |
| 4 BHK | 2,819 – 53,820 sq ft | 90 |
| 4 BHK duplex | 1,630 – 1,706 sq ft | 4 |
| 4 BHK with servent | 2,070 – 2,133 sq ft | 88 |
| 5 BHK duplex | 2,130 – 2,133 sq ft | 4 |
Home types, counts and carpet areas as filed with Karnataka RERA (carpet area, not super built-up).
We have not collected floor-plan drawings; the builder’s sales team can share them.
The Presidential Tower possession date and construction status
Promoter’s quarterly update to RERA for Q4 2025-26, submitted 2026-07-11.
Units sold and unsold, from RERA (Q4 2025-26)
| Type | Homes | Booked | Available |
|---|---|---|---|
| 3 BHK WITH SERVENT | 132 | 66 | 66 |
| 3 BHK | 132 | 128 | 4 |
| 4 BHK DUPLEX | 4 | 0 | 4 |
| 4 BHK WITH SERVENT | 88 | 71 | 17 |
| 4 BHK | 8 | 3 | 5 |
| 5 BHK DUPLEX | 4 | 0 | 4 |
As reported by the promoter in the quarterly update to RERA, not verified by us.
Timeline
- 1 Jul 2014Project start date given to RERA
- 14 Oct 2017Registered with Karnataka RERA
- 30 Jun 2021Completion date given at registration
- 30 Mar 2022Covid Extension: completion date moved to this date
- 3 Mar 2023Section 6 Extension: completion date moved to this date
- 30 Jun 2027Further Extension: completion date moved to this date
Construction pace from RERA quarterly filings
At the average pace so far, construction would reach 100% around May 2027 — about 1 month before the completion date on RERA (30 Jun 2027).
At the pace between the 2 quarterly filings we have (86% → 91% in 3 months), it would be around Sep 2026 — about 10 months before the RERA date.
- Filed on RERA
- Average pace since start
- Pace between filings (and 0% assumed at the start date)
- RERA completion date
Quarterly filings
| Quarter | Filed on | Built | Homes booked |
|---|---|---|---|
| Q4 2025-26to 31 Mar 2026 | 11 Jul 2026 | 91% | 268 of 368 |
| Q3 2025-26to 31 Dec 2025 | 6 Mar 2026 | 86% | 267 of 368 |
How we calculate
Average pace = % built ÷ months since the start date in the RERA record. Here: 91% ÷ 141 months (1 Jul 2014 to 31 Mar 2026) = 0.6% a month.
Estimated finish = latest filing date + (100 − % built) ÷ pace = 31 Mar 2026 + 9 ÷ 0.6 = 13.9 months → May 2027. This is an estimate, not a date from the builder or RERA.
Pace between filings = (91% − 86%) ÷ 3 months = 1.7% a month.
A straight line is a simplification: the builder reports one overall %, which mixes excavation, structure and finishing, and work rarely moves at a constant speed. The % values are the promoter’s own figures filed with RERA, not checked by us. Promoter’s quarterly update to RERA for Q4 2025-26, submitted 2026-07-11.
Sources:Source (rera.karnataka.gov.in) (opens in a new tab)How we calculate this
Approvals and documents checklist
| Approval | Authority | Source |
|---|---|---|
| Building plan | BBMP - Bruhat Bengaluru Mahanagara Palike | Source (rera.karnataka.gov.in) (opens in a new tab) |
Documents uploaded to RERA
- Building or layout plan · Approved drawings from the planning authorityFiled on RERA ✓ — scanned copy uploaded; number and date not read yet
- Commencement certificate · Permission to start buildingNot on RERA yet
- Environment clearance · SEIAA KarnatakaNot on RERA yet
- Fire NOC · Karnataka Fire and Emergency ServicesNot on RERA yet
- Pollution board consent · KSPCBNot on RERA yet
- Water and sewerage · BWSSBNot on RERA yet
- Electricity · BESCOMNot on RERA yet
- Height clearance · Airports Authority of IndiaNot on RERA yet
- Occupancy certificate (OC) · Issued only when the building is finishedNot on RERA yet — expected at completion
From the documents the promoter uploaded to Karnataka RERA, collected 15 Oct 2026. “Filed” means a document is on RERA — we have not checked its contents or validity. Not every approval applies to every project (for example, smaller projects may not need an environment clearance). The project page on RERA lists each upload.
The Presidential Tower RERA complaints and orders
11 complaints as on Source (rera.karnataka.gov.in) (opens in a new tab)
11 rows: rera complaints. Scroll inside the table to see them all.
| Complaint ref | Filed | Subject | Status | Source |
|---|---|---|---|---|
| 01033/2026 | 20 Aug 2026 | Complaint seeking termination of Agreement to Sell and cancellation of allotment due to continuous default in payment by the Allottee | Under enquiry | Source (rera.karnataka.gov.in) (opens in a new tab) |
| 00950/2026 | 4 Aug 2026 | Compensation for Delay in handing over possession of Residential Flat or Unit No. PB 4003 | Under enquiry | Source (rera.karnataka.gov.in) (opens in a new tab) |
| 00456/2026 | 2 May 2026 | Refund of amount | Under enquiry | Source (rera.karnataka.gov.in) (opens in a new tab) |
| 01448/2025 | 8 Dec 2025 | Delayed delivery of possession along with compensation and refund of interest paid to the bank in which the developer had agreed but not paid | Under enquiry | Source (rera.karnataka.gov.in) (opens in a new tab) |
| 01447/2025 | 8 Dec 2025 | Delayed delivery of possession along with compensation and refund of interest paid to the bank in which the developer had agreed but not paid | Under enquiry | Source (rera.karnataka.gov.in) (opens in a new tab) |
| 01156/2025 | 11 Sep 2025 | Complaint against builder for delay in possession of Apartment No. PB-4302 | Posted for orders | Source (rera.karnataka.gov.in) (opens in a new tab) |
| 00202/2024 | 19 Feb 2024 | Interest on Delay period | Disposed | Source (rera.karnataka.gov.in) (opens in a new tab) |
| 01871/2023 | 26 Dec 2023 | Not providing agreement and demand for payment in cash | Disposed | Source (rera.karnataka.gov.in) (opens in a new tab) |
| CMP/220608/0009606 | 8 Jun 2022 | Direction to promoter | Disposed | Source (rera.karnataka.gov.in) (opens in a new tab) |
| CMP/190520/0003099 | 20 May 2019 | Delay in Construction and Default in Payment of PRE-EMI's | Disposed ao | Source (rera.karnataka.gov.in) (opens in a new tab) |
| CMP/190515/0003030 | 15 May 2019 | Memorandum of complaint under section 31 of the real estate (regulation & development) act 2016 read with rule 29 of the karnataka real estate (regulation & development) rules 2017 | Disposed ao | Source (rera.karnataka.gov.in) (opens in a new tab) |
Court and consumer cases
We list case numbers, courts and outcomes only — never names of private individuals.
About Best Golden Developers Pvt Ltd
- Promoter type
- Company
- Projects on this site
- 1
- RERA complaints against promoter
- 11
- Company number (CIN)
- U70100KA2011PTC061674
From Karnataka RERA, as collected so far (15 Oct 2026). Complaints are those RERA lists against this promoter across all its projects.
Best Golden Developers Pvt Ltd’s RERA recordBest Golden Developers Pvt Ltd delivery record
- 1Projects in Bengaluru on RERA1 approved registration under Best Golden Developers Pvt Ltd in Bengaluru Urban and Rural. Source (rera.karnataka.gov.in) (opens in a new tab)
- 538Homes registeredAs stated in each registrations.
- 11RERA complaints6 open, 5 disposed. as on Source (rera.karnataka.gov.in) (opens in a new tab)
- 20.4Complaints per 1,000 homes11 complaints ÷ 538 homes in its 1 registration on Karnataka RERA in Bengaluru.
What the complaints are about
11 complaint subjects as written on RERA, as on . Each subject is sorted into one group by keywords (first match wins: delay, refund, registration, quality, litigation, association); one complaint often raises several issues. Source (rera.karnataka.gov.in) (opens in a new tab)
Sources:Source (rera.karnataka.gov.in) (opens in a new tab)How we calculate this
What’s changed since Jul 2014
- 30 Jun 2027Completion date extended to 30 Jun 2027 Source (rera.karnataka.gov.in) (opens in a new tab)
- 20 Aug 2026Complaint 01033/2026 filed with RERA: “Complaint seeking termination of Agreement to Sell and cancellation of allotment due to continuous default in payment by the Allottee” — now under enquiry Source (rera.karnataka.gov.in) (opens in a new tab)
- 4 Aug 2026Complaint 00950/2026 filed with RERA: “Compensation for Delay in handing over possession of Residential Flat or Unit No. PB 4003” — now under enquiry Source (rera.karnataka.gov.in) (opens in a new tab)
- 11 Jul 2026Quarterly update filed for Q4 2025-26: 91% built, 268 of 368 homes booked Source (rera.karnataka.gov.in) (opens in a new tab)
- 2 May 2026Complaint 00456/2026 filed with RERA: “Refund of amount” — now under enquiry Source (rera.karnataka.gov.in) (opens in a new tab)
- 6 Mar 2026Quarterly update filed for Q3 2025-26: 86% built, 267 of 368 homes booked Source (rera.karnataka.gov.in) (opens in a new tab)
- 8 Dec 2025Complaint 01448/2025 filed with RERA: “Delayed delivery of possession along with compensation and refund of interest paid to the bank in which the developer had agreed but not paid” — now under enquiry Source (rera.karnataka.gov.in) (opens in a new tab)
- 8 Dec 2025Complaint 01447/2025 filed with RERA: “Delayed delivery of possession along with compensation and refund of interest paid to the bank in which the developer had agreed but not paid” — now under enquiry Source (rera.karnataka.gov.in) (opens in a new tab)
- 11 Sep 2025Complaint 01156/2025 filed with RERA: “Complaint against builder for delay in possession of Apartment No. PB-4302” — now posted for orders Source (rera.karnataka.gov.in) (opens in a new tab)
- 19 Feb 2024Complaint 00202/2024 filed with RERA: “Interest on Delay period” — now disposed Source (rera.karnataka.gov.in) (opens in a new tab)
- 26 Dec 2023Complaint 01871/2023 filed with RERA: “Not providing agreement and demand for payment in cash” — now disposed Source (rera.karnataka.gov.in) (opens in a new tab)
- 8 Jun 2022Complaint CMP/220608/0009606 filed with RERA: “Direction to promoter” — now disposed Source (rera.karnataka.gov.in) (opens in a new tab)
- 20 May 2019Complaint CMP/190520/0003099 filed with RERA: “Delay in Construction and Default in Payment of PRE-EMI's” — now disposed Source (rera.karnataka.gov.in) (opens in a new tab)
- 15 May 2019Complaint CMP/190515/0003030 filed with RERA: “Memorandum of complaint under section 31 of the real estate (regulation & development) act 2016 read with rule 29 of the karnataka real estate (regulation & development) rules 2017” — now disposed Source (rera.karnataka.gov.in) (opens in a new tab)
- 14 Oct 2017Registered with Karnataka RERA (PRM/KA/RERA/1251/309/PR/171014/000565); completion date 30 Jun 2021 Source (rera.karnataka.gov.in) (opens in a new tab)
- 1 Jul 2014Project start date in the RERA record Source (rera.karnataka.gov.in) (opens in a new tab)
Newest first. When the RERA crawl sees a new filing, complaint or extension, it is added here with its date.
Home loan EMI calculator
- Monthly EMI
- —
- Down payment
- —
- Loan amount
- —
- Total interest
- —
A calculation only, from the numbers you enter — not a loan offer.
All-in cost: GST, registration and other charges
The calculator loads when you scroll to it.
Assumptions
- Base price: the builder’s price is not published in a form we could collect — enter it from the cost sheet.
- GST 5% on the base price and charges — the usual rate for an under-construction home that is not “affordable housing” (1%).
- Stamp duty about 5.6% and registration 2% — the Karnataka rule (registration was raised from 1% to 2% on 31 Aug 2025). Calculated on the agreement value.
- Car parking, other charges and the maintenance deposit are not in the public record we collect; enter them from the builder’s cost sheet.
- Loan on the agreement value (banks usually lend up to 75–90%); EMI is the standard reducing-balance formula. Example rate only — use your bank’s quote.
The Presidential Tower FAQs
What is the completion date for The Presidential Tower?
The project completion date on RERA is 30 June 2027. The original completion date was 30 June 2021, with extensions granted for Covid, Section 6, and further reasons.
What home types are available in The Presidential Tower?
The project offers 3 BHK, 3 BHK with servant, 4 BHK, 4 BHK with servant, 4 BHK duplex, and 5 BHK duplex units.
What is the carpet area range in The Presidential Tower?
Carpet areas range from 1,086 sq ft to 53,820 sq ft depending on home type.
How many homes are in The Presidential Tower?
The project has 538 homes total across 1 tower.
Where is The Presidential Tower located?
The project is in Bengaluru North taluk, Bengaluru Urban district, PIN code 560043.
What is the construction progress of The Presidential Tower?
As of the Q4 2025-26 quarterly update (quarter ended 31 March 2026), the project is 91% complete with 268 homes booked and 368 homes in the booking table.
What is the RERA registration number for The Presidential Tower?
The project is registered with RERA registration number PRM/KA/RERA/1251/309/PR/171014/000565.
How many RERA complaints are there on The Presidential Tower?
There are 11 RERA complaints on this project.
What is the builder's record with other projects?
Golden Developers Pvt Ltd has 1 project in the Bengaluru RERA records with 11 total complaints against the builder across all projects.
Which bank is the escrow bank for The Presidential Tower?
Axis Bank is the escrow bank for the project.
Written by AI from the RERA record above on 15 Oct 2026. Answers use only that record; check them against the source before you decide.
Questions about The Presidential Tower
No questions published yet. Ask the first one: you get an instant answer from this page’s public record, and our team follows up on anything the record does not show.
Bought a home from Best Golden Developers Pvt Ltd? Review the builder.
Reviews of Best Golden Developers Pvt Ltd by verified buyers
No verified reviews of Best Golden Developers Pvt Ltd yet. If you bought a home from them, your review helps other buyers.
How reviews work: only buyers and owners can review; we confirm each purchase by phone before publishing, publish positive and negative reviews alike, never accept payment for reviews, and the builder may reply.
Sources and last checked dates
Collected on 15 Oct 2026 by AI research agents reading public pages. Facts are written in our own words. Not found yet: price; court cases; landmarks; specifications; news.
How to check on RERA: On rera.karnataka.gov.in/viewAllProjects, type the registration number in 'Registration No', press Search, then click the 'View Project Details' icon. Complaints open from the 'Complaints / Litigation' icon in the same row. Registration number: PRM/KA/RERA/1251/309/PR/171014/000565.
- RERA record last checked: 15 Oct 2026
- Last change in the record (registration, quarterly filing or complaint): 20 Aug 2026
How this page is made: software builds it from public records (Karnataka RERA filings, OpenStreetMap, the builder’s own website). AI is used only to read filings into fields and to write the plain-English summary and FAQ answers, which are checked against the record. Facts are checked automatically against the RERA filing. Methodology · How we earn · Report an error
More new projects in Yeshwanthpur
Hosakerehalli, Rajarajeshwari NagarArtist’s impressionUnder constructionRERA registeredBuyers’ group openSobha Valley View - Heritage
by Sobha
Price: Price on requestGet brochure & price →
- 2 BHK, 3 BHK
- 917 – 1,267 sq ft
- Feb 2019
RERA not updated since promised Feb 2019 · 624 homes · 19 RERA complaints
Be one of the first 10 buyers in this groupFounding members — it’s free
Join group for Sobha Valley View - Heritage
Agara, HSR LayoutArtist’s impressionUnder constructionRERA registeredBuyers’ group openSterling Infinia
by Sterling
Price: Price on requestGet brochure & price →
- 1 BHK, 2 BHK, 3 BHK, 4 BHK
- 904 – 2,336 sq ft
- Sep 2026 (extended)
RERA not updated since promised Sep 2026 · 344 homes · 4 RERA complaints
Be one of the first 10 buyers in this groupFounding members — it’s free
Join group for Sterling Infinia
Kammanahalli, near Begur RoadUnder constructionRERA registeredBuyers’ group openSound of Water Phase 3
by Puravankara
Price: Price on requestGet brochure & price →
- 3 BHK, 4 BHK
- 1,787 – 2,749 sq ft
- Jun 2027
60 homes
Be one of the first 10 buyers in this groupFounding members — it’s free
Join group for Sound of Water Phase 3