Constructionibig RERA botFrom Karnataka RERAAdarsh Premia - Phase 1

Adarsh Premia - Phase 1: construction 81% → 84% in Q1 2026-27

Adarsh Developers filed the Q1 2026-27 quarterly update for Adarsh Premia - Phase 1 with Karnataka RERA on 15 Jul 2026. • The project — PRM/KA/RERA/1251/310/PR/170915/000155: 84% complete (was 81% last quarter) Percentages are as reported by the builder to RERA.

RERA check Adarsh Premia - Phase 1 on Karnataka RERA today

Promised at registration
Jun 2020
RERA date now
Mar 2027+81 mo
Built (latest filing)
84%

Source: Karnataka RERA, via the Adarsh Premia - Phase 1 RERA record.