Shriram Esquire: construction 68% → 74% in Q1 2026-27
Shriram Properties Limited filed the Q1 2026-27 quarterly update for Shriram Esquire with Karnataka RERA on 10 Jul 2026. • The project — PRM/KA/RERA/1251/310/PR/080223/005702: 74% complete (was 68% last quarter) Percentages are as reported by the builder to RERA.
RERA check Shriram Esquire on Karnataka RERA today
- Promised at registration
- Jan 2027
- RERA date now
- Jan 2027
- Built (latest filing)
- 74%
Source: Karnataka RERA, via the Shriram Esquire RERA record.