The Magic Faraway Tree: Q2 2026-27 RERA construction filings show progress

Total Environment Building Systems Pvt Ltd filed the Q2 2026-27 quarterly update for The Magic Faraway Tree with Karnataka RERA on 15 Oct 2026. • Phase 2a — PRM/KA/RERA/1251/310/PR/181204/002194: 90% complete (was 84% last quarter) • Phase 2 — PRM/KA/RERA/1251/310/PR/171015/000424: 82% complete (was 72% last quarter) Percentages are as reported by the builder to RERA.

RERA check The Magic Faraway Tree on Karnataka RERA today

Promised at registration
Dec 2024
RERA date now
Sep 2027+33 mo
Built (latest filing)
86%

Source: Karnataka RERA, via the The Magic Faraway Tree RERA record.