Salarpuria Sattva Misty Charm: completion date moved from 31 Jan 2023 to 31 Oct 2023
Karnataka RERA now shows 31 Oct 2023 as the completion date of Salarpuria Sattva Misty Charm (PRM/KA/RERA/1251/310/PR/180507/001635), earlier 31 Jan 2023. This came through the COVID-19 extension Karnataka RERA gave to all projects. Under Section 18 of the RERA Act, buyers can claim interest for delays beyond the date in their agreement. The delay check shows the numbers.
RERA check Salarpuria Sattva Misty Charm on Karnataka RERA today
- Promised at registration
- Jan 2023
- RERA date now
- Oct 2024+21 mo
- Built (latest filing)
- not filed
Source: Karnataka RERA, via the Salarpuria Sattva Misty Charm RERA record.