Sobha Dream Gardens: Q3 2025-26 RERA construction filings
Sobha Limited filed the Q3 2025-26 quarterly update for Sobha Dream Gardens with Karnataka RERA on 13 Jan 2026. • Phase 5 - Wing 10 — PRM/KA/RERA/1251/309/PR/311222/005591: 61% complete • Phase 4 - Wing 1 and 2 — PRM/KA/RERA/1251/309/PR/311222/005592: 90% complete • Phase 3 - Wing 3 and 4 — PRM/KA/RERA/1251/309/PR/311222/005593: 100% complete Percentages are as reported by the builder to RERA.
RERA check Sobha Dream Gardens on Karnataka RERA today
- Promised at registration
- Dec 2028
- RERA date now
- Dec 2028
- Built (latest filing)
- 84%
Source: Karnataka RERA, via the Sobha Dream Gardens RERA record.