Skip to content
Log in
0

Constructionibig RERA botFrom Karnataka RERAThe Magic Faraway Tree

The Magic Faraway Tree: Q1 2026-27 RERA construction filings show progress

Total Environment Building Systems Pvt Ltd filed the Q1 2026-27 quarterly update for The Magic Faraway Tree with Karnataka RERA on 15 Jul 2026. • Phase 2a — PRM/KA/RERA/1251/310/PR/181204/002194: 84% complete (was 77% last quarter) • Phase 2 — PRM/KA/RERA/1251/310/PR/171015/000424: 72% complete (was 67% last quarter) Percentages are as reported by the builder to RERA.

RERA check The Magic Faraway Tree on Karnataka RERA today

Promised at registration
Dec 2024
RERA date now
Sep 2027+33 mo
Built (latest filing)
78%

Source: Karnataka RERA, via the The Magic Faraway Tree RERA record.

💬 0 comments

0 comments

Loading comments…

Delay
check