Nature'S Nest at a glance
- Possession (RERA)Dec 2031Karnataka RERA
- Construction17% built · on pace for Mar 2029RERA filing to 30 Sep 2026; estimate from average pace
- Homes booked2 of 352 (1%)RERA update · as on 30 Sep 2026
- RERA complaints (project)None listedKarnataka RERA · as on 19 Oct 2026
- Approvals filed7 of 9 on RERAKarnataka RERA uploads · 19 Oct 2026
- Nearest metroWhitefield (Kadugodi) · 3.94 kmstraight line · OpenStreetMap, 5 Oct 2026
- Airport driveapprox. 79 min at peak19.6 km straight line · estimate
- Nearest lakeBidare Agrahara Lake · 313 mFrom the RERA map point · OpenStreetMap, 5 Oct 2026
Project summary
Nature'S Nest is a residential project by NPS Developers in Bengaluru with 352 homes, registered with Karnataka RERA. The completion date on RERA is 31 Dec 2031.
Not in the RERA record we collected yet: locality. This page fills in as the record is collected.
Facts collected on 19 Oct 2026 from public records — each linked to its source. Free for buyers. If you book through us, the builder pays us a commission.
Nature'S Nest buyers’ group: join to ask for a group price
No one has joined yet. Be one of the first 10 buyers in this group — the founding members.
Join free. When enough buyers have joined, our agent partner asks NPS Developers for a group price — for example a lower price, an easier payment plan or waived charges. Nothing is promised: you see what the builder offers and book directly with the builder if you want to. Free for buyers. If you book through us, the builder pays us a commission.
- Gathering buyers
- Talking to the builder
- Group offer
- Group site visit
- Booking
0 buyers have joined · 0 committed
Committed buyers have confirmed their budget, home type and timeline with us on a call; builders negotiate with them. Joining is free and never obliges you to buy.
Join the Nature'S Nest buyers’ groupHow group buying works
See it for yourself
Visit the site with our team, or get a call to clear your questions. Free, no obligation.
Key facts: home types, towers, land and possession
- Home types
- 2 BHK, 3 BHK, 4 BHK
- Carpet area
- 800 – 1,498 sq ft
- Towers
- 2
- Floors
- 27
- Total homes
- 352
- Land
- 6.09 acres
- Possession (RERA)
- Dec 2031
- Built (RERA update)
- 17%
Nature'S Nest RERA number and registration details
- RERA number
- PRM/KA/RERA/1251/446/PR/090626/008711
- Registered on
- 9 Jun 2026
- Promised completion
- 31 Dec 2031
- Extended to
- No extension recorded
- RERA status
- Under construction
- Homes booked
- 2 of 352 as on
- Price
- Not found in public records yet: price
- Project type
- Residential
Towers and blocks (RERA filing)
| Tower | Floors | Basements | Homes |
|---|---|---|---|
| 1 | 27 | 2 | 216 |
| 2 | 17 | 2 | 136 |
A dash (—) means the filing did not state that value.
Summary in plain English
Nature'S Nest is a residential project by NPS Developers with 352 homes across 2 towers in Bengaluru East, located in PIN code 560067. The project has 3 BHK, 2 BHK and 4 BHK homes and is registered with RERA for completion by 31 December 2031.
Written by AI from the RERA record above on 19 Oct 2026. Every number in it was checked against that record; if anything differs, the record wins.
Open space, home loans, escrow and other details
- Open space
- 100% of land
- Water and power
- Water source filed with RERA: BoreWell
- Home loans: approved banks
- Not found in public records yet: bank approvals
- Payment plans
- Not found in public records yet: payment plans
- Maintenance
- Not found in public records yet: maintenance
- Car parking
- Not found in public records yet: car parking charge
- Escrow bank (RERA)
- Bank of Baroda, SANJAY NAGAR
- Building plan (RERA)
- BDA - Bangalore Development Authority · No. BDA/N M/A S/A .A-5/TP-4/P/70/2025-26 · dated 16 Feb 2026
- Project cost declared to RERA
- ₹210 Cr
Open area as a share of the land, from the areas filed with RERA (includes driveways and landscaped areas).
Amenities
- Electricity
- Smart Home Automation
- CCTV Surveillance
- Club House
- Community Hall
- Outdoor Sports facility
- Indoor Sports facility
- Swimming Pool
- Gym
- Parks
- Power Backup
- Piped Gas
- Water and Sanitation
- Air Conditioning
Amenities and internal works as filed by the promoter with Karnataka RERA; we have not visited the site.
Nature'S Nest location and address
- Address
- Sy. No 45/1, 46, 47/2, 47/3, 47/4, 47/5, 47/6, 54/4, 54/6, 54/11, 54/12, 57/3, 57/4, 57/5, 57/9, 57/10, 59/2, 59/3, 59/4, 59/5, 59/6, BIDARE AGRAHARA , BIDARAHALLI HOBLI , Bengaluru East , Bengaluru Urban, Karnataka - 560067
- Village (RERA)
- Not found in public records yet: village
- Locality
- Old Madras RoadAlso known as OMR, Old Madras Road
- PIN code
- 560067
- City
- Bengaluru
- State
- Karnataka
- Coordinates
- 13.02917, 77.74578
Distances to landmarks
Not found in public records yet: landmarksAbout Old Madras Road
Not found in public records yet: locality factsCommute times to tech parks and the airport
| To | Straight line | Peak-hour drive (estimate) |
|---|---|---|
| ITPL, Whitefield (main gate)Map point on OpenStreetMap (opens in a new tab) | 4.7 km | approx. 19 min |
| Outer Ring Road tech corridor (RMZ Ecospace, Bellandur)Map point on OpenStreetMap (opens in a new tab) | 13.65 km | approx. 55 min |
| Manyata Tech ParkMap point on OpenStreetMap (opens in a new tab) | 13.8 km | approx. 56 min |
| Kempegowda International AirportMap point on OpenStreetMap (opens in a new tab) | 19.6 km | approx. 79 min |
| KSR Bengaluru City railway station (Majestic)Map point on OpenStreetMap (opens in a new tab) | 19.92 km | approx. 81 min |
| Electronic City Phase 1Map point on OpenStreetMap (opens in a new tab) | 21.8 km | approx. 88 min |
How we calculate
Straight line: from the project’s map point on RERA to the destination’s point on OpenStreetMap.
Peak-hour drive is a rough estimate, not a route: straight line × 1.35 for the road network, at 20 km/h. Real times vary a lot with the route and the hour.
Sources:Source (openstreetmap.org) (opens in a new tab)How we calculate this
Schools and hospitals nearby
Within 2 km
- 9Schools and colleges8 schools, 1 colleges, 0 kindergartens
- 3Hospitals and clinics3 hospitals, 0 clinics
Nearest schools and colleges
- Auxillium School · 1.22 km
Nearest hospitals and clinics
- Geetha Hospital · 1.36 km
- S.N. Hospital · 1.4 km
- Kannamangala Primary Health Center · 1.55 km
Places as mapped on OpenStreetMap (amenity=school, college, kindergarten, university; hospital, clinic), counted within 2 km in a straight line of the RERA map point. Volunteers map these, so some places may be missing or closed. Places data © OpenStreetMap contributors, extract of 5 Oct 2026.
Nearest metro station and railway
- Whitefield (Kadugodi) (ವೈಟ್ಫೀಲ್ಡ್ (ಕಾಡುಗೋಡಿ))Open now — nearest operating metro station3.94 km
- Whitefield (ವೈಟ್ಫೀಲ್ಡ್)Nearest railway station4.02 km
Straight-line distances from the RERA map point to the station points mapped on OpenStreetMap; status (open or under construction) as tagged there. Places data © OpenStreetMap contributors, extract of 5 Oct 2026.
Lake and lake-buffer check
The nearest mapped lake is Bidare Agrahara Lake, 313 m from the project’s RERA map point.
The site boundary is not published as a shape, so its nearest edge can be closer than this point. Whether any building sits inside a lake buffer can only be checked on the approved plan.
- Bidare Agrahara Lake on OpenStreetMap (opens in a new tab) 313 m
- Unnamed lake (mapped on OpenStreetMap) on OpenStreetMap (opens in a new tab) 1,163 m
- Yellamallappa Chetty Lake on OpenStreetMap (opens in a new tab) (ಯೆಲ್ಲಮಲ್ಲಪ್ಪ ಚೆಟ್ಟಿ ಕೆರೆ)1,323 m
The buffer rule
Bengaluru’s lake buffer rule has changed over time: the National Green Tribunal ordered a 75 m buffer in May 2016; the Supreme Court set that order aside on 5 March 2019, leaving the 30 m buffer of the Revised Master Plan 2015. Check the current rule and the approved plan before relying on either number.
- LiveLaw: SC sets aside NGT order enlarging buffer zones (2019) (livelaw.in) (opens in a new tab)
- Citizen Matters: Shrinking lake buffers (citizenmatters.in) (opens in a new tab)
Shortest distance from the RERA map point to the mapped water edge (OpenStreetMap water polygons tagged lake or reservoir, or named lake/kere/tank). Mapped shorelines can differ from the revenue-record boundary of a lake. Places data © OpenStreetMap contributors, extract of 5 Oct 2026.
Sources:Source (openstreetmap.org) (opens in a new tab)Source (livelaw.in) (opens in a new tab)Source (citizenmatters.in) (opens in a new tab)How we calculate this
Satellite time-lapse of the site
Satellite photos load when you scroll to them.
Photos from Esri World Imagery Wayback, centred on the project’s map point; dates are the capture dates in Esri’s metadata. Loaded from Esri when you scroll here.
Sources:Source (livingatlas.arcgis.com) (opens in a new tab)
Nature'S Nest floor plans, brochure and elevations
Documents the builder uploaded to Karnataka RERA, shown as filed. Tap a page to see it full size; the full PDF opens on the RERA website.
Floor plans8 files

5 Plan Typical floor 1 to 17 Tower 1 & 2Filed 20 May 2026 · Full PDF on RERA 
5 Plan Typical floor 1 to 17 Tower 1 & 2Filed 25 May 2026 · Full PDF on RERA 
Plan Typical floor 1 to 17 Tower 1 & 2Filed 5 Jun 2026 · Full PDF on RERA 
Plan 18th FloorFiled 5 Jun 2026 · Full PDF on RERA 
Plan 20th to 27th FLoorFiled 5 Jun 2026 · Full PDF on RERA 
Plan Ground floorFiled 5 Jun 2026 · Full PDF on RERA 
Plan Lower basment floorFiled 5 Jun 2026 · Full PDF on RERA 
Plan Upper basement floorFiled 5 Jun 2026 · Full PDF on RERA
Elevations3 files

9 Plan ElevationFiled 20 May 2026 · Full PDF on RERA 
9 Plan ElevationFiled 25 May 2026 · Full PDF on RERA 
Plan ElevationFiled 5 Jun 2026 · Full PDF on RERA
Approved building plan3 files

Approved Building PlanFull PDF on RERA 
Approved PlanFiled 20 May 2026 · Full PDF on RERA 
Approved PlanFiled 25 May 2026 · Full PDF on RERA
Approved layout plan

Single Layout Plan - NPSFiled 5 Jun 2026 · Full PDF on RERA
| Home type | Carpet area | Homes |
|---|---|---|
| 2 BHK | 800 – 850 sq ft | 105 |
| 3 BHK | 1,047 – 1,185 sq ft | 220 |
| 4 BHK | 1,498 sq ft | 27 |
Home types, counts and carpet areas as filed with Karnataka RERA (carpet area, not super built-up).
We have not collected floor-plan drawings; the builder’s sales team can share them.
Nature'S Nest possession date and construction status
Promoter’s quarterly update to RERA for Q2 2026-27, submitted 2026-10-15.
By tower (Q2 2026-27)
Units sold and unsold, from RERA (Q2 2026-27)
| Type | Homes | Booked | Available |
|---|---|---|---|
| 2 BHK | 105 | 0 | 105 |
| 3 BHK | 220 | 2 | 218 |
| 4 BHK | 27 | 0 | 27 |
As reported by the promoter in the quarterly update to RERA, not verified by us.
Timeline
- 1 Apr 2026Project start date given to RERA
- 9 Jun 2026Registered with Karnataka RERA
- 31 Dec 2031Completion date given at registration
Construction pace from RERA quarterly filings
At the average pace so far, construction would reach 100% around Mar 2029 — about 34 months before the completion date on RERA (31 Dec 2031).
At the pace between the 2 quarterly filings we have (0% → 17% in 3 months), it would be around Dec 2027 — about 48 months before the RERA date.
- Filed on RERA
- Average pace since start
- Pace between filings (and 0% assumed at the start date)
- RERA completion date
Quarterly filings
| Quarter | Filed on | Built | Homes booked |
|---|---|---|---|
| Q2 2026-27to 30 Sep 2026 | 15 Oct 2026 | 17% | 2 of 352 |
| Q1 2026-27to 30 Jun 2026 | 12 Oct 2026 | 0% | 0 of 352 |
How we calculate
Average pace = % built ÷ months since the start date in the RERA record. Here: 17% ÷ 6 months (1 Apr 2026 to 30 Sep 2026) = 2.8% a month.
Estimated finish = latest filing date + (100 − % built) ÷ pace = 30 Sep 2026 + 83 ÷ 2.8 = 29.2 months → Mar 2029. This is an estimate, not a date from the builder or RERA.
Pace between filings = (17% − 0%) ÷ 3 months = 5.6% a month.
A straight line is a simplification: the builder reports one overall %, which mixes excavation, structure and finishing, and work rarely moves at a constant speed. The % values are the promoter’s own figures filed with RERA, not checked by us. Promoter’s quarterly update to RERA for Q2 2026-27, submitted 2026-10-15.
Sources:Source (rera.karnataka.gov.in) (opens in a new tab)How we calculate this
Approvals and documents checklist
| Approval | Authority | Source |
|---|---|---|
| Building plan | BDA - Bangalore Development Authority · No. BDA/N M/A S/A .A-5/TP-4/P/70/2025-26 · dated 2026-02-16 | Source (rera.karnataka.gov.in) (opens in a new tab) |
| Land conversion (21 orders) | DC · No. 5545 and 20 more · dated 2025-08-18 | Source (rera.karnataka.gov.in) (opens in a new tab) |
| Approved Building Plan | scan uploaded to RERA | Source (rera.karnataka.gov.in) (opens in a new tab) |
| ESCOM/Electricity | scan uploaded to RERA | Source (rera.karnataka.gov.in) (opens in a new tab) |
| KWSSB/Water | scan uploaded to RERA | Source (rera.karnataka.gov.in) (opens in a new tab) |
| KSPCB | scan uploaded to RERA | Source (rera.karnataka.gov.in) (opens in a new tab) |
| SEIAA | scan uploaded to RERA | Source (rera.karnataka.gov.in) (opens in a new tab) |
| Fire Force Department | scan uploaded to RERA | Source (rera.karnataka.gov.in) (opens in a new tab) |
| Airport Authority of India | scan uploaded to RERA | Source (rera.karnataka.gov.in) (opens in a new tab) |
Documents uploaded to RERA
- Building or layout plan · Approved drawings from the planning authorityFiled on RERA ✓ — BDA - Bangalore Development Authority · No. BDA/N M/A S/A .A-5/TP-4/P/70/2025-26 · dated 16 Feb 2026
- Commencement certificate · Permission to start buildingNot on RERA yet
- Environment clearance · SEIAA KarnatakaFiled on RERA ✓ — scanned copy uploaded; number and date not read yet
- Fire NOC · Karnataka Fire and Emergency ServicesFiled on RERA ✓ — scanned copy uploaded; number and date not read yet
- Pollution board consent · KSPCBFiled on RERA ✓ — scanned copy uploaded; number and date not read yet
- Water and sewerage · BWSSBFiled on RERA ✓ — scanned copy uploaded; number and date not read yet
- Electricity · BESCOMFiled on RERA ✓ — scanned copy uploaded; number and date not read yet
- Height clearance · Airports Authority of IndiaFiled on RERA ✓ — scanned copy uploaded; number and date not read yet
- Occupancy certificate (OC) · Issued only when the building is finishedNot on RERA yet — expected at completion
From the documents the promoter uploaded to Karnataka RERA, collected 19 Oct 2026. “Filed” means a document is on RERA — we have not checked its contents or validity. Not every approval applies to every project (for example, smaller projects may not need an environment clearance). The project page on RERA lists each upload.
Nature'S Nest RERA complaints
No complaints listed on Karnataka RERA for this registration as on Source (rera.karnataka.gov.in) (opens in a new tab)
Court and consumer cases
We list case numbers, courts and outcomes only — never names of private individuals.
About NPS Developers
- Promoter type
- Partnership Firm
- Projects on this site
- 1
- RERA complaints against promoter
- 0
- Company number (CIN)
- Not found in public records yet: CIN
From Karnataka RERA, as collected so far (19 Oct 2026). Complaints are those RERA lists against this promoter across all its projects.
NPS Developers’s RERA recordNPS Developers delivery record
- 1Projects in Bengaluru on RERA1 approved registration under NPS Developers in Bengaluru Urban and Rural. Source (rera.karnataka.gov.in) (opens in a new tab)
- 352Homes registeredAs stated in each registrations.
- 0RERA complaintsas on Source (rera.karnataka.gov.in) (opens in a new tab)
- 0Complaints per 1,000 homes0 complaints ÷ 352 homes in its 1 registration on Karnataka RERA in Bengaluru.
Sources:Source (rera.karnataka.gov.in) (opens in a new tab)How we calculate this
What’s changed since Feb 2026
- 15 Oct 2026Quarterly update filed for Q2 2026-27: 17% built, 2 of 352 homes booked Source (rera.karnataka.gov.in) (opens in a new tab)
- 12 Oct 2026Quarterly update filed for Q1 2026-27: 0% built, 0 of 352 homes booked Source (rera.karnataka.gov.in) (opens in a new tab)
- 9 Jun 2026Registered with Karnataka RERA (PRM/KA/RERA/1251/446/PR/090626/008711); completion date 31 Dec 2031 Source (rera.karnataka.gov.in) (opens in a new tab)
- 1 Apr 2026Project start date in the RERA record Source (rera.karnataka.gov.in) (opens in a new tab)
- 16 Feb 2026Building plan approved by BDA - Bangalore Development Authority (No. BDA/N M/A S/A .A-5/TP-4/P/70/2025-26) Source (rera.karnataka.gov.in) (opens in a new tab)
Newest first. No extension of the completion date is recorded on RERA. When the RERA crawl sees a new filing, complaint or extension, it is added here with its date.
Home loan EMI calculator
- Monthly EMI
- —
- Down payment
- —
- Loan amount
- —
- Total interest
- —
A calculation only, from the numbers you enter — not a loan offer.
All-in cost: GST, registration and other charges
The calculator loads when you scroll to it.
Assumptions
- Base price: the builder’s price is not published in a form we could collect — enter it from the cost sheet.
- GST 5% on the base price and charges — the usual rate for an under-construction home that is not “affordable housing” (1%).
- Stamp duty about 5.6% and registration 2% — the Karnataka rule (registration was raised from 1% to 2% on 31 Aug 2025). Calculated on the agreement value.
- Car parking, other charges and the maintenance deposit are not in the public record we collect; enter them from the builder’s cost sheet.
- Loan on the agreement value (banks usually lend up to 75–90%); EMI is the standard reducing-balance formula. Example rate only — use your bank’s quote.
Nature'S Nest FAQs
What is the completion date for Nature'S Nest?
According to the RERA record, the project completion date is 31 December 2031.
How many homes are in Nature'S Nest?
The project has 352 homes across 2 towers, with a maximum of 27 floors.
What home types are available at Nature'S Nest?
The project offers 4 BHK (27 homes), 3 BHK (220 homes) and 2 BHK (105 homes).
What is the carpet area range at Nature'S Nest?
The 4 BHK homes are 1,498 sq ft, 3 BHK homes range from 1,047 to 1,185 sq ft, and 2 BHK homes range from 800 to 850 sq ft.
What is the construction progress of Nature'S Nest?
As of 30 September 2026, the project is 17% complete.
How many homes have been booked at Nature'S Nest?
As of the quarter ended 30 September 2026, 2 homes have been booked out of 352 available.
What is the RERA registration number for Nature'S Nest?
The project is registered as PRM/KA/RERA/1251/446/PR/090626/008711, registered on 9 June 2026.
Are there any RERA complaints against Nature'S Nest?
No complaints have been filed against this project on RERA.
Where is Nature'S Nest located?
The project is located in Bengaluru East taluk, Bengaluru Urban district, PIN code 560067.
Who is the builder of Nature'S Nest?
The project is developed by NPS Developers, a partnership firm, with no complaints filed against the builder on RERA.
Written by AI from the RERA record above on 19 Oct 2026. Answers use only that record; check them against the source before you decide.
Questions about Nature'S Nest
No questions published yet. Ask the first one: you get an instant answer from this page’s public record, and our team follows up on anything the record does not show.
Bought a home from NPS Developers? Review the builder.
Reviews of NPS Developers by verified buyers
No verified reviews of NPS Developers yet. If you bought a home from them, your review helps other buyers.
How reviews work: only buyers and owners can review; we confirm each purchase by phone before publishing, publish positive and negative reviews alike, never accept payment for reviews, and the builder may reply.
Similar projects within 5 km
| Project | Distance | Homes | Possession (RERA) | Built | Complaints | Price |
|---|---|---|---|---|---|---|
| Amrutha Lake VistaAmrutha Shelters Private Limited | 0.4 km | 523 | Apr 2031 | 25% | 0 | Not collected |
| Assetz Bloom & DellApg Premium Residential Private Limited | 0.4 km | 446 | Oct 2027 | — | 0 | Not collected |
| Sarang By SumadhuraSumadhura Infracon Private Limited | 0.7 km | 410 | Jun 2027 | — | 0 | Not collected |
| Bren AsperaBren Corporation Private Limited | 1.2 km | 394 | Nov 2026extended | 94% | 0 | Not collected |
| Sattva AanganeSattva Resi Private Limited | 1.2 km | 625 | Oct 2032 | 3% | 0 | Not collected |
| Concorde EleveConcorde Housing Corporation Pvt Ltd | 1.3 km | 142 | Dec 2030 | 16% | 0 | Not collected |
Projects of the same kind within 5 km in a straight line of this project’s RERA map point, nearest first. % built is the promoter’s latest quarterly figure on RERA (shown for single-registration projects); prices are from the builder’s own website where we found one.
Sources and last checked dates
Collected on 19 Oct 2026 by AI research agents reading public pages. Facts are written in our own words. Not found yet: price; court cases; landmarks; specifications; news.
How to check on RERA: On rera.karnataka.gov.in/viewAllProjects, type the registration number in 'Registration No', press Search, then click the 'View Project Details' icon. Complaints open from the 'Complaints / Litigation' icon in the same row. Registration number: PRM/KA/RERA/1251/446/PR/090626/008711.
- RERA record last checked: 19 Oct 2026
- Last change in the record (registration, quarterly filing or complaint): 19 Oct 2026
How this page is made: software builds it from public records (Karnataka RERA filings, OpenStreetMap, the builder’s own website). AI is used only to read filings into fields and to write the plain-English summary and FAQ answers, which are checked against the record. Facts are checked automatically against the RERA filing. Methodology · How we earn · Report an error
More new projects in Old Madras Road
Bidare Agrahara, Old Madras RoadUnder constructionRERA registeredBuyers’ group openAmrutha Lake Vista
by Amrutha Shelters
Price: Price on requestGet brochure & price →
- 3 BHK
- 965 – 1,250 sq ft
- Apr 2031
523 homes
Be one of the first 10 buyers in this groupFounding members — it’s free
Join group for Amrutha Lake Vista
Doddabanahalli, Old Madras RoadUnder constructionRERA registeredBuyers’ group openAssetz Bloom & Dell
by Apg Premium Residential
Price: Price on requestGet brochure & price →
- Studio, 3 BHK, 4 BHK
- 231 – 1,775 sq ft
- Oct 2027
2 phases on RERA · 446 homes
Be one of the first 10 buyers in this groupFounding members — it’s free
Join group for Assetz Bloom & Dell
Doddabanahalli, Old Madras RoadUnder constructionRERA registeredBuyers’ group openSarang By Sumadhura
by Sumadhura Infracon
Price: Price on requestGet brochure & price →
- 2 BHK, 3 BHK, 4 BHK
- 770 – 1,640 sq ft
- Jun 2027
2 phases on RERA · 410 homes
Be one of the first 10 buyers in this groupFounding members — it’s free