Pursuit Of A Radical Rhapsody: Q1 2026-27 RERA construction filings show progress
Total Environment Habitat Private Limited filed the Q1 2026-27 quarterly update for Pursuit Of A Radical Rhapsody with Karnataka RERA on 15 Jul 2026. • Tower 8 — PRM/KA/RERA/1251/446/PR/220922/005261: 9% complete (was 8% last quarter) • Tower 5 — PRM/KA/RERA/1251/446/PR/281222/005565: 28% complete (reported 34% last quarter) • Phase 2 — PRM/KA/RERA/1251/446/PR/190102/002271: 51% complete (reported 54% last quarter) Percentages are as reported by the builder to RERA.
RERA check Pursuit Of A Radical Rhapsody on Karnataka RERA today
- Promised at registration
- Dec 2029
- RERA date now
- Dec 2029
- Built (latest filing)
- 29%
Source: Karnataka RERA, via the Pursuit Of A Radical Rhapsody RERA record.