Pursuit Of A Radical Rhapsody at a glance
- Possession (RERA)Mar 2027 ExtendedWas Dec 2029 · Karnataka RERA
- Construction52% built · on pace for Jan 2034 82 mo after RERA dateRERA filing to 30 Sep 2026 (Phase 2); estimate from average pace
- RERA complaints (project)5 complaintsKarnataka RERA · as on 22 Oct 2026
- Approvals filed7 of 9 on RERAKarnataka RERA uploads · 22 Oct 2026
- Nearest metroHoodi · 1.01 kmstraight line · OpenStreetMap, 5 Oct 2026
- Airport driveapprox. 96 min at peak23.65 km straight line · estimate
- Nearest lakeHoodi Lake · 130 mFrom the RERA map point · OpenStreetMap, 5 Oct 2026
Project summary
Pursuit Of A Radical Rhapsody is a residential project by Total Environment Habitat Private Limited in Hoodi, Bengaluru with 715 homes, registered with Karnataka RERA. The completion date on RERA is 30 Mar 2027. It is registered in 4 phases.
Facts collected on 22 Oct 2026 from public records — each linked to its source. Free for buyers. If you book through us, the builder pays us a commission.
Pursuit Of A Radical Rhapsody buyers’ group: join to ask for a group price
No one has joined yet. Be one of the first 10 buyers in this group — the founding members.
Join free. When enough buyers have joined, our agent partner asks Total Environment Habitat Private Limited for a group price — for example a lower price, an easier payment plan or waived charges. Nothing is promised: you see what the builder offers and book directly with the builder if you want to. Free for buyers. If you book through us, the builder pays us a commission.
- Gathering buyers
- Talking to the builder
- Group offer
- Group site visit
- Booking
0 buyers have joined · 0 committed
Committed buyers have confirmed their budget, home type and timeline with us on a call; builders negotiate with them. Joining is free and never obliges you to buy.
Join the Pursuit Of A Radical Rhapsody buyers’ groupHow group buying works
See it for yourself
Visit the site with our team, or get a call to clear your questions. Free, no obligation.
Key facts: home types, towers, land and possession
- Home types
- 2 BHK, 3 BHK, 4 BHK, 5 BHK
- Carpet area
- 846 – 18,056 sq ft
- Towers
- 6
- Floors
- 33
- Total homes
- 715
- Land
- 14.96 acres
- Possession (extended)
- Mar 2027
- Built (RERA update)
- Not found in public records yet: construction progress
Pursuit Of A Radical Rhapsody RERA number and registration details
- RERA number
- PRM/KA/RERA/1251/446/PR/190102/002271
- Registered on
- 2 Jan 2019
- Promised completion
- 1 Dec 2029
- Extended to
- 30 Mar 2027
- RERA status
- New launch
- Homes booked
- Not found in public records yet: homes booked
- Price
- Not found in public records yet: price
- Project type
- Residential
4 RERA registrations (one per phase) are shown together on this page; dates above are the latest across phases.
Phases and RERA numbers
| Phase | RERA number | Promised completion | Homes | Status | Source |
|---|---|---|---|---|---|
| Phase 2 | PRM/KA/RERA/1251/446/PR/190102/002271 | 30 Jun 2026Extended to 30 Mar 2027 | 201 | New launch | Source (rera.karnataka.gov.in) (opens in a new tab) |
| Phase III | PRM/KA/RERA/1251/446/PR/200817/003551 | 30 Jun 2026 | 22 | Completed | Source (rera.karnataka.gov.in) (opens in a new tab) |
| Tower 8 | PRM/KA/RERA/1251/446/PR/220922/005261 | 30 Sep 2029 | 362 | New launch | Source (rera.karnataka.gov.in) (opens in a new tab) |
| Tower 5 | PRM/KA/RERA/1251/446/PR/281222/005565 | 1 Dec 2029 | 130 | New launch | Source (rera.karnataka.gov.in) (opens in a new tab) |
Towers and blocks (RERA filing)
| Tower | Phase | Floors | Basements | Homes |
|---|---|---|---|---|
| Tower 6 | Phase 2 | 30 | 2 | 130 |
| Tower 7 | Phase 2 | 28 | 2 | 114 |
| Villa | Phase 2 | 1 | 0 | 20 |
| Building 3 Commercial | Phase III | 16 | 3 | 22 |
| Tower 08 | Tower 8 | 33 | 4 | 362 |
| Tower 05 | Tower 5 | 30 | 2 | 130 |
A dash (—) means the filing did not state that value.
Summary in plain English
Pursuit Of A Radical Rhapsody is a mixed-use project by Total Environment Habitat Private Limited in Hoodi, Bengaluru East, with 715 homes across 4 RERA registrations. The project includes multiple phases with completion dates ranging from 26 June 2026 to 30 September 2029.
Written by AI from the RERA record above on 22 Oct 2026. Every number in it was checked against that record; if anything differs, the record wins.
Open space, home loans, escrow and other details
- Open space
- Not found in public records yet: open space
- Water and power
- Water source filed with RERA: BWSSB
- Home loans: approved banks
- Not found in public records yet: bank approvals
- Payment plans
- Not found in public records yet: payment plans
- Maintenance
- Not found in public records yet: maintenance
- Car parking
- Not found in public records yet: car parking charge
- Escrow bank (RERA) · Phase 2
- STATE BANK OF INDIA, COMMERCIAL BRANCH, BANGALORE
- Escrow bank (RERA) · Phase III
- RATNAKAR BANK, Residency Road Branch
- Escrow bank (RERA) · Tower 8
- STATE BANK OF INDIA, COMMERCIAL BRANCH, BANGALORE
- Escrow bank (RERA) · Tower 5
- STATE BANK OF INDIA, COMMERCIAL BRANCH, BANGALORE
Amenities
- Electricity
- CCTV Surveillance
- Club House
- Community Hall
- Outdoor Sports facility
- Indoor Sports facility
- Gym
- Parks
- Power Backup
- Piped Gas
- Water and Sanitation
Amenities and internal works as filed by the promoter with Karnataka RERA; we have not visited the site.
Pursuit Of A Radical Rhapsody location and address
- Address
- Sy. No. 170(P), 170/1A, 169/1 to 169/4, 176/3, 177, 172/1, 172/2, 175 (P) & 136/1, Hoodi Village, KR Puram Hobli, Ward No. 82, Bangalore
- Village (RERA)
- Hoodi
- Locality
- Mahadevapura
- PIN code
- 560066
- City
- Bengaluru
- State
- Karnataka
- Coordinates
- 12.98862, 77.72064
Distances to landmarks
Not found in public records yet: landmarksAbout Mahadevapura
Not found in public records yet: locality factsCommute times to tech parks and the airport
| To | Straight line | Peak-hour drive (estimate) |
|---|---|---|
| ITPL, Whitefield (main gate)Map point on OpenStreetMap (opens in a new tab) | 1.86 km | approx. 8 min |
| Outer Ring Road tech corridor (RMZ Ecospace, Bellandur)Map point on OpenStreetMap (opens in a new tab) | 8.39 km | approx. 34 min |
| Manyata Tech ParkMap point on OpenStreetMap (opens in a new tab) | 12.77 km | approx. 52 min |
| KSR Bengaluru City railway station (Majestic)Map point on OpenStreetMap (opens in a new tab) | 16.41 km | approx. 66 min |
| Electronic City Phase 1Map point on OpenStreetMap (opens in a new tab) | 16.59 km | approx. 67 min |
| Kempegowda International AirportMap point on OpenStreetMap (opens in a new tab) | 23.65 km | approx. 96 min |
How we calculate
Straight line: from the project’s map point on RERA to the destination’s point on OpenStreetMap.
Peak-hour drive is a rough estimate, not a route: straight line × 1.35 for the road network, at 20 km/h. Real times vary a lot with the route and the hour.
Sources:Source (openstreetmap.org) (opens in a new tab)How we calculate this
Schools and hospitals nearby
Within 2 km
- 24Schools and colleges13 schools, 7 colleges, 4 kindergartens
- 17Hospitals and clinics13 hospitals, 4 clinics
Nearest schools and colleges
- Sri Chaitanya Techno School · 0.44 km
- Gopalan International Schoool · 0.44 km
- GCEM-Gopalan College of Engineering and Management · 0.45 km
Nearest hospitals and clinics
- Manipal Hospitals Whitefield · 0.87 km
- Healing Hands Clinic - Whitefield, Bengaluru · 1 km
- Dr. Batra Clinic · 1.21 km
Places as mapped on OpenStreetMap (amenity=school, college, kindergarten, university; hospital, clinic), counted within 2 km in a straight line of the RERA map point. Volunteers map these, so some places may be missing or closed. Places data © OpenStreetMap contributors, extract of 5 Oct 2026.
Nearest metro station and railway
- Hoodi (ಹೂಡಿ)Open now — nearest operating metro station1.01 km
- Hoodi Nearest railway station0.83 km
Straight-line distances from the RERA map point to the station points mapped on OpenStreetMap; status (open or under construction) as tagged there. Places data © OpenStreetMap contributors, extract of 5 Oct 2026.
Lake and lake-buffer check
The nearest mapped lake is Hoodi Lake, 130 m from the project’s RERA map point.
The site boundary is not published as a shape, so its nearest edge can be closer than this point. Whether any building sits inside a lake buffer can only be checked on the approved plan.
- Hoodi Lake on OpenStreetMap (opens in a new tab) (ಸೀತಾರಾಮಪಾಳ್ಯ ಕೆರೆ)130 m
- Unnamed lake (mapped on OpenStreetMap) on OpenStreetMap (opens in a new tab) 773 m
- Seetharampalya Lake on OpenStreetMap (opens in a new tab) (ಸೀತಾರಾಮಪಾಳ್ಯ ಕೆರೆ)992 m
The buffer rule
Bengaluru’s lake buffer rule has changed over time: the National Green Tribunal ordered a 75 m buffer in May 2016; the Supreme Court set that order aside on 5 March 2019, leaving the 30 m buffer of the Revised Master Plan 2015. Check the current rule and the approved plan before relying on either number.
- LiveLaw: SC sets aside NGT order enlarging buffer zones (2019) (livelaw.in) (opens in a new tab)
- Citizen Matters: Shrinking lake buffers (citizenmatters.in) (opens in a new tab)
Shortest distance from the RERA map point to the mapped water edge (OpenStreetMap water polygons tagged lake or reservoir, or named lake/kere/tank). Mapped shorelines can differ from the revenue-record boundary of a lake. Places data © OpenStreetMap contributors, extract of 5 Oct 2026.
Sources:Source (openstreetmap.org) (opens in a new tab)Source (livelaw.in) (opens in a new tab)Source (citizenmatters.in) (opens in a new tab)How we calculate this
Satellite time-lapse of the site
Satellite photos load when you scroll to them.
Photos from Esri World Imagery Wayback, centred on the project’s map point; dates are the capture dates in Esri’s metadata. Loaded from Esri when you scroll here.
Sources:Source (livingatlas.arcgis.com) (opens in a new tab)
Pursuit Of A Radical Rhapsody floor plans, brochure and elevations
Documents the builder uploaded to Karnataka RERA, shown as filed. Tap a page to see it full size; the full PDF opens on the RERA website.
Floor plans8 files

Tower 5: 6 Building 2- Residential 4 Basement 1st and typical floor plan.pdfFull PDF on RERA 
Tower 8: 6 Building 2- Residential 4 Basement 1st and typical floor planFiled 17 Sep 2022 · Full PDF on RERA 
Tower 8: 8 Building 2-Residential ground floor plan and elevationFiled 17 Sep 2022 · Full PDF on RERA 
Tower 5: 8 Building 2-Residential ground floor plan and elevation.pdfFull PDF on RERA 
Tower 8: 4 Building 2- Residential 2 Basement and typ even floor planFiled 17 Sep 2022 · Full PDF on RERA 
Tower 5: 4 Building 2- Residential 2 Basement and typ even floor plan.pdfFull PDF on RERA 
Tower 8: 7 Building 2-Residential 1 Basement 33 and Terrace floor planFiled 17 Sep 2022 · Full PDF on RERA 
Tower 5: 7 Building 2-Residential 1 Basement 33 and Terrace floor plan.pdfFull PDF on RERA
Approved building plan10 files

Phase 2: 24 BBMP Approved Plan SignatureFull PDF on RERA 
Tower 8: 24 BBMP Approved Plan SignatureFiled 17 Sep 2022 · Full PDF on RERA 
Tower 8: 3 Building Sanction PlanFiled 17 Sep 2022 · Full PDF on RERA 
Tower 5: 3 Building Sanction Plan.pdfFull PDF on RERA 
Tower 5: BBMP Approved Building Sanction Plan-1.pdfFull PDF on RERA 
Tower 8: BBMP Approved Building Sanction Plan-1Filed 17 Sep 2022 · Full PDF on RERA 
Tower 5: BBMP Approved Building Sanction Plan-2.pdfFull PDF on RERA 
Tower 8: BBMP Approved Building Sanction Plan-2Filed 17 Sep 2022 · Full PDF on RERA 
Tower 5: BBMP Approved Building Sanction Plan-3.pdfFull PDF on RERA 
Phase 2: BBMPDevelopmentPlanLowRes.pdfFull PDF on RERA
Approved layout plan6 files

Tower 5: Approved Layout PlanFull PDF on RERA 
Tower 8: Approved Layout PlanFull PDF on RERA 
Tower 5: Existing Layout PlanFull PDF on RERA 
Tower 8: Demarcation of Tower 8.pdfFull PDF on RERA 
Tower 5: Location and Demarcation.pdfFull PDF on RERA 
Tower 8: STP demarcation plan.pdfFull PDF on RERA
| Home type | Carpet area | Homes |
|---|---|---|
| 2 BHK | 846 – 850 sq ft | 12 |
| 3 BHK | 1,505 – 2,678 sq ft | 642 |
| 4 BHK | 2,959 – 3,864 sq ft | 35 |
| 5 BHK | 5,336 – 5,428 sq ft | 4 |
| Commercial | 8,234 – 18,056 sq ft | 22 |
Home types, counts and carpet areas as filed with Karnataka RERA (carpet area, not super built-up).
We have not collected floor-plan drawings; the builder’s sales team can share them.
Pursuit Of A Radical Rhapsody possession date and construction status
Timeline
- 1 Nov 2018Phase 2: Project start date given to RERA
- 1 Nov 2018Phase III: Project start date given to RERA
- 2 Jan 2019Phase 2: Registered with Karnataka RERA
- 17 Aug 2020Phase III: Registered with Karnataka RERA
- 22 Sep 2022Tower 8: Registered with Karnataka RERA
- 1 Oct 2022Tower 8: Project start date given to RERA
- 1 Dec 2022Tower 5: Project start date given to RERA
- 28 Dec 2022Tower 5: Registered with Karnataka RERA
- 3 Dec 2024Phase III: Promoter applied to RERA for completion
- 30 Jun 2026Phase 2: Completion date given at registration
- 30 Jun 2026Phase III: Completion date given at registration
- 30 Mar 2027Phase 2: Covid Extension: completion date moved to this date
- 30 Sep 2029Tower 8: Completion date given at registration
- 1 Dec 2029Tower 5: Completion date given at registration
Construction pace from RERA quarterly filings (Phase 2)
At the average pace so far, construction would reach 100% around Jan 2034 — about 82 months after the completion date on RERA (30 Mar 2027).
This project has 4 RERA registrations; the chart uses Phase 2, the one with the most quarterly filings.
- Filed on RERA
- Average pace since start
- RERA completion date
Quarterly filings
| Quarter | Filed on | Built | Homes booked |
|---|---|---|---|
| Q2 2026-27to 30 Sep 2026 | 15 Oct 2026 | 52% | 246 of 264 |
| Q1 2026-27to 30 Jun 2026 | 15 Jul 2026 | 51% | 243 of 264 |
| Q4 2025-26to 31 Mar 2026 | 15 Apr 2026 | 54% | 239 of 264 |
| Q3 2025-26to 31 Dec 2025 | 28 Jan 2026 | 55% | 239 of 264 |
How we calculate
Average pace = % built ÷ months since the start date in the RERA record. Here: 52% ÷ 94.9 months (1 Nov 2018 to 30 Sep 2026) = 0.5% a month.
Estimated finish = latest filing date + (100 − % built) ÷ pace = 30 Sep 2026 + 48 ÷ 0.5 = 87.6 months → Jan 2034. This is an estimate, not a date from the builder or RERA.
Pace between filings = (52% − 55%) ÷ 9 months = -0.3% a month.
A straight line is a simplification: the builder reports one overall %, which mixes excavation, structure and finishing, and work rarely moves at a constant speed. The % values are the promoter’s own figures filed with RERA, not checked by us.
Sources:Source (rera.karnataka.gov.in) (opens in a new tab)How we calculate this
Approvals and documents checklist
30 rows: approvals. Scroll inside the table to see them all.
| Approval | Authority | Source |
|---|---|---|
| Building plan (Phase 2) | BDA - Bangalore Development Authority | Source (rera.karnataka.gov.in) (opens in a new tab) |
| Building plan (Phase III) | BBMP - Bruhat Bengaluru Mahanagara Palike | Source (rera.karnataka.gov.in) (opens in a new tab) |
| Building plan (Tower 8) | BDA - Bangalore Development Authority · No. BBMP/Ad.Com./MDP/0099/22-23 · dated 2022-09-15 | Source (rera.karnataka.gov.in) (opens in a new tab) |
| Land conversion (2 orders) (Tower 8) | DC Bengaluru · No. ALN[E.K.H.W.]SR 177A/2011-12 and 1 more · dated 2016-04-20 | Source (rera.karnataka.gov.in) (opens in a new tab) |
| Commencement Certificate (Tower 8) | scan uploaded to RERA | Source (rera.karnataka.gov.in) (opens in a new tab) |
| Electricity Permission Letter (Tower 8) | scan uploaded to RERA | Source (rera.karnataka.gov.in) (opens in a new tab) |
| Water Permission Letter (Tower 8) | scan uploaded to RERA | Source (rera.karnataka.gov.in) (opens in a new tab) |
| Approved Layout Plan (Tower 8) | scan uploaded to RERA | Source (rera.karnataka.gov.in) (opens in a new tab) |
| Change of Land Use (Tower 8) | scan uploaded to RERA | Source (rera.karnataka.gov.in) (opens in a new tab) |
| ESCOM/Electricity (Tower 8) | scan uploaded to RERA | Source (rera.karnataka.gov.in) (opens in a new tab) |
| KWSSB/Water (Tower 8) | scan uploaded to RERA | Source (rera.karnataka.gov.in) (opens in a new tab) |
| Airport Authority of India (Tower 8) | scan uploaded to RERA | Source (rera.karnataka.gov.in) (opens in a new tab) |
| KSPCB (Tower 8) | scan uploaded to RERA | Source (rera.karnataka.gov.in) (opens in a new tab) |
| SEIAA (Tower 8) | scan uploaded to RERA | Source (rera.karnataka.gov.in) (opens in a new tab) |
| Building plan (Tower 5) | BBMP - Bruhat Bengaluru Mahanagara Palike · No. BBMP/Ad.Com./MDP/0099/22-23 · dated 2022-09-15 | Source (rera.karnataka.gov.in) (opens in a new tab) |
| Land conversion (3 orders) (Tower 5) | DC Bengaluru · No. BDS/ALN/SR/6479/73-74 and 2 more · dated 2015-09-09 | Source (rera.karnataka.gov.in) (opens in a new tab) |
| Commencement Certificate (Tower 5) | scan uploaded to RERA | Source (rera.karnataka.gov.in) (opens in a new tab) |
| Electricity Permission Letter (Tower 5) | scan uploaded to RERA | Source (rera.karnataka.gov.in) (opens in a new tab) |
| Water Permission Letter (Tower 5) | scan uploaded to RERA | Source (rera.karnataka.gov.in) (opens in a new tab) |
| Approved Layout Plan (Tower 5) | scan uploaded to RERA | Source (rera.karnataka.gov.in) (opens in a new tab) |
| Approved Building/Plotting Plan (Tower 5) | scan uploaded to RERA | Source (rera.karnataka.gov.in) (opens in a new tab) |
| Approved Section Of Building/Infrastructure Plan of Plotting (Tower 5) | scan uploaded to RERA | Source (rera.karnataka.gov.in) (opens in a new tab) |
| Change of Land Use (Tower 5) | scan uploaded to RERA | Source (rera.karnataka.gov.in) (opens in a new tab) |
| District Magistrate (Tower 5) | scan uploaded to RERA | Source (rera.karnataka.gov.in) (opens in a new tab) |
| Conversion Certificate under section 95 of the KLR Act 1964 (Tower 5) | scan uploaded to RERA | Source (rera.karnataka.gov.in) (opens in a new tab) |
| ESCOM/Electricity (Tower 5) | scan uploaded to RERA | Source (rera.karnataka.gov.in) (opens in a new tab) |
| KWSSB/Water (Tower 5) | scan uploaded to RERA | Source (rera.karnataka.gov.in) (opens in a new tab) |
| Airport Authority of India (Tower 5) | scan uploaded to RERA | Source (rera.karnataka.gov.in) (opens in a new tab) |
| KSPCB (Tower 5) | scan uploaded to RERA | Source (rera.karnataka.gov.in) (opens in a new tab) |
| SEIAA (Tower 5) | scan uploaded to RERA | Source (rera.karnataka.gov.in) (opens in a new tab) |
Documents uploaded to RERA (Tower 5)
- Building or layout plan · Approved drawings from the planning authorityFiled on RERA ✓ — BBMP - Bruhat Bengaluru Mahanagara Palike · No. BBMP/Ad.Com./MDP/0099/22-23 · dated 15 Sep 2022
- Commencement certificate · Permission to start buildingFiled on RERA ✓ — scanned copy uploaded; number and date not read yet
- Environment clearance · SEIAA KarnatakaFiled on RERA ✓ — scanned copy uploaded; number and date not read yet
- Fire NOC · Karnataka Fire and Emergency ServicesNot on RERA yet
- Pollution board consent · KSPCBFiled on RERA ✓ — scanned copy uploaded; number and date not read yet
- Water and sewerage · BWSSBFiled on RERA ✓ — scanned copy uploaded; number and date not read yet
- Electricity · BESCOMFiled on RERA ✓ — scanned copy uploaded; number and date not read yet
- Height clearance · Airports Authority of IndiaFiled on RERA ✓ — scanned copy uploaded; number and date not read yet
- Occupancy certificate (OC) · Issued only when the building is finishedNot on RERA yet — expected at completion
From the documents the promoter uploaded to Karnataka RERA, collected 22 Oct 2026. “Filed” means a document is on RERA — we have not checked its contents or validity. Not every approval applies to every project (for example, smaller projects may not need an environment clearance). Each phase is registered separately; this list is for the phase named above. The project page on RERA lists each upload.
Pursuit Of A Radical Rhapsody RERA complaints and orders
5 complaints as on Source (rera.karnataka.gov.in) (opens in a new tab)
| Complaint ref | Filed | Subject | Status | Source |
|---|---|---|---|---|
| 01153/2026 | 25 Sep 2026 | Delay interest claim under Sec 18(1), past committed date 30-11-2025 | Scrutiny completed | Source (rera.karnataka.gov.in) (opens in a new tab) |
| 00166/2026 | 23 Feb 2026 | Complaint under proviso to section 18(1) of the rera (real estate regulation & development act), 2016, for interest | Posted for orders | Source (rera.karnataka.gov.in) (opens in a new tab) |
| CMP/210926/0008383 | 26 Sep 2021 | Project Unit possession date is delayed from the date agreed upon during signing the sales deed. | Disposed | Source (rera.karnataka.gov.in) (opens in a new tab) |
| CMP/200204/0005367 | 4 Feb 2020 | Project Delayed - Return of amount | Disposed ao | Source (rera.karnataka.gov.in) (opens in a new tab) |
| CMP/191216/0004995 | 16 Dec 2019 | Not returning full refund | Disposed ao | Source (rera.karnataka.gov.in) (opens in a new tab) |
Court and consumer cases
We list case numbers, courts and outcomes only — never names of private individuals.
About Total Environment Habitat Private Limited
- Promoter type
- Company
- Projects on this site
- 2
- RERA complaints against promoter
- 26
- Company number (CIN)
- U45201KA2010PTC054651
From Karnataka RERA, as collected so far (22 Oct 2026). Complaints are those RERA lists against this promoter across all its projects.
Total Environment Habitat Private Limited’s RERA recordTotal Environment Habitat Private Limited delivery record
- 2Projects in Bengaluru on RERA5 approved registrations under Total Environment Habitat Private Limited in Bengaluru Urban and Rural. Source (rera.karnataka.gov.in) (opens in a new tab)
- 1,049Homes registeredAs stated in each registrations.
- 26RERA complaints11 open, 15 disposed. as on Source (rera.karnataka.gov.in) (opens in a new tab)
- 24.8Complaints per 1,000 homes26 complaints ÷ 1,049 homes in its 5 registrations on Karnataka RERA in Bengaluru.
- 1Completion filed on RERARegistrations where the promoter applied to RERA for completion; 1 with an occupancy certificate on RERA.
- 1 of 1Filed by the date given at registrationMedian gap 0 months (on-time ones count as 0). The completion application can come after handover, so this is an upper bound on lateness.
What the complaints are about
26 complaint subjects as written on RERA, as on . Each subject is sorted into one group by keywords (first match wins: delay, refund, registration, quality, litigation, association); one complaint often raises several issues. Source (rera.karnataka.gov.in) (opens in a new tab)
Completion filed on RERA
| Project | Date at registration | Completion filed | Gap |
|---|---|---|---|
| Pursuit Of A Radical Rhapsody Phase IIIOC on RERA | 30 Jun 2026 | 3 Dec 2024 | By the date |
Measured against the completion date given at registration; many projects had RERA extensions (including the COVID-period extension), shown under the date.
Sources:Source (rera.karnataka.gov.in) (opens in a new tab)How we calculate this
What’s changed since Nov 2018
- 30 Mar 2027Phase 2: Completion date extended to 30 Mar 2027 Source (rera.karnataka.gov.in) (opens in a new tab)
- 15 Oct 2026Phase 2: Quarterly update filed for Q2 2026-27: 52% built, 246 of 264 homes booked Source (rera.karnataka.gov.in) (opens in a new tab)
- 15 Oct 2026Tower 8: Quarterly update filed for Q2 2026-27: 9% built, 312 of 362 homes booked Source (rera.karnataka.gov.in) (opens in a new tab)
- 15 Oct 2026Tower 5: Quarterly update filed for Q2 2026-27: 28% built, 108 of 130 homes booked Source (rera.karnataka.gov.in) (opens in a new tab)
- 25 Sep 2026Complaint 01153/2026 filed with RERA: “Delay interest claim under Sec 18(1), past committed date 30-11-2025” — now scrutiny completed Source (rera.karnataka.gov.in) (opens in a new tab)
- 15 Jul 2026Phase 2: Quarterly update filed for Q1 2026-27: 51% built, 243 of 264 homes booked Source (rera.karnataka.gov.in) (opens in a new tab)
- 15 Jul 2026Tower 8: Quarterly update filed for Q1 2026-27: 9% built, 307 of 362 homes booked Source (rera.karnataka.gov.in) (opens in a new tab)
- 15 Jul 2026Tower 5: Quarterly update filed for Q1 2026-27: 28% built, 115 of 130 homes booked Source (rera.karnataka.gov.in) (opens in a new tab)
- 15 Apr 2026Phase 2: Quarterly update filed for Q4 2025-26: 54% built, 239 of 264 homes booked Source (rera.karnataka.gov.in) (opens in a new tab)
- 15 Apr 2026Tower 8: Quarterly update filed for Q4 2025-26: 8% built, 339 of 362 homes booked Source (rera.karnataka.gov.in) (opens in a new tab)
- 15 Apr 2026Tower 5: Quarterly update filed for Q4 2025-26: 34% built Source (rera.karnataka.gov.in) (opens in a new tab)
- 23 Feb 2026Complaint 00166/2026 filed with RERA: “Complaint under proviso to section 18(1) of the rera (real estate regulation & development act), 2016, for interest” — now posted for orders Source (rera.karnataka.gov.in) (opens in a new tab)
- 28 Jan 2026Phase 2: Quarterly update filed for Q3 2025-26: 55% built, 239 of 264 homes booked Source (rera.karnataka.gov.in) (opens in a new tab)
- 28 Jan 2026Tower 8: Quarterly update filed for Q3 2025-26: 59% built, 296 of 362 homes booked Source (rera.karnataka.gov.in) (opens in a new tab)
- 27 Jan 2026Tower 5: Quarterly update filed for Q3 2025-26: 60% built, 113 of 130 homes booked Source (rera.karnataka.gov.in) (opens in a new tab)
- 3 Dec 2024Phase III: Promoter applied to RERA for completion (occupancy certificate on RERA) Source (rera.karnataka.gov.in) (opens in a new tab)
- 28 Dec 2022Tower 5: Registered with Karnataka RERA (PRM/KA/RERA/1251/446/PR/281222/005565); completion date 1 Dec 2029 Source (rera.karnataka.gov.in) (opens in a new tab)
- 1 Dec 2022Tower 5: Project start date in the RERA record Source (rera.karnataka.gov.in) (opens in a new tab)
- 1 Oct 2022Tower 8: Project start date in the RERA record Source (rera.karnataka.gov.in) (opens in a new tab)
- 22 Sep 2022Tower 8: Registered with Karnataka RERA (PRM/KA/RERA/1251/446/PR/220922/005261); completion date 30 Sep 2029 Source (rera.karnataka.gov.in) (opens in a new tab)
- 15 Sep 2022Tower 8: Building plan approved by BDA - Bangalore Development Authority (No. BBMP/Ad.Com./MDP/0099/22-23) Source (rera.karnataka.gov.in) (opens in a new tab)
- 15 Sep 2022Tower 5: Building plan approved by BBMP - Bruhat Bengaluru Mahanagara Palike (No. BBMP/Ad.Com./MDP/0099/22-23) Source (rera.karnataka.gov.in) (opens in a new tab)
- 26 Sep 2021Complaint CMP/210926/0008383 filed with RERA: “Project Unit possession date is delayed from the date agreed upon during signing the sales deed.” — now disposed Source (rera.karnataka.gov.in) (opens in a new tab)
- 17 Aug 2020Phase III: Registered with Karnataka RERA (PRM/KA/RERA/1251/446/PR/200817/003551); completion date 30 Jun 2026 Source (rera.karnataka.gov.in) (opens in a new tab)
- 4 Feb 2020Complaint CMP/200204/0005367 filed with RERA: “Project Delayed - Return of amount” — now disposed Source (rera.karnataka.gov.in) (opens in a new tab)
- 16 Dec 2019Complaint CMP/191216/0004995 filed with RERA: “Not returning full refund” — now disposed Source (rera.karnataka.gov.in) (opens in a new tab)
- 2 Jan 2019Phase 2: Registered with Karnataka RERA (PRM/KA/RERA/1251/446/PR/190102/002271); completion date 30 Jun 2026 Source (rera.karnataka.gov.in) (opens in a new tab)
- 1 Nov 2018Phase 2: Project start date in the RERA record Source (rera.karnataka.gov.in) (opens in a new tab)
- 1 Nov 2018Phase III: Project start date in the RERA record Source (rera.karnataka.gov.in) (opens in a new tab)
Newest first. When the RERA crawl sees a new filing, complaint or extension, it is added here with its date.
Home loan EMI calculator
- Monthly EMI
- —
- Down payment
- —
- Loan amount
- —
- Total interest
- —
A calculation only, from the numbers you enter — not a loan offer.
All-in cost: GST, registration and other charges
The calculator loads when you scroll to it.
Assumptions
- Base price: the builder’s price is not published in a form we could collect — enter it from the cost sheet.
- GST 5% on the base price and charges — the usual rate for an under-construction home that is not “affordable housing” (1%).
- Stamp duty about 5.6% and registration 2% — the Karnataka rule (registration was raised from 1% to 2% on 31 Aug 2025). Calculated on the agreement value.
- Car parking, other charges and the maintenance deposit are not in the public record we collect; enter them from the builder’s cost sheet.
- Loan on the agreement value (banks usually lend up to 75–90%); EMI is the standard reducing-balance formula. Example rate only — use your bank’s quote.
Pursuit Of A Radical Rhapsody FAQs
What is Pursuit Of A Radical Rhapsody?
It is a mixed-use project by Total Environment Habitat Private Limited located in Hoodi, Bengaluru East, comprising 715 homes across multiple phases and towers.
How many homes are in Pursuit Of A Radical Rhapsody?
The project has 715 homes in total across 4 RERA registrations: Phase 2 (201 homes), Phase III (22 commercial units), Tower 8 (362 homes), and Tower 5 (130 homes).
What home types are available in Pursuit Of A Radical Rhapsody?
The project offers 2 BHK, 3 BHK, 4 BHK, 5 BHK, and commercial units. Carpet areas range from 846 sq ft for 2 BHK homes to 18,056 sq ft for commercial units.
What is the completion date for Pursuit Of A Radical Rhapsody?
Completion dates vary by phase: Phase 2 is 30 March 2027, Phase III is 30 June 2026, Tower 8 is 30 September 2029, and Tower 5 is 1 December 2029.
Has Phase 2 had a completion date extension?
Yes, Phase 2 had a Covid Extension and the completion date was extended to 30 March 2027.
What is the construction progress of Pursuit Of A Radical Rhapsody?
As of Q2 2026-27, Phase 2 is 52% complete, Tower 8 is 9% complete, and Tower 5 is 28% complete.
How many homes are booked in Pursuit Of A Radical Rhapsody?
As of Q2 2026-27, Phase 2 has 246 homes booked, Tower 8 has 312 homes booked, and Tower 5 has 108 homes booked.
Are there RERA complaints against Pursuit Of A Radical Rhapsody?
There are 5 RERA complaints on the project, all registered against Phase 2.
How many RERA complaints are against Total Environment Habitat Private Limited across all projects?
There are 26 RERA complaints against Total Environment Habitat Private Limited across all projects in the RERA records.
What are the RERA registration numbers for Pursuit Of A Radical Rhapsody?
The RERA registration numbers are: Phase 2 (PRM/KA/RERA/1251/446/PR/190102/002271), Phase III (PRM/KA/RERA/1251/446/PR/200817/003551), Tower 8 (PRM/KA/RERA/1251/446/PR/220922/005261), and Tower 5 (PRM/KA/RERA/1251/446/PR/281222/005565).
Written by AI from the RERA record above on 22 Oct 2026. Answers use only that record; check them against the source before you decide.
Questions about Pursuit Of A Radical Rhapsody
No questions published yet. Ask the first one: you get an instant answer from this page’s public record, and our team follows up on anything the record does not show.
Bought a home from Total Environment Habitat Private Limited? Review the builder.
Reviews of Total Environment Habitat Private Limited by verified buyers
No verified reviews of Total Environment Habitat Private Limited yet. If you bought a home from them, your review helps other buyers.
How reviews work: only buyers and owners can review; we confirm each purchase by phone before publishing, publish positive and negative reviews alike, never accept payment for reviews, and the builder may reply.
Similar projects within 5 km
| Project | Distance | Homes | Possession (RERA) | Built | Complaints | Price |
|---|---|---|---|---|---|---|
| Embassy East AvenueVigor Developments Limited | 0.7 km | 393 | Sep 2028 | 83% | 1 | Not collected |
| Vikyath ElegantVikyath Properties Pvt Ltd | 0.9 km | 80 | Dec 2025 | — | 0 | Not collected |
| Jai SignatureJai Shelters , H.A.Venugopal & 10 Others | 1.1 km | 50 | Mar 2028 | — | 0 | Not collected |
| Jai Fortune SquareJai Builders | 1.2 km | 136 | Dec 2025 | — | 0 | Not collected |
| Garuda GrandBalaji Buildres | 1.2 km | 136 | Mar 2028extended | 87% | 0 | Not collected |
| Jai Kings LandJai Shelters | 1.5 km | 378 | Dec 2028 | — | 0 | Not collected |
Projects of the same kind within 5 km in a straight line of this project’s RERA map point, nearest first. % built is the promoter’s latest quarterly figure on RERA (shown for single-registration projects); prices are from the builder’s own website where we found one.
Sources and last checked dates
Collected on 22 Oct 2026 by AI research agents reading public pages. Facts are written in our own words. Not found yet: price; court cases; landmarks; specifications; news.
How to check on RERA: On rera.karnataka.gov.in/viewAllProjects, type the registration number in 'Registration No', press Search, then click the 'View Project Details' icon. Complaints open from the 'Complaints / Litigation' icon in the same row. Registration numbers: PRM/KA/RERA/1251/446/PR/190102/002271, PRM/KA/RERA/1251/446/PR/200817/003551, PRM/KA/RERA/1251/446/PR/220922/005261, PRM/KA/RERA/1251/446/PR/281222/005565.
- RERA record last checked: 22 Oct 2026
- Last change in the record (registration, quarterly filing or complaint): 22 Oct 2026
How this page is made: software builds it from public records (Karnataka RERA filings, OpenStreetMap, the builder’s own website). AI is used only to read filings into fields and to write the plain-English summary and FAQ answers, which are checked against the record. Facts are checked automatically against the RERA filing. Methodology · How we earn · Report an error
More new projects in Mahadevapura
Hoodi, near MahadevapuraUnder constructionRERA registeredBuyers’ group openEmbassy East Avenue
by Vigor Developments
Price: Price on requestGet brochure & price →
- 1 BHK, 1.5 BHK, 2 BHK, 2.5 BHK, +1 more
- 581 – 1,444 sq ft
- Sep 2028
393 homes · 1 RERA complaint
Be one of the first 10 buyers in this groupFounding members — it’s free
Join group for Embassy East Avenue
Hoodi, MahadevapuraReady to moveRERA registeredBuyers’ group openVikyath Elegant
by Vikyath Properties
Price: Price on requestGet brochure & price →
- 2 BHK, 3 BHK
- 649 – 1,103 sq ft
- Dec 2025
80 homes
Be one of the first 10 buyers in this groupFounding members — it’s free
Join group for Vikyath Elegant
Hoodi, near MahadevapuraUnder constructionRERA registeredBuyers’ group openJai Signature
by Jai Shelters , H.A.Venugopal & 10 Others
Price: Price on requestGet brochure & price →
- 2 BHK, 3 BHK
- 418 – 723 sq ft
- Mar 2028
50 homes
Be one of the first 10 buyers in this groupFounding members — it’s free
Join group for Jai Signature