Purva Orient Grand
3 & 4 BHK apartments by Puravankara Limited · Bengaluru
Bengaluru
- Under construction
- RERA registered
- residential
Listed price: ₹5.5 Cr – ₹9 Cr
Purva Orient Grand luxury apartments on Lalbagh Road, Bengaluru Artist’s impression · © Puravankara Limited · Source ↗ (opens in a new tab)
Purva Orient Grand at a glance
- Price from₹5.5 Cr · 4 BHKBuilder’s website · as on 17 Oct 2026
- All-in from₹6.19 Cr · 4 BHKBuilder price + GST, stamp duty, registration · 17 Oct 2026
- Possession (RERA)Jun 2027Karnataka RERA
- Construction51% built · on pace for Apr 2030 34 mo after RERA dateRERA filing to 31 Dec 2025; estimate from average pace
- Homes booked11 of 97 (11%)RERA update · as on 31 Dec 2025
- RERA complaints (project)None listedKarnataka RERA · as on 12 Oct 2026
- Approvals filed1 of 9 on RERAKarnataka RERA uploads · 12 Oct 2026
Project summary
Purva Orient Grand is a residential project by Puravankara Limited in Bengaluru with 97 homes, registered with Karnataka RERA. The completion date on RERA is 30 Jun 2027.
Not in the RERA record we collected yet: locality, map location. This page fills in as the record is collected.
Facts collected on 12 Oct 2026 from public records — each linked to its source. Free for buyers. If you book through us, the builder pays us a commission.
Purva Orient Grand buyers’ group: join to ask for a group price
No one has joined yet. Be one of the first 10 buyers in this group — the founding members.
Join free. When enough buyers have joined, our agent partner asks Puravankara Limited for a group price — for example a lower price, an easier payment plan or waived charges. Nothing is promised: you see what the builder offers and book directly with the builder if you want to. Free for buyers. If you book through us, the builder pays us a commission.
- Gathering buyers
- Talking to the builder
- Group offer
- Group site visit
- Booking
0 buyers have joined · 0 committed
Committed buyers have confirmed their budget, home type and timeline with us on a call; builders negotiate with them. Joining is free and never obliges you to buy.
Join the Purva Orient Grand buyers’ groupHow group buying works
See it for yourself
Visit the site with our team, or get a call to clear your questions. Free, no obligation.
Key facts: home types, towers, land and possession
- Home types
- 3 BHK, 4 BHK
- Carpet area
- 1,275 – 2,303 sq ft
- Towers
- 1
- Floors
- 24
- Total homes
- 97
- Land
- 1.16 acres
- Possession (RERA)
- Jun 2027
- Built (RERA update)
- 51%
Purva Orient Grand RERA number and registration details
- RERA number
- PRM/KA/RERA/1251/310/PR/210907/004299
- Registered on
- 7 Sep 2021
- Promised completion
- 30 Jun 2027
- Extended to
- No extension recorded
- RERA status
- New launch
- Homes booked
- 11 of 97 as on
- Price
- ₹5.5 Cr – ₹9 Cr as on
- Project type
- Residential
From the builder’s own website; see the price list below for size basis.
Towers and blocks (RERA filing)
| Tower | Floors | Basements | Homes |
|---|---|---|---|
| Purva Orient Grand | 24 | 2 | 97 |
A dash (—) means the filing did not state that value.
Purva Orient Grand price list
| Home type | Size | Price | ₹ per sq ft | Source |
|---|---|---|---|---|
| 3 & 4 BHK | —unknown | From ₹9 Cronwards | — | Source (puravankara.com) (opens in a new tab) |
| 4 BHK | —unknown | From ₹5.5 Cronwards | — | Source (puravankara.com) (opens in a new tab) |
As published by the builder on the date shown — not an offer, and not checked with the builder. Check whether the size is carpet or super built-up area before comparing.
Price per sq ft vs projects within 5 km
The builder’s published prices work out to about ₹23,900 – ₹41,700 per sq ft of carpet area.
| Home type | Builder price | Carpet area (RERA) | ₹ per sq ft carpet |
|---|---|---|---|
| 4 BHK | from ₹5.5 Crseen 17 Oct 2026 | 1,318 – 2,303 sq ft | ₹23,900 – ₹41,700 |
Worked out as the builder’s “from” price ÷ the largest and smallest carpet area RERA lists for that home type — we don’t know which unit the starting price is for. Builders usually say taxes and other charges are extra. Builder price list (puravankara.com) (opens in a new tab) RERA carpet areas (rera.karnataka.gov.in) (opens in a new tab)
Sources:Source (puravankara.com) (opens in a new tab)Source (rera.karnataka.gov.in) (opens in a new tab)How we calculate this
Price history
One snapshot so far: the builder’s “onwards” prices seen on 17 Oct 2026. Each new check of the builder’s website adds a dated point here, so rises and offers show up with their dates.
| Seen on | Where | Prices |
|---|---|---|
| 17 Oct 2026 | Builder’s website Source (puravankara.com) (opens in a new tab) | 3 & 4 BHK from ₹9 Cr · 4 BHK from ₹5.5 Cr |
Summary in plain English
Purva Orient Grand is a residential project by Puravankara Limited in Bengaluru South with 97 homes in one 24-storey tower. It has 23 three-bedroom and 74 four-bedroom homes. The project is scheduled for completion on 30 June 2027.
Written by AI from the RERA record above on 5 Oct 2026. Every number in it was checked against that record; if anything differs, the record wins.
Open space, home loans, escrow and other details
- Open space
- 83.2% of land
- Water and power
- Not found in public records yet: water and power
- Home loans: approved banks
- Not found in public records yet: bank approvals
- Payment plans
- Not found in public records yet: payment plans
- Maintenance
- Not found in public records yet: maintenance
- Car parking
- Not found in public records yet: car parking charge
- Escrow bank (RERA)
- South Indian Bank Ltd., NEXT TO ST.JOSEPHS COLLEGE OF COMMERCE BRIGADE ROAD
- Project cost declared to RERA
- ₹228 Cr
Open area as a share of the land, from the areas filed with RERA (includes driveways and landscaped areas).
Amenities
Purva Orient Grand location and address
- Address
- Municipal No. 5, Lalbagh Road, Sudhamanagar, Ward No. 118, Bengaluru - 560027
- Village (RERA)
- Not found in public records yet: village
- City
- Bengaluru
- State
- Karnataka
- Coordinates
- Not found in public records yet: coordinates
Distances to landmarks
Not found in public records yet: landmarksAbout the locality
Not found in public records yet: locality factsPurva Orient Grand floor plans, brochure and elevations
Documents the builder uploaded to Karnataka RERA, shown as filed. Tap a page to see it full size; the full PDF opens on the RERA website.
Brochure

BrochureFiled 7 May 2022 · Full PDF on RERA
Floor plans5 pages

Floor Plans (POG)Filed 30 Jul 2021 · Full PDF on RERA
Approved building plan2 files

Project PlanFull PDF on RERA 
Building Plan (Purva Orient Grand).pdfFull PDF on RERA
| Home type | Carpet area | Homes |
|---|---|---|
| 3 BHK | 1,275 – 1,604 sq ft | 23 |
| 4 BHK | 1,318 – 2,303 sq ft | 74 |
Home types, counts and carpet areas as filed with Karnataka RERA (carpet area, not super built-up).
We have not collected floor-plan drawings; the builder’s sales team can share them.
Purva Orient Grand possession date and construction status
Promoter’s quarterly update to RERA for Q3 2025-26, submitted 2026-03-31.
Units sold and unsold, from RERA (Q3 2025-26)
| Type | Homes | Booked | Available |
|---|---|---|---|
| 3 BHK | 22 | 7 | 15 |
| 4 BHK | 75 | 4 | 71 |
As reported by the promoter in the quarterly update to RERA, not verified by us.
Timeline
- 30 Jun 2021Project start date given to RERA
- 7 Sep 2021Registered with Karnataka RERA
- 30 Jun 2027Completion date given at registration
Construction pace from RERA quarterly filings
At the average pace so far, construction would reach 100% around Apr 2030 — about 34 months after the completion date on RERA (30 Jun 2027).
- Filed on RERA
- Average pace since start
- RERA completion date
Quarterly filings
| Quarter | Filed on | Built | Homes booked |
|---|---|---|---|
| Q3 2025-26to 31 Dec 2025 | 31 Mar 2026 | 51% | 11 of 97 |
How we calculate
Average pace = % built ÷ months since the start date in the RERA record. Here: 51% ÷ 54 months (30 Jun 2021 to 31 Dec 2025) = 0.9% a month.
Estimated finish = latest filing date + (100 − % built) ÷ pace = 31 Dec 2025 + 49 ÷ 0.9 = 51.9 months → Apr 2030. This is an estimate, not a date from the builder or RERA.
A straight line is a simplification: the builder reports one overall %, which mixes excavation, structure and finishing, and work rarely moves at a constant speed. The % values are the promoter’s own figures filed with RERA, not checked by us. Promoter’s quarterly update to RERA for Q3 2025-26, submitted 2026-03-31.
Sources:Source (rera.karnataka.gov.in) (opens in a new tab)How we calculate this
Approvals and documents checklist
| Approval | Authority | Source |
|---|---|---|
| Building plan | BBMP - Bruhat Bengaluru Mahanagara Palike | Source (rera.karnataka.gov.in) (opens in a new tab) |
Documents uploaded to RERA
- Building or layout plan · Approved drawings from the planning authorityFiled on RERA ✓ — scanned copy uploaded; number and date not read yet
- Commencement certificate · Permission to start buildingNot on RERA yet
- Environment clearance · SEIAA KarnatakaNot on RERA yet
- Fire NOC · Karnataka Fire and Emergency ServicesNot on RERA yet
- Pollution board consent · KSPCBNot on RERA yet
- Water and sewerage · BWSSBNot on RERA yet
- Electricity · BESCOMNot on RERA yet
- Height clearance · Airports Authority of IndiaNot on RERA yet
- Occupancy certificate (OC) · Issued only when the building is finishedNot on RERA yet — expected at completion
From the documents the promoter uploaded to Karnataka RERA, collected 12 Oct 2026. “Filed” means a document is on RERA — we have not checked its contents or validity. Not every approval applies to every project (for example, smaller projects may not need an environment clearance). The project page on RERA lists each upload.
Purva Orient Grand RERA complaints
No complaints listed on Karnataka RERA for this registration as on Source (rera.karnataka.gov.in) (opens in a new tab)
Court and consumer cases
We list case numbers, courts and outcomes only — never names of private individuals.
About Puravankara Limited
- Promoter type
- Company
- Projects on this site
- 25
- RERA complaints against promoter
- 111
- Company number (CIN)
- L45200KA1986PLC051571
From Karnataka RERA, as collected so far (12 Oct 2026). Complaints are those RERA lists against this promoter across all its projects.
Puravankara Limited’s RERA recordPuravankara Limited delivery record
- 25Projects in Bengaluru on RERA36 approved registrations under Puravankara Limited in Bengaluru Urban and Rural. Source (rera.karnataka.gov.in) (opens in a new tab)
- 14,135Homes and plots registeredAs stated in each registrations.
- 111RERA complaints19 open, 92 disposed. as on Source (rera.karnataka.gov.in) (opens in a new tab)
- 7.9Complaints per 1,000 homes and plots111 complaints ÷ 14,135 homes and plots in its 36 registrations on Karnataka RERA in Bengaluru.
- 1Completion filed on RERARegistrations where the promoter applied to RERA for completion; 0 with an occupancy certificate on RERA.
- 0 of 1Filed by the date given at registrationMedian gap 7.4 months (on-time ones count as 0). The completion application can come after handover, so this is an upper bound on lateness.
What the complaints are about
111 complaint subjects as written on RERA, as on . Each subject is sorted into one group by keywords (first match wins: delay, refund, registration, quality, litigation, association); one complaint often raises several issues. Source (rera.karnataka.gov.in) (opens in a new tab)
Completion filed on RERA
| Project | Date at registration | Completion filed | Gap |
|---|---|---|---|
| Sound of Water Phase 1 by Puravankara | 31 Dec 2019 | 11 Aug 2020 | 7 months after |
Measured against the completion date given at registration; many projects had RERA extensions (including the COVID-period extension), shown under the date.
Sources:Source (rera.karnataka.gov.in) (opens in a new tab)How we calculate this
What’s changed since Jun 2021
- 17 Oct 2026Builder’s price list seen: 3 & 4 BHK from ₹9 Cr, 4 BHK from ₹5.5 Cr Source (puravankara.com) (opens in a new tab)
- 31 Mar 2026Quarterly update filed for Q3 2025-26: 51% built, 11 of 97 homes booked Source (rera.karnataka.gov.in) (opens in a new tab)
- 7 Sep 2021Registered with Karnataka RERA (PRM/KA/RERA/1251/310/PR/210907/004299); completion date 30 Jun 2027 Source (rera.karnataka.gov.in) (opens in a new tab)
- 30 Jun 2021Project start date in the RERA record Source (rera.karnataka.gov.in) (opens in a new tab)
Newest first. No extension of the completion date is recorded on RERA. When the RERA crawl sees a new filing, complaint or extension, it is added here with its date.
Home loan EMI calculator
- Monthly EMI
- ₹3,81,842
- Down payment
- ₹1,10,00,000
- Loan amount
- ₹4,40,00,000
- Total interest
- ₹4,76,42,133
A calculation only, from the numbers you enter — not a loan offer.
All-in cost: GST, registration and other charges
The calculator loads when you scroll to it.
Assumptions
- Base price: the builder’s published “onwards” price for the home type, where it publishes one (it usually says government charges, other charges and taxes are extra). You can change it.
- GST 5% on the base price and charges — the usual rate for an under-construction home that is not “affordable housing” (1%).
- Stamp duty about 5.6% and registration 2% — the Karnataka rule (registration was raised from 1% to 2% on 31 Aug 2025). Calculated on the agreement value.
- Car parking, other charges and the maintenance deposit are not in the public record we collect; enter them from the builder’s cost sheet.
- Loan on the agreement value (banks usually lend up to 75–90%); EMI is the standard reducing-balance formula. Example rate only — use your bank’s quote.
Sources:Source (puravankara.com) (opens in a new tab)How we calculate this
Purva Orient Grand FAQs
What is Purva Orient Grand?
Purva Orient Grand is a residential project by Puravankara Limited located in Bengaluru South with 97 homes in a single tower.
How many homes are in Purva Orient Grand?
The project has 97 homes: 23 three-bedroom units and 74 four-bedroom units.
What is the carpet area of homes in Purva Orient Grand?
Three-bedroom homes range from 1,275 to 1,604 sq ft carpet area, and four-bedroom homes range from 1,318 to 2,303 sq ft carpet area.
When will Purva Orient Grand be completed?
The RERA record shows a completion date of 30 June 2027.
What is the construction progress of Purva Orient Grand?
As of Q3 2025-26, construction is 51% complete with 11 homes booked out of 97.
What is the RERA registration number for Purva Orient Grand?
The RERA registration number is PRM/KA/RERA/1251/310/PR/210907/004299, registered on 7 September 2021.
Are there any RERA complaints on Purva Orient Grand?
There are no RERA complaints on this project.
What is the location and PIN code of Purva Orient Grand?
The project is located in Bengaluru South taluk, Bengaluru Urban district, with PIN code 560001.
What is Puravankara Limited's track record?
The builder has 23 projects in the RERA records for Bengaluru and 110 RERA complaints across all projects.
Which bank is the escrow bank for Purva Orient Grand?
South Indian Bank Ltd. is the escrow bank for this project.
Written by AI from the RERA record above on 5 Oct 2026. Answers use only that record; check them against the source before you decide.
Questions about Purva Orient Grand
No questions published yet. Ask the first one: you get an instant answer from this page’s public record, and our team follows up on anything the record does not show.
Bought a home from Puravankara Limited? Review the builder.
Reviews of Puravankara Limited by verified buyers
No verified reviews of Puravankara Limited yet. If you bought a home from them, your review helps other buyers.
How reviews work: only buyers and owners can review; we confirm each purchase by phone before publishing, publish positive and negative reviews alike, never accept payment for reviews, and the builder may reply.
Sources and last checked dates
Collected on 12 Oct 2026 by AI research agents reading public pages. Facts are written in our own words. Not found yet: price; court cases; landmarks; specifications; news.
How to check on RERA: On rera.karnataka.gov.in/viewAllProjects, type the registration number in 'Registration No', press Search, then click the 'View Project Details' icon. Complaints open from the 'Complaints / Litigation' icon in the same row. Registration number: PRM/KA/RERA/1251/310/PR/210907/004299.
- RERA record last checked: 12 Oct 2026
- Last change in the record (registration, quarterly filing or complaint): 17 Oct 2026
- Builder price list seen: 17 Oct 2026
How this page is made: software builds it from public records (Karnataka RERA filings, OpenStreetMap, the builder’s own website). AI is used only to read filings into fields and to write the plain-English summary and FAQ answers, which are checked against the record. Facts are checked automatically against the RERA filing. Methodology · How we earn · Report an error
More new projects nearby
Hosakerehalli, Rajarajeshwari NagarArtist’s impressionUnder constructionRERA registeredBuyers’ group openSobha Valley View - Heritage
by Sobha
Price: Price on requestGet brochure & price →
- 2 BHK, 3 BHK
- 917 – 1,267 sq ft
- Feb 2019
RERA not updated since promised Feb 2019 · 624 homes · 19 RERA complaints
Be one of the first 10 buyers in this groupFounding members — it’s free
Join group for Sobha Valley View - Heritage
Agara, HSR LayoutArtist’s impressionUnder constructionRERA registeredBuyers’ group openSterling Infinia
by Sterling
Price: Price on requestGet brochure & price →
- 1 BHK, 2 BHK, 3 BHK, 4 BHK
- 904 – 2,336 sq ft
- Sep 2026 (extended)
RERA not updated since promised Sep 2026 · 344 homes · 4 RERA complaints
Be one of the first 10 buyers in this groupFounding members — it’s free
Join group for Sterling Infinia
Kammanahalli, near Begur RoadUnder constructionRERA registeredBuyers’ group openSound of Water Phase 3
by Puravankara
Price: Price on requestGet brochure & price →
- 3 BHK, 4 BHK
- 1,787 – 2,749 sq ft
- Jun 2027
60 homes
Be one of the first 10 buyers in this groupFounding members — it’s free
Join group for Sound of Water Phase 3