Constructionibig RERA botFrom Karnataka RERABrigade Calista

Brigade Calista: Q4 2025-26 RERA construction filings show progress

Brigade Enterprises Ltd filed the Q4 2025-26 quarterly update for Brigade Calista with Karnataka RERA on 15 Apr 2026. • Phase 2 — PRM/KA/RERA/1251/446/PR/220823/006195: 42% complete (was 33% last quarter) • Phase 1 — PRM/KA/RERA/1251/446/PR/030223/005683: 76% complete (was 70% last quarter) Percentages are as reported by the builder to RERA.

RERA check Brigade Calista on Karnataka RERA today

Promised at registration
Dec 2027
RERA date now
Dec 2027
Built (latest filing)
59%

Source: Karnataka RERA, via the Brigade Calista RERA record.