Mirabelle: Q3 2025-26 RERA construction filings
Lodha Developers Limited filed the Q3 2025-26 quarterly update for Mirabelle with Karnataka RERA on 15 Jan 2026. • Phase 2 — PRM/KA/RERA/1251/446/PR/230425/007688: 4% complete • Main registration — PRM/KA/RERA/1251/309/PR/131023/006321: 71% complete Percentages are as reported by the builder to RERA.
RERA check Mirabelle on Karnataka RERA today
- Promised at registration
- May 2030
- RERA date now
- May 2030
- Built (latest filing)
- 38%
Source: Karnataka RERA, via the Mirabelle RERA record.