After the Rain (Phase II A): completion date moved from 31 Dec 2022 to 30 Sep 2023
Karnataka RERA now shows 30 Sep 2023 as the completion date of After the Rain (Phase II A) (PRM/KA/RERA/1251/309/PR/180519/001763), earlier 31 Dec 2022. This came through the COVID-19 extension Karnataka RERA gave to all projects. Under Section 18 of the RERA Act, buyers can claim interest for delays beyond the date in their agreement. The delay check shows the numbers.
RERA check After the Rain on Karnataka RERA today
- Promised at registration
- Dec 2022
- RERA date now
- Sep 2024+21 mo
- Built (latest filing)
- not filed
Source: Karnataka RERA, via the After the Rain RERA record.