Trivik Signature at a glance
- Possession (RERA)Dec 2031Karnataka RERA
- Construction21% built · on pace for Mar 2029RERA filing to 30 Sep 2026; estimate from average pace
- Homes booked18 of 408 (4%)RERA update · as on 30 Sep 2026
- RERA complaints (project)None listedKarnataka RERA · as on 19 Oct 2026
- Approvals filed8 of 9 on RERAKarnataka RERA uploads · 19 Oct 2026
- Nearest metroWhitefield (Kadugodi) · 2.89 kmstraight line · OpenStreetMap, 5 Oct 2026
- Airport driveapprox. 100 min at peak24.79 km straight line · estimate
- Nearest lakeKoralur Lake · 891 mFrom the RERA map point · OpenStreetMap, 5 Oct 2026
Project summary
Trivik Signature is a residential project by Trivik Signature in Koralur, Bengaluru with 408 homes, registered with Karnataka RERA. The completion date on RERA is 26 Dec 2031.
Facts collected on 19 Oct 2026 from public records — each linked to its source. Free for buyers. If you book through us, the builder pays us a commission.
Trivik Signature buyers’ group: join to ask for a group price
No one has joined yet. Be one of the first 10 buyers in this group — the founding members.
Join free. When enough buyers have joined, our agent partner asks Trivik Signature for a group price — for example a lower price, an easier payment plan or waived charges. Nothing is promised: you see what the builder offers and book directly with the builder if you want to. Free for buyers. If you book through us, the builder pays us a commission.
- Gathering buyers
- Talking to the builder
- Group offer
- Group site visit
- Booking
0 buyers have joined · 0 committed
Committed buyers have confirmed their budget, home type and timeline with us on a call; builders negotiate with them. Joining is free and never obliges you to buy.
Join the Trivik Signature buyers’ groupHow group buying works
See it for yourself
Visit the site with our team, or get a call to clear your questions. Free, no obligation.
Key facts: home types, towers, land and possession
- Home types
- 3 BHK
- Carpet area
- 986 – 1,990 sq ft
- Towers
- 3
- Floors
- 18
- Total homes
- 408
- Land
- 7.04 acres
- Possession (RERA)
- Dec 2031
- Built (RERA update)
- 21%
Trivik Signature RERA number and registration details
- RERA number
- PRM/KA/RERA/1250/304/PR/260226/008490
- Registered on
- 26 Feb 2026
- Promised completion
- 26 Dec 2031
- Extended to
- No extension recorded
- RERA status
- New launch
- Homes booked
- 18 of 408 as on
- Price
- Not found in public records yet: price
- Project type
- Residential
Towers and blocks (RERA filing)
| Tower | Floors | Basements | Homes |
|---|---|---|---|
| A Block | 18 | 1 | 136 |
| B Block | 18 | 1 | 136 |
| C Block | 18 | 1 | 136 |
A dash (—) means the filing did not state that value.
Summary in plain English
Trivik Signature is a residential project by Trivik Signature in Koralur, Hosakote, with 408 homes across 3 towers. The project has 24 duplexes and 384 three-bedroom homes. Completion is set for 26 December 2031.
Written by AI from the RERA record above on 19 Oct 2026. Every number in it was checked against that record; if anything differs, the record wins.
Open space, home loans, escrow and other details
- Open space
- 82.4% of land
- Water and power
- Water source filed with RERA: Local Authority
- Home loans: approved banks
- Not found in public records yet: bank approvals
- Payment plans
- Not found in public records yet: payment plans
- Maintenance
- Not found in public records yet: maintenance
- Car parking
- Not found in public records yet: car parking charge
- Escrow bank (RERA)
- ICICI Bank, Hoodi Circle
- Building plan (RERA)
- Satellite Town Ring Road Planning Authority · No. STRRPA/TP/CC/297/2025-26 · dated 17 Dec 2025
- Project cost declared to RERA
- ₹377 Cr
Open area as a share of the land, from the areas filed with RERA (includes driveways and landscaped areas).
Amenities
- Electricity
- CCTV Surveillance
- Club House
- Community Hall
- Outdoor Sports facility
- Indoor Sports facility
- Swimming Pool
- Gym
- Parks
- Power Backup
- Water and Sanitation
Amenities and internal works as filed by the promoter with Karnataka RERA; we have not visited the site.
Trivik Signature location and address
- Address
- E Khatha No. 150300402500200375, Sy no 94/1, 94/2, 94/4 and 95/1A1 of Koralur Village , Kasaba Hobli , Hosakote , Bengaluru Rural, Karnataka - 560067
- Village (RERA)
- Koralur
- Locality
- Near Kadugodi–Hope FarmAlso known as Kadugodi, Hope Farm
- PIN code
- 560067
- City
- Bengaluru
- State
- Karnataka
- Coordinates
- 12.99175, 77.78426
Distances to landmarks
Not found in public records yet: landmarksAbout Koralur
Not found in public records yet: locality factsCommute times to tech parks and the airport
| To | Straight line | Peak-hour drive (estimate) |
|---|---|---|
| ITPL, Whitefield (main gate)Map point on OpenStreetMap (opens in a new tab) | 5.06 km | approx. 20 min |
| Outer Ring Road tech corridor (RMZ Ecospace, Bellandur)Map point on OpenStreetMap (opens in a new tab) | 13.49 km | approx. 55 min |
| Manyata Tech ParkMap point on OpenStreetMap (opens in a new tab) | 18.88 km | approx. 76 min |
| Electronic City Phase 1Map point on OpenStreetMap (opens in a new tab) | 20.41 km | approx. 83 min |
| KSR Bengaluru City railway station (Majestic)Map point on OpenStreetMap (opens in a new tab) | 23.31 km | approx. 94 min |
| Kempegowda International AirportMap point on OpenStreetMap (opens in a new tab) | 24.79 km | approx. 100 min |
How we calculate
Straight line: from the project’s map point on RERA to the destination’s point on OpenStreetMap.
Peak-hour drive is a rough estimate, not a route: straight line × 1.35 for the road network, at 20 km/h. Real times vary a lot with the route and the hour.
Sources:Source (openstreetmap.org) (opens in a new tab)How we calculate this
Schools and hospitals nearby
Within 2 km
- 1Schools and colleges1 schools, 0 colleges, 0 kindergartens
- 1Hospitals and clinics0 hospitals, 1 clinics
Nearest schools and colleges
- Bangalore International Academy · 1.37 km
Nearest hospitals and clinics
- Soukya International Holistic Health Center · 1.45 km
Places as mapped on OpenStreetMap (amenity=school, college, kindergarten, university; hospital, clinic), counted within 2 km in a straight line of the RERA map point. Volunteers map these, so some places may be missing or closed. Places data © OpenStreetMap contributors, extract of 5 Oct 2026.
Nearest metro station and railway
- Whitefield (Kadugodi) (ವೈಟ್ಫೀಲ್ಡ್ (ಕಾಡುಗೋಡಿ))Open now — nearest operating metro station2.89 km
- Whitefield (ವೈಟ್ಫೀಲ್ಡ್)Nearest railway station2.53 km
Straight-line distances from the RERA map point to the station points mapped on OpenStreetMap; status (open or under construction) as tagged there. Places data © OpenStreetMap contributors, extract of 5 Oct 2026.
Lake and lake-buffer check
The nearest mapped lake is Koralur Lake, 891 m from the project’s RERA map point.
The site boundary is not published as a shape, so its nearest edge can be closer than this point. Whether any building sits inside a lake buffer can only be checked on the approved plan.
- Koralur Lake on OpenStreetMap (opens in a new tab) (ಕೊರಳೂರು ಕೆರೆ)891 m
- Unnamed lake (mapped on OpenStreetMap) on OpenStreetMap (opens in a new tab) 1,688 m
The buffer rule
Bengaluru’s lake buffer rule has changed over time: the National Green Tribunal ordered a 75 m buffer in May 2016; the Supreme Court set that order aside on 5 March 2019, leaving the 30 m buffer of the Revised Master Plan 2015. Check the current rule and the approved plan before relying on either number.
- LiveLaw: SC sets aside NGT order enlarging buffer zones (2019) (livelaw.in) (opens in a new tab)
- Citizen Matters: Shrinking lake buffers (citizenmatters.in) (opens in a new tab)
Shortest distance from the RERA map point to the mapped water edge (OpenStreetMap water polygons tagged lake or reservoir, or named lake/kere/tank). Mapped shorelines can differ from the revenue-record boundary of a lake. Places data © OpenStreetMap contributors, extract of 5 Oct 2026.
Sources:Source (openstreetmap.org) (opens in a new tab)Source (livelaw.in) (opens in a new tab)Source (citizenmatters.in) (opens in a new tab)How we calculate this
Satellite time-lapse of the site
Satellite photos load when you scroll to them.
Photos from Esri World Imagery Wayback, centred on the project’s map point; dates are the capture dates in Esri’s metadata. Loaded from Esri when you scroll here.
Sources:Source (livingatlas.arcgis.com) (opens in a new tab)
Trivik Signature home types and carpet areas
Documents the builder uploaded to Karnataka RERA, shown as filed. Tap a page to see it full size; the full PDF opens on the RERA website.
Approved building plan

Approved Building PlanFull PDF on RERA
Approved layout plan3 files

CDP Demarcation Koralru.pdfFull PDF on RERA 
Google Map Demarcation Koralur.pdfFull PDF on RERA 
Village map Demarcation Koralur.pdfFull PDF on RERA
Floor plans and brochure not published? The builder shares them only on request. We’ll get the brochure, floor plans and current price list for you, free.
Get brochure, floor plans & price| Home type | Carpet area | Homes |
|---|---|---|
| 3b + 3t | 986 – 1,110 sq ft | 384 |
| Duplex | 1,774 – 1,990 sq ft | 24 |
Home types, counts and carpet areas as filed with Karnataka RERA (carpet area, not super built-up).
We have not collected floor-plan drawings; the builder’s sales team can share them.
Trivik Signature possession date and construction status
Promoter’s quarterly update to RERA for Q2 2026-27, submitted 2026-10-15.
By tower (Q2 2026-27)
Units sold and unsold, from RERA (Q2 2026-27)
| Type | Homes | Booked | Available |
|---|---|---|---|
| 3B + 3T | 384 | 18 | 366 |
| DUPLEX | 24 | 0 | 24 |
As reported by the promoter in the quarterly update to RERA, not verified by us.
Timeline
- 1 Feb 2026Project start date given to RERA
- 26 Feb 2026Registered with Karnataka RERA
- 26 Dec 2031Completion date given at registration
Construction pace from RERA quarterly filings
At the average pace so far, construction would reach 100% around Mar 2029 — about 33 months before the completion date on RERA (26 Dec 2031).
At the pace between the 3 quarterly filings we have (8% → 21% in 6 months), it would be around Oct 2029 — about 26 months before the RERA date.
- Filed on RERA
- Average pace since start
- Pace between filings (and 0% assumed at the start date)
- RERA completion date
Quarterly filings
| Quarter | Filed on | Built | Homes booked |
|---|---|---|---|
| Q2 2026-27to 30 Sep 2026 | 15 Oct 2026 | 21% | 18 of 408 |
| Q1 2026-27to 30 Jun 2026 | 14 Jul 2026 | 13% | 13 of 408 |
| Q4 2025-26to 31 Mar 2026 | 15 Apr 2026 | 8% | 8 of 408 |
How we calculate
Average pace = % built ÷ months since the start date in the RERA record. Here: 21% ÷ 7.9 months (1 Feb 2026 to 30 Sep 2026) = 2.7% a month.
Estimated finish = latest filing date + (100 − % built) ÷ pace = 30 Sep 2026 + 79 ÷ 2.7 = 29.8 months → Mar 2029. This is an estimate, not a date from the builder or RERA.
Pace between filings = (21% − 8%) ÷ 6 months = 2.2% a month.
A straight line is a simplification: the builder reports one overall %, which mixes excavation, structure and finishing, and work rarely moves at a constant speed. The % values are the promoter’s own figures filed with RERA, not checked by us. Promoter’s quarterly update to RERA for Q2 2026-27, submitted 2026-10-15.
Sources:Source (rera.karnataka.gov.in) (opens in a new tab)How we calculate this
Approvals and documents checklist
| Approval | Authority | Source |
|---|---|---|
| Building plan | Satellite Town Ring Road Planning Authority · No. STRRPA/TP/CC/297/2025-26 · dated 2025-12-17 | Source (rera.karnataka.gov.in) (opens in a new tab) |
| Land conversion (5 orders) | DC Office, Bangalore Rural · No. 34065 and 4 more · dated 2024-12-17 | Source (rera.karnataka.gov.in) (opens in a new tab) |
| Commencement Certificate | scan uploaded to RERA | Source (rera.karnataka.gov.in) (opens in a new tab) |
| Approved Building Plan | scan uploaded to RERA | Source (rera.karnataka.gov.in) (opens in a new tab) |
| ESCOM/Electricity | scan uploaded to RERA | Source (rera.karnataka.gov.in) (opens in a new tab) |
| KWSSB/Water | scan uploaded to RERA | Source (rera.karnataka.gov.in) (opens in a new tab) |
| KSPCB | scan uploaded to RERA | Source (rera.karnataka.gov.in) (opens in a new tab) |
| SEIAA | scan uploaded to RERA | Source (rera.karnataka.gov.in) (opens in a new tab) |
| Fire Force Department | scan uploaded to RERA | Source (rera.karnataka.gov.in) (opens in a new tab) |
| Airport Authority of India | scan uploaded to RERA | Source (rera.karnataka.gov.in) (opens in a new tab) |
Documents uploaded to RERA
- Building or layout plan · Approved drawings from the planning authorityFiled on RERA ✓ — Satellite Town Ring Road Planning Authority · No. STRRPA/TP/CC/297/2025-26 · dated 17 Dec 2025
- Commencement certificate · Permission to start buildingFiled on RERA ✓ — scanned copy uploaded; number and date not read yet
- Environment clearance · SEIAA KarnatakaFiled on RERA ✓ — scanned copy uploaded; number and date not read yet
- Fire NOC · Karnataka Fire and Emergency ServicesFiled on RERA ✓ — scanned copy uploaded; number and date not read yet
- Pollution board consent · KSPCBFiled on RERA ✓ — scanned copy uploaded; number and date not read yet
- Water and sewerage · BWSSBFiled on RERA ✓ — scanned copy uploaded; number and date not read yet
- Electricity · BESCOMFiled on RERA ✓ — scanned copy uploaded; number and date not read yet
- Height clearance · Airports Authority of IndiaFiled on RERA ✓ — scanned copy uploaded; number and date not read yet
- Occupancy certificate (OC) · Issued only when the building is finishedNot on RERA yet — expected at completion
From the documents the promoter uploaded to Karnataka RERA, collected 19 Oct 2026. “Filed” means a document is on RERA — we have not checked its contents or validity. Not every approval applies to every project (for example, smaller projects may not need an environment clearance). The project page on RERA lists each upload.
Trivik Signature RERA complaints
No complaints listed on Karnataka RERA for this registration as on Source (rera.karnataka.gov.in) (opens in a new tab)
Court and consumer cases
We list case numbers, courts and outcomes only — never names of private individuals.
About Trivik Signature
- Promoter type
- Partnership Firm
- Projects on this site
- 1
- RERA complaints against promoter
- 0
- Company number (CIN)
- Not found in public records yet: CIN
From Karnataka RERA, as collected so far (19 Oct 2026). Complaints are those RERA lists against this promoter across all its projects.
Trivik Signature’s RERA recordTrivik Signature delivery record
- 1Projects in Bengaluru on RERA1 approved registration under Trivik Signature in Bengaluru Urban and Rural. Source (rera.karnataka.gov.in) (opens in a new tab)
- 408Homes registeredAs stated in each registrations.
- 0RERA complaintsas on Source (rera.karnataka.gov.in) (opens in a new tab)
- 0Complaints per 1,000 homes0 complaints ÷ 408 homes in its 1 registration on Karnataka RERA in Bengaluru.
Sources:Source (rera.karnataka.gov.in) (opens in a new tab)How we calculate this
What’s changed since Dec 2025
- 15 Oct 2026Quarterly update filed for Q2 2026-27: 21% built, 18 of 408 homes booked Source (rera.karnataka.gov.in) (opens in a new tab)
- 14 Jul 2026Quarterly update filed for Q1 2026-27: 13% built, 13 of 408 homes booked Source (rera.karnataka.gov.in) (opens in a new tab)
- 15 Apr 2026Quarterly update filed for Q4 2025-26: 8% built, 8 of 408 homes booked Source (rera.karnataka.gov.in) (opens in a new tab)
- 26 Feb 2026Registered with Karnataka RERA (PRM/KA/RERA/1250/304/PR/260226/008490); completion date 26 Dec 2031 Source (rera.karnataka.gov.in) (opens in a new tab)
- 1 Feb 2026Project start date in the RERA record Source (rera.karnataka.gov.in) (opens in a new tab)
- 17 Dec 2025Building plan approved by Satellite Town Ring Road Planning Authority (No. STRRPA/TP/CC/297/2025-26) Source (rera.karnataka.gov.in) (opens in a new tab)
Newest first. No extension of the completion date is recorded on RERA. When the RERA crawl sees a new filing, complaint or extension, it is added here with its date.
Home loan EMI calculator
- Monthly EMI
- —
- Down payment
- —
- Loan amount
- —
- Total interest
- —
A calculation only, from the numbers you enter — not a loan offer.
All-in cost: GST, registration and other charges
The calculator loads when you scroll to it.
Assumptions
- Base price: the builder’s price is not published in a form we could collect — enter it from the cost sheet.
- GST 5% on the base price and charges — the usual rate for an under-construction home that is not “affordable housing” (1%).
- Stamp duty about 5.6% and registration 2% — the Karnataka rule (registration was raised from 1% to 2% on 31 Aug 2025). Calculated on the agreement value.
- Car parking, other charges and the maintenance deposit are not in the public record we collect; enter them from the builder’s cost sheet.
- Loan on the agreement value (banks usually lend up to 75–90%); EMI is the standard reducing-balance formula. Example rate only — use your bank’s quote.
Trivik Signature FAQs
When will Trivik Signature be completed?
The project completion date on RERA is 26 December 2031.
How many homes are in Trivik Signature?
The project has 408 homes: 24 duplexes and 384 three-bedroom homes.
What is the carpet area in Trivik Signature?
Duplexes have carpet area from 1,774 to 1,990 sq ft. Three-bedroom homes have carpet area from 986 to 1,110 sq ft.
What is the RERA registration number for Trivik Signature?
The RERA registration number is PRM/KA/RERA/1250/304/PR/260226/008490.
How many towers are in Trivik Signature?
The project has 3 towers, each up to 18 floors.
What is the construction progress of Trivik Signature?
As of 30 September 2026, the project is 21% complete with 18 homes booked out of 408.
Where is Trivik Signature located?
The project is in Koralur, Hosakote taluk, Bengaluru Rural district, PIN code 560067.
Are there any RERA complaints on Trivik Signature?
There are no RERA complaints on this project or against the builder.
Which bank holds the escrow for Trivik Signature?
ICICI Bank holds the escrow account for the project.
How much land does Trivik Signature have?
The project land area is 28,505 sq m.
Written by AI from the RERA record above on 19 Oct 2026. Answers use only that record; check them against the source before you decide.
Questions about Trivik Signature
No questions published yet. Ask the first one: you get an instant answer from this page’s public record, and our team follows up on anything the record does not show.
Bought a home from Trivik Signature? Review the builder.
Reviews of Trivik Signature by verified buyers
No verified reviews of Trivik Signature yet. If you bought a home from them, your review helps other buyers.
How reviews work: only buyers and owners can review; we confirm each purchase by phone before publishing, publish positive and negative reviews alike, never accept payment for reviews, and the builder may reply.
Similar projects within 5 km
| Project | Distance | Homes | Possession (RERA) | Built | Complaints | Price |
|---|---|---|---|---|---|---|
| Riviera UnoNirvana Developers | 0.8 km | 137 | Jan 2030 | 65% | 0 | Not collected |
| Kumari NautilusKumari Infra Homes Private Limited | 0.8 km | 165 | Jan 2028 | 90% | 0 | Not collected |
| Isha HilifeIsha Corp | 1.1 km | 195 | Dec 2026 | 95% | 0 | Not collected |
| United Green WoodsUnited Green Woods | 1.3 km | 282 | Mar 2028 | 65% | 0 | Not collected |
| Sowparnika Rhythm of RainSowparnika Homes Private Limited | 1.3 km | 725 | Jan 2032 | 36% | 0 | Not collected |
| Emmay Environs PrideEmmay environs | 1.3 km | 77 | Mar 2024extended | — | 0 | Not collected |
Projects of the same kind within 5 km in a straight line of this project’s RERA map point, nearest first. % built is the promoter’s latest quarterly figure on RERA (shown for single-registration projects); prices are from the builder’s own website where we found one.
Sources and last checked dates
Collected on 19 Oct 2026 by AI research agents reading public pages. Facts are written in our own words. Not found yet: price; court cases; landmarks; specifications; news.
How to check on RERA: On rera.karnataka.gov.in/viewAllProjects, type the registration number in 'Registration No', press Search, then click the 'View Project Details' icon. Complaints open from the 'Complaints / Litigation' icon in the same row. Registration number: PRM/KA/RERA/1250/304/PR/260226/008490.
- RERA record last checked: 19 Oct 2026
- Last change in the record (registration, quarterly filing or complaint): 19 Oct 2026
How this page is made: software builds it from public records (Karnataka RERA filings, OpenStreetMap, the builder’s own website). AI is used only to read filings into fields and to write the plain-English summary and FAQ answers, which are checked against the record. Facts are checked automatically against the RERA filing. Methodology · How we earn · Report an error
More new projects nearby
Koraluru, near Kadugodi–Hope FarmUnder constructionRERA registeredBuyers’ group openRiviera Uno
by Nirvana
Price: Price on requestGet brochure & price →
- 4 BHK
- 2,499 – 2,524 sq ft
- Jan 2030
137 homes
Be one of the first 10 buyers in this groupFounding members — it’s free
Join group for Riviera Uno
Mallasandra, Kanakapura RoadUnder constructionRERA registeredBuyers’ group openKumari Nautilus
by Kumari Infra Homes
Price: Price on requestGet brochure & price →
- Villa
- 1,617 – 2,255 sq ft
- Jan 2028
165 homes
Be one of the first 10 buyers in this groupFounding members — it’s free
Join group for Kumari Nautilus
Thirumalashettihalli, near Kadugodi–Hope FarmUnder constructionRERA registeredBuyers’ group openIsha Hilife
by Isha Corp
Price: Price on requestGet brochure & price →
- Studio, 1 BHK, 2 BHK, 3 BHK
- 528 – 3,459 sq ft
- Dec 2026
195 homes
Be one of the first 10 buyers in this groupFounding members — it’s free
Join group for Isha Hilife