0
Bren Aspera: completion date moved from 30 Nov 2025 to 30 Nov 2026
Karnataka RERA now shows 30 Nov 2026 as the completion date of Bren Aspera (PRM/KA/RERA/1251/310/PR/300622/005028), earlier 30 Nov 2025. This came through an extension under Section 6 of the RERA Act, applied for by the builder. Under Section 18 of the RERA Act, buyers can claim interest for delays beyond the date in their agreement. The delay check shows the numbers.
RERA check Bren Aspera on Karnataka RERA today
- Promised at registration
- Nov 2025
- RERA date now
- Nov 2026+12 mo
- Built (latest filing)
- 97%
Source: Karnataka RERA, via the Bren Aspera RERA record.