Brigade Calista: Q1 2026-27 RERA construction filings show progress

Brigade Enterprises Ltd filed the Q1 2026-27 quarterly update for Brigade Calista with Karnataka RERA on 15 Jul 2026. • Phase 2 — PRM/KA/RERA/1251/446/PR/220823/006195: 50% complete (was 42% last quarter) • Phase 1 — PRM/KA/RERA/1251/446/PR/030223/005683: 77% complete (was 76% last quarter) Percentages are as reported by the builder to RERA.

RERA check Brigade Calista on Karnataka RERA today

Promised at registration
Dec 2027
RERA date now
Dec 2027
Built (latest filing)
64%

Source: Karnataka RERA, via the Brigade Calista RERA record.