Godrej Ananda: completion date moved from 8 Jan 2026 to 8 Jan 2027
Karnataka RERA now shows 8 Jan 2027 as the completion date of Godrej Ananda (PRM/KA/RERA/1251/309/PR/210331/004084), earlier 8 Jan 2026. This came through an extension under Section 6 of the RERA Act, applied for by the builder. Under Section 18 of the RERA Act, buyers can claim interest for delays beyond the date in their agreement. The delay check shows the numbers.
RERA check Godrej Ananda on Karnataka RERA today
- Promised at registration
- Jan 2026
- RERA date now
- Jan 2027+12 mo
- Built (latest filing)
- 100%
Source: Karnataka RERA, via the Godrej Ananda RERA record.