Bhartiya Garden Estate: Q4 2025-26 RERA construction filings show progress

Bhartiya Urban Private Limited filed the Q4 2025-26 quarterly update for Bhartiya Garden Estate with Karnataka RERA on 20 Apr 2026. • Phase-1 — PRM/KA/RERA/1251/472/PR/260825/008038: 11% complete (was 3% last quarter) • Phase-2 — PRM/KA/RERA/1251/309/PR/060925/008064: 5% complete (was 3% last quarter) • Phase-3 — PRM/KA/RERA/1251/309/PR/060925/008065: 4% complete (was 3% last quarter) Percentages are as reported by the builder to RERA.

RERA check Bhartiya Garden Estate on Karnataka RERA today

Promised at registration
Aug 2031
RERA date now
Aug 2031
Built (latest filing)
7%

Source: Karnataka RERA, via the Bhartiya Garden Estate RERA record.