arsis green hills
2 & 3 BHK apartments by Arsis Developers Pvt Ltd · Old Madras Road, Bengaluru
Old Madras Road, BengaluruOpen on Google Maps (opens in a new tab)
- Under construction
- RERA registered
- residential
Price: Price on request
Site photo filed with Karnataka RERA Karnataka RERA filing · Source ↗ (opens in a new tab)
arsis green hills at a glance
- Possession (RERA)Oct 2028 ExtendedWas Dec 2022 · Karnataka RERA
- Construction63% built · on pace for Jun 2031 32 mo after RERA dateRERA filing to 30 Jun 2026; estimate from average pace
- Homes booked409 of 596 (69%)RERA update · as on 30 Jun 2026
- RERA complaints (project)18 complaintsKarnataka RERA · as on 14 Oct 2026
- Approvals filed1 of 9 on RERAKarnataka RERA uploads · 14 Oct 2026
- Nearest metroGarudacharpalya · 2.99 kmstraight line · OpenStreetMap, 5 Oct 2026
- Airport driveapprox. 81 min at peak20.08 km straight line · estimate
- Nearest lakeVengayyana Lake · 447 mFrom the RERA map point · OpenStreetMap, 5 Oct 2026
Project summary
arsis green hills is a residential project by Arsis Developers Pvt Ltd in Bengaluru with 596 homes, registered with Karnataka RERA. The completion date on RERA is 31 Oct 2028.
Not in the RERA record we collected yet: locality. This page fills in as the record is collected.
Facts collected on 14 Oct 2026 from public records — each linked to its source. Free for buyers. If you book through us, the builder pays us a commission.
arsis green hills buyers’ group: join to ask for a group price
No one has joined yet. Be one of the first 10 buyers in this group — the founding members.
Join free. When enough buyers have joined, our agent partner asks Arsis Developers Pvt Ltd for a group price — for example a lower price, an easier payment plan or waived charges. Nothing is promised: you see what the builder offers and book directly with the builder if you want to. Free for buyers. If you book through us, the builder pays us a commission.
- Gathering buyers
- Talking to the builder
- Group offer
- Group site visit
- Booking
0 buyers have joined · 0 committed
Committed buyers have confirmed their budget, home type and timeline with us on a call; builders negotiate with them. Joining is free and never obliges you to buy.
Join the arsis green hills buyers’ groupHow group buying works
See it for yourself
Visit the site with our team, or get a call to clear your questions. Free, no obligation.
Key facts: home types, towers, land and possession
- Home types
- 2 BHK, 2.5 BHK, 3 BHK
- Carpet area
- 850 – 1,142 sq ft
- Towers
- 3
- Floors
- 31
- Total homes
- 596
- Land
- 4.34 acres
- Possession (extended)
- Oct 2028
- Built (RERA update)
- 63%
arsis green hills RERA number and registration details
- RERA number
- PRM/KA/RERA/1251/446/PR/180130/002413
- Registered on
- 30 Jan 2018
- Promised completion
- 31 Dec 2022
- Extended to
- 31 Oct 2028
- RERA status
- New launch
- Homes booked
- 409 of 596 as on
- Price
- Not found in public records yet: price
- Project type
- Residential
Towers and blocks (RERA filing)
| Tower | Floors | Basements | Homes |
|---|---|---|---|
| MOUNT DALE | 31 | 2 | 178 |
| MOUNT VALLEY | 31 | 2 | 178 |
| MOUNT SUMMIT | 14 | 2 | 82 |
A dash (—) means the filing did not state that value.
Summary in plain English
Arsis Green Hills is a residential project by Arsis Developers Pvt Ltd in Bengaluru East with 596 homes across 3 towers. The project includes 2, 2.5 and 3 BHK flats with completion scheduled for 31 October 2028 according to the RERA record.
Written by AI from the RERA record above on 5 Oct 2026. Every number in it was checked against that record; if anything differs, the record wins.
Open space, home loans, escrow and other details
- Open space
- 95.4% of land
- Water and power
- Not found in public records yet: water and power
- Home loans: approved banks
- Not found in public records yet: bank approvals
- Payment plans
- Not found in public records yet: payment plans
- Maintenance
- Not found in public records yet: maintenance
- Car parking
- Not found in public records yet: car parking charge
- Escrow bank (RERA)
- HDFC, BHATTARAHALLI
- Project cost declared to RERA
- ₹98.73 Cr
Open area as a share of the land, from the areas filed with RERA (includes driveways and landscaped areas).
Amenities
arsis green hills location and address
- Address
- Sy. No. 52/2B, Beside Purvi Greens Hotel, , Old Madras Road, Bhattarahalli, Virgo Nagar Post,
- Village (RERA)
- Not found in public records yet: village
- Locality
- Old Madras RoadAlso known as OMR, Old Madras Road
- PIN code
- 560020
- City
- Bengaluru
- State
- Karnataka
- Coordinates
- 13.02018, 77.70646
Distances to landmarks
Not found in public records yet: landmarksAbout Old Madras Road
Not found in public records yet: locality factsCommute times to tech parks and the airport
| To | Straight line | Peak-hour drive (estimate) |
|---|---|---|
| ITPL, Whitefield (main gate)Map point on OpenStreetMap (opens in a new tab) | 4.96 km | approx. 20 min |
| Manyata Tech ParkMap point on OpenStreetMap (opens in a new tab) | 9.88 km | approx. 40 min |
| Outer Ring Road tech corridor (RMZ Ecospace, Bellandur)Map point on OpenStreetMap (opens in a new tab) | 11.07 km | approx. 45 min |
| KSR Bengaluru City railway station (Majestic)Map point on OpenStreetMap (opens in a new tab) | 15.55 km | approx. 63 min |
| Electronic City Phase 1Map point on OpenStreetMap (opens in a new tab) | 19.48 km | approx. 79 min |
| Kempegowda International AirportMap point on OpenStreetMap (opens in a new tab) | 20.08 km | approx. 81 min |
How we calculate
Straight line: from the project’s map point on RERA to the destination’s point on OpenStreetMap.
Peak-hour drive is a rough estimate, not a route: straight line × 1.35 for the road network, at 20 km/h. Real times vary a lot with the route and the hour.
Sources:Source (openstreetmap.org) (opens in a new tab)How we calculate this
Schools and hospitals nearby
Within 2 km
- 39Schools and colleges23 schools, 15 colleges, 1 kindergartens
- 51Hospitals and clinics21 hospitals, 30 clinics
Nearest schools and colleges
- Indus Valley School · 0.12 km
- Visvadeep: Institute of Youth Ministry and Faith Education · 0.24 km
- Kristu Jyoti College · 0.42 km
Nearest hospitals and clinics
- Swiss Medic Health Care · 0.46 km
- Shanthinilaya Hospital · 0.53 km
- Thyrocare · 0.59 km
Places as mapped on OpenStreetMap (amenity=school, college, kindergarten, university; hospital, clinic), counted within 2 km in a straight line of the RERA map point. Volunteers map these, so some places may be missing or closed. Places data © OpenStreetMap contributors, extract of 5 Oct 2026.
Nearest metro station and railway
- Garudacharpalya (ಗರುಡಾಚಾರ್ ಪಾಳ್ಯ)Open now — nearest operating metro station2.99 km
- Hoodi Nearest railway station3.03 km
Straight-line distances from the RERA map point to the station points mapped on OpenStreetMap; status (open or under construction) as tagged there. Places data © OpenStreetMap contributors, extract of 5 Oct 2026.
Lake and lake-buffer check
The nearest mapped lake is Vengayyana Lake, 447 m from the project’s RERA map point.
The site boundary is not published as a shape, so its nearest edge can be closer than this point. Whether any building sits inside a lake buffer can only be checked on the approved plan.
- Vengayyana Lake on OpenStreetMap (opens in a new tab) (ವೆಂಗಯ್ಯನ ಕೆರೆ)447 m
- Bhattarahalli Lake on OpenStreetMap (opens in a new tab) 461 m
- Seegehalli Lake on OpenStreetMap (opens in a new tab) (ಸೀಗೆಹಳ್ಳಿ ಕೆರೆ)649 m
The buffer rule
Bengaluru’s lake buffer rule has changed over time: the National Green Tribunal ordered a 75 m buffer in May 2016; the Supreme Court set that order aside on 5 March 2019, leaving the 30 m buffer of the Revised Master Plan 2015. Check the current rule and the approved plan before relying on either number.
- LiveLaw: SC sets aside NGT order enlarging buffer zones (2019) (livelaw.in) (opens in a new tab)
- Citizen Matters: Shrinking lake buffers (citizenmatters.in) (opens in a new tab)
Shortest distance from the RERA map point to the mapped water edge (OpenStreetMap water polygons tagged lake or reservoir, or named lake/kere/tank). Mapped shorelines can differ from the revenue-record boundary of a lake. Places data © OpenStreetMap contributors, extract of 5 Oct 2026.
Sources:Source (openstreetmap.org) (opens in a new tab)Source (livelaw.in) (opens in a new tab)Source (citizenmatters.in) (opens in a new tab)How we calculate this
Satellite time-lapse of the site
Satellite photos load when you scroll to them.
Photos from Esri World Imagery Wayback, centred on the project’s map point; dates are the capture dates in Esri’s metadata. Loaded from Esri when you scroll here.
Sources:Source (livingatlas.arcgis.com) (opens in a new tab)
arsis green hills home types and carpet areas
Floor plans and brochure not published? The builder shares them only on request. We’ll get the brochure, floor plans and current price list for you, free.
Get brochure, floor plans & price| Home type | Carpet area | Homes |
|---|---|---|
| 2 , 2.5 &3 BHK flats | 915 sq ft | 158 |
| 2 BHK | 850 – 865 sq ft | 266 |
| 2.5 BHK | 865 sq ft | 30 |
| 3 BHK | 1,106 – 1,142 sq ft | 142 |
Home types, counts and carpet areas as filed with Karnataka RERA (carpet area, not super built-up).
We have not collected floor-plan drawings; the builder’s sales team can share them.
arsis green hills possession date and construction status
Promoter’s quarterly update to RERA for Q1 2026-27, submitted 2026-07-15.
By tower (Q1 2026-27)
Units sold and unsold, from RERA (Q1 2026-27)
| Type | Homes | Booked | Available |
|---|---|---|---|
| 2 BHK | 266 | 254 | 12 |
| 2.5 BHK | 30 | 27 | 3 |
| 3 BHK | 142 | 128 | 14 |
As reported by the promoter in the quarterly update to RERA, not verified by us.
Timeline
- 1 Jan 2018Project start date given to RERA
- 30 Jan 2018Registered with Karnataka RERA
- 31 Dec 2022Completion date given at registration
- 30 Sep 2023Covid Extension: completion date moved to this date
- 30 Sep 2024Section 6 Extension: completion date moved to this date
- 31 Oct 2028Further Extension: completion date moved to this date
Construction pace from RERA quarterly filings
At the average pace so far, construction would reach 100% around Jun 2031 — about 32 months after the completion date on RERA (31 Oct 2028).
- Filed on RERA
- Average pace since start
- RERA completion date
Quarterly filings
| Quarter | Filed on | Built | Homes booked |
|---|---|---|---|
| Q1 2026-27to 30 Jun 2026 | 15 Jul 2026 | 63% | 409 of 438 |
| Q4 2025-26to 31 Mar 2026 | 15 Apr 2026 | 63% | 406 of 438 |
| Q3 2025-26to 31 Dec 2025 | 18 Feb 2026 | 62% | 400 of 438 |
How we calculate
Average pace = % built ÷ months since the start date in the RERA record. Here: 63% ÷ 101.9 months (1 Jan 2018 to 30 Jun 2026) = 0.6% a month.
Estimated finish = latest filing date + (100 − % built) ÷ pace = 30 Jun 2026 + 37 ÷ 0.6 = 59.8 months → Jun 2031. This is an estimate, not a date from the builder or RERA.
Pace between filings = (63% − 62%) ÷ 5.9 months = 0.2% a month.
A straight line is a simplification: the builder reports one overall %, which mixes excavation, structure and finishing, and work rarely moves at a constant speed. The % values are the promoter’s own figures filed with RERA, not checked by us. Promoter’s quarterly update to RERA for Q1 2026-27, submitted 2026-07-15.
Sources:Source (rera.karnataka.gov.in) (opens in a new tab)How we calculate this
Approvals and documents checklist
| Approval | Authority | Source |
|---|---|---|
| Building plan | BBMP - Bruhat Bengaluru Mahanagara Palike | Source (rera.karnataka.gov.in) (opens in a new tab) |
Documents uploaded to RERA
- Building or layout plan · Approved drawings from the planning authorityFiled on RERA ✓ — scanned copy uploaded; number and date not read yet
- Commencement certificate · Permission to start buildingNot on RERA yet
- Environment clearance · SEIAA KarnatakaNot on RERA yet
- Fire NOC · Karnataka Fire and Emergency ServicesNot on RERA yet
- Pollution board consent · KSPCBNot on RERA yet
- Water and sewerage · BWSSBNot on RERA yet
- Electricity · BESCOMNot on RERA yet
- Height clearance · Airports Authority of IndiaNot on RERA yet
- Occupancy certificate (OC) · Issued only when the building is finishedNot on RERA yet — expected at completion
From the documents the promoter uploaded to Karnataka RERA, collected 14 Oct 2026. “Filed” means a document is on RERA — we have not checked its contents or validity. Not every approval applies to every project (for example, smaller projects may not need an environment clearance). The project page on RERA lists each upload.
arsis green hills RERA complaints and orders
18 complaints as on Source (rera.karnataka.gov.in) (opens in a new tab)
18 rows: rera complaints. Scroll inside the table to see them all.
| Complaint ref | Filed | Subject | Status | Source |
|---|---|---|---|---|
| 01866/2023 | 26 Dec 2023 | Breach of project delivery timelines and no fair commitment | Disposed | Source (rera.karnataka.gov.in) (opens in a new tab) |
| 01676/2023 | 8 Nov 2023 | Delay of project completion and handover | Disposed | Source (rera.karnataka.gov.in) (opens in a new tab) |
| 01667/2023 | 6 Nov 2023 | Delay in Flat Delivery | Disposed ao | Source (rera.karnataka.gov.in) (opens in a new tab) |
| 01608/2023 | 19 Oct 2023 | Delay in Flat delivery | Disposed | Source (rera.karnataka.gov.in) (opens in a new tab) |
| 01609/2023 | 19 Oct 2023 | Breach of Sale agreement | Disposed | Source (rera.karnataka.gov.in) (opens in a new tab) |
| 01606/2023 | 18 Oct 2023 | Flat handover not happening, sale agreement is not honoured as rent is not paid even after grace period. | Disposed ao | Source (rera.karnataka.gov.in) (opens in a new tab) |
| 01592/2023 | 16 Oct 2023 | Project delayed more than a year and Rental amount is not being paid | Disposed | Source (rera.karnataka.gov.in) (opens in a new tab) |
| 01576/2023 | 11 Oct 2023 | Delay in Apartment Handover | Disposed | Source (rera.karnataka.gov.in) (opens in a new tab) |
| 01539/2023 | 6 Oct 2023 | Breach of Sale Deed Agreement, No proper update on timelines of pocession of apartment | Disposed | Source (rera.karnataka.gov.in) (opens in a new tab) |
| 01470/2023 | 21 Sep 2023 | B. Jayaprasad and P. Anupama purchaser request you take necessary action on builder to compensate the rent of Rs. 30,000 as agreed in the sale agreement from June 2022, breach in agareement | Disposed ao | Source (rera.karnataka.gov.in) (opens in a new tab) |
| 01471/2023 | 21 Sep 2023 | Request to re-assign project to another builder | Disposed | Source (rera.karnataka.gov.in) (opens in a new tab) |
| 01316/2023 | 1 Sep 2023 | As per Agreement Handover date for my flat was Dec 2021. I have still not got possession of my flat | Disposed ao | Source (rera.karnataka.gov.in) (opens in a new tab) |
| 01197/2023 | 27 Jul 2023 | Project delayed too much, no possession yet, Need Rent as per agreeemnt | Disposed ao | Source (rera.karnataka.gov.in) (opens in a new tab) |
| 00887/2023 | 5 Jun 2023 | Delayed delivery for Mount Dale Wing for which date already passed (DEC-2021+ 6 months grace period) | Disposed | Source (rera.karnataka.gov.in) (opens in a new tab) |
| 00869/2023 | 1 Jun 2023 | Handover of Project getting delayed and no updates from Builder | Disposed | Source (rera.karnataka.gov.in) (opens in a new tab) |
| 00857/2023 | 31 May 2023 | Indefinite delay and non-adherence to agreement terms | Disposed | Source (rera.karnataka.gov.in) (opens in a new tab) |
| 00841/2023 | 30 May 2023 | Project Delayed and Non-Compliance with Rent Payment Clause as per Sale Agreement | Disposed | Source (rera.karnataka.gov.in) (opens in a new tab) |
| 00837/2023 | 29 May 2023 | Project delayed more than a year and Rental amount is not being paid. | Disposed ao | Source (rera.karnataka.gov.in) (opens in a new tab) |
Court and consumer cases
We list case numbers, courts and outcomes only — never names of private individuals.
About Arsis Developers Pvt Ltd
- Promoter type
- Company
- Projects on this site
- 1
- RERA complaints against promoter
- 18
- Company number (CIN)
- U70100KA2014PTC075088
From Karnataka RERA, as collected so far (14 Oct 2026). Complaints are those RERA lists against this promoter across all its projects.
Arsis Developers Pvt Ltd’s RERA recordArsis Developers Pvt Ltd delivery record
- 1Projects in Bengaluru on RERA1 approved registration under Arsis Developers Pvt Ltd in Bengaluru Urban and Rural. Source (rera.karnataka.gov.in) (opens in a new tab)
- 596Homes registeredAs stated in each registrations.
- 18RERA complaints0 open, 18 disposed. as on Source (rera.karnataka.gov.in) (opens in a new tab)
- 30.2Complaints per 1,000 homes18 complaints ÷ 596 homes in its 1 registration on Karnataka RERA in Bengaluru.
What the complaints are about
18 complaint subjects as written on RERA, as on . Each subject is sorted into one group by keywords (first match wins: delay, refund, registration, quality, litigation, association); one complaint often raises several issues. Source (rera.karnataka.gov.in) (opens in a new tab)
Sources:Source (rera.karnataka.gov.in) (opens in a new tab)How we calculate this
What’s changed since Jan 2018
- 31 Oct 2028Completion date extended to 31 Oct 2028 Source (rera.karnataka.gov.in) (opens in a new tab)
- 15 Jul 2026Quarterly update filed for Q1 2026-27: 63% built, 409 of 438 homes booked Source (rera.karnataka.gov.in) (opens in a new tab)
- 15 Apr 2026Quarterly update filed for Q4 2025-26: 63% built, 406 of 438 homes booked Source (rera.karnataka.gov.in) (opens in a new tab)
- 18 Feb 2026Quarterly update filed for Q3 2025-26: 62% built, 400 of 438 homes booked Source (rera.karnataka.gov.in) (opens in a new tab)
- 26 Dec 2023Complaint 01866/2023 filed with RERA: “Breach of project delivery timelines and no fair commitment” — now disposed Source (rera.karnataka.gov.in) (opens in a new tab)
- 8 Nov 2023Complaint 01676/2023 filed with RERA: “Delay of project completion and handover” — now disposed Source (rera.karnataka.gov.in) (opens in a new tab)
- 6 Nov 2023Complaint 01667/2023 filed with RERA: “Delay in Flat Delivery” — now disposed Source (rera.karnataka.gov.in) (opens in a new tab)
- 19 Oct 2023Complaint 01608/2023 filed with RERA: “Delay in Flat delivery” — now disposed Source (rera.karnataka.gov.in) (opens in a new tab)
- 19 Oct 2023Complaint 01609/2023 filed with RERA: “Breach of Sale agreement” — now disposed Source (rera.karnataka.gov.in) (opens in a new tab)
- 18 Oct 2023Complaint 01606/2023 filed with RERA: “Flat handover not happening, sale agreement is not honoured as rent is not paid even after grace period.” — now disposed Source (rera.karnataka.gov.in) (opens in a new tab)
- 16 Oct 2023Complaint 01592/2023 filed with RERA: “Project delayed more than a year and Rental amount is not being paid” — now disposed Source (rera.karnataka.gov.in) (opens in a new tab)
- 11 Oct 2023Complaint 01576/2023 filed with RERA: “Delay in Apartment Handover” — now disposed Source (rera.karnataka.gov.in) (opens in a new tab)
- 6 Oct 2023Complaint 01539/2023 filed with RERA: “Breach of Sale Deed Agreement, No proper update on timelines of pocession of apartment” — now disposed Source (rera.karnataka.gov.in) (opens in a new tab)
- 21 Sep 2023Complaint 01470/2023 filed with RERA: “B. Jayaprasad and P. Anupama purchaser request you take necessary action on builder to compensate the rent of Rs. 30,000 as agreed in the sale agreement from June 2022, breach in agareement” — now disposed Source (rera.karnataka.gov.in) (opens in a new tab)
- 21 Sep 2023Complaint 01471/2023 filed with RERA: “Request to re-assign project to another builder” — now disposed Source (rera.karnataka.gov.in) (opens in a new tab)
- 1 Sep 2023Complaint 01316/2023 filed with RERA: “As per Agreement Handover date for my flat was Dec 2021. I have still not got possession of my flat” — now disposed Source (rera.karnataka.gov.in) (opens in a new tab)
- 27 Jul 2023Complaint 01197/2023 filed with RERA: “Project delayed too much, no possession yet, Need Rent as per agreeemnt” — now disposed Source (rera.karnataka.gov.in) (opens in a new tab)
- 5 Jun 2023Complaint 00887/2023 filed with RERA: “Delayed delivery for Mount Dale Wing for which date already passed (DEC-2021+ 6 months grace period)” — now disposed Source (rera.karnataka.gov.in) (opens in a new tab)
- 1 Jun 2023Complaint 00869/2023 filed with RERA: “Handover of Project getting delayed and no updates from Builder” — now disposed Source (rera.karnataka.gov.in) (opens in a new tab)
- 31 May 2023Complaint 00857/2023 filed with RERA: “Indefinite delay and non-adherence to agreement terms” — now disposed Source (rera.karnataka.gov.in) (opens in a new tab)
- 30 May 2023Complaint 00841/2023 filed with RERA: “Project Delayed and Non-Compliance with Rent Payment Clause as per Sale Agreement” — now disposed Source (rera.karnataka.gov.in) (opens in a new tab)
- 29 May 2023Complaint 00837/2023 filed with RERA: “Project delayed more than a year and Rental amount is not being paid.” — now disposed Source (rera.karnataka.gov.in) (opens in a new tab)
- 30 Jan 2018Registered with Karnataka RERA (PRM/KA/RERA/1251/446/PR/180130/002413); completion date 31 Dec 2022 Source (rera.karnataka.gov.in) (opens in a new tab)
- 1 Jan 2018Project start date in the RERA record Source (rera.karnataka.gov.in) (opens in a new tab)
Newest first. When the RERA crawl sees a new filing, complaint or extension, it is added here with its date.
Home loan EMI calculator
- Monthly EMI
- —
- Down payment
- —
- Loan amount
- —
- Total interest
- —
A calculation only, from the numbers you enter — not a loan offer.
All-in cost: GST, registration and other charges
The calculator loads when you scroll to it.
Assumptions
- Base price: the builder’s price is not published in a form we could collect — enter it from the cost sheet.
- GST 5% on the base price and charges — the usual rate for an under-construction home that is not “affordable housing” (1%).
- Stamp duty about 5.6% and registration 2% — the Karnataka rule (registration was raised from 1% to 2% on 31 Aug 2025). Calculated on the agreement value.
- Car parking, other charges and the maintenance deposit are not in the public record we collect; enter them from the builder’s cost sheet.
- Loan on the agreement value (banks usually lend up to 75–90%); EMI is the standard reducing-balance formula. Example rate only — use your bank’s quote.
arsis green hills FAQs
What is the RERA registration number for Arsis Green Hills?
The project is registered under RERA registration number PRM/KA/RERA/1251/446/PR/180130/002413.
When is Arsis Green Hills expected to be completed?
The completion date on the current RERA record is 31 October 2028. The project was originally registered with a completion date of 31 December 2022.
How many homes are in Arsis Green Hills?
The project has 596 homes across 3 towers with a maximum of 31 floors.
What home types are available in Arsis Green Hills?
The project offers 2 BHK (266 homes, 850–865 sq ft carpet area), 2.5 BHK (30 homes, 865 sq ft carpet area), 3 BHK (142 homes, 1,106–1,142 sq ft carpet area) and 2, 2.5 and 3 BHK flats (158 homes, 915 sq ft carpet area).
What is the construction progress of Arsis Green Hills?
As of the quarter ended 30 June 2026, the project was 63% complete with 409 homes booked and 438 homes in the booking table.
Where is Arsis Green Hills located?
The project is located in Bengaluru East taluk, Bengaluru Urban district, PIN code 560020.
How many RERA complaints have been filed against Arsis Green Hills?
18 RERA complaints have been filed on this project registration.
What extensions have been granted for Arsis Green Hills?
The project has received three extensions: a Covid Extension to 30 September 2023, a Section 6 Extension to 30 September 2024, and a Further Extension to 31 October 2028.
How many RERA complaints are on record against Arsis Developers Pvt Ltd?
18 RERA complaints are recorded against the builder across all projects.
What is the land area of Arsis Green Hills?
The project land area is 17,582 sq m.
Written by AI from the RERA record above on 5 Oct 2026. Answers use only that record; check them against the source before you decide.
Questions about arsis green hills
No questions published yet. Ask the first one: you get an instant answer from this page’s public record, and our team follows up on anything the record does not show.
Bought a home from Arsis Developers Pvt Ltd? Review the builder.
Reviews of Arsis Developers Pvt Ltd by verified buyers
No verified reviews of Arsis Developers Pvt Ltd yet. If you bought a home from them, your review helps other buyers.
How reviews work: only buyers and owners can review; we confirm each purchase by phone before publishing, publish positive and negative reviews alike, never accept payment for reviews, and the builder may reply.
Similar projects within 5 km
| Project | Distance | Homes | Possession (RERA) | Built | Complaints | Price |
|---|---|---|---|---|---|---|
| Casagrand MeridianCasa Grande Garden City Builders Pvt Ltd | 0.5 km | 215 | Nov 2026extended | 100% | 13 | Not collected |
| Pride EuphoraPride Housing | 0.6 km | 212 | Sep 2027 | 65% | 0 | Not collected |
| OhanaA One Shelters Private Limited | 0.9 km | 336 | Jun 2030extended | — | 0 | Not collected |
| Brigade LakecrestBrigade Enterprises Ltd | 1.1 km | 604 | Mar 2030 | 20% | 0 | from ₹1.6 Crabout ₹16,800/sq ft carpet |
| Sree Adithya Lotus ParkSree Adithya Developers | 1.3 km | 141 | Sep 2026 | 98% | 0 | Not collected |
| Galaxy OneGalaxy Developers | 1.4 km | 212 | Dec 2025 | — | 0 | Not collected |
Projects of the same kind within 5 km in a straight line of this project’s RERA map point, nearest first. % built is the promoter’s latest quarterly figure on RERA (shown for single-registration projects); prices are from the builder’s own website where we found one.
Sources and last checked dates
Collected on 14 Oct 2026 by AI research agents reading public pages. Facts are written in our own words. Not found yet: price; court cases; landmarks; specifications; news.
How to check on RERA: On rera.karnataka.gov.in/viewAllProjects, type the registration number in 'Registration No', press Search, then click the 'View Project Details' icon. Complaints open from the 'Complaints / Litigation' icon in the same row. Registration number: PRM/KA/RERA/1251/446/PR/180130/002413.
- RERA record last checked: 14 Oct 2026
- Last change in the record (registration, quarterly filing or complaint): 15 Jul 2026
How this page is made: software builds it from public records (Karnataka RERA filings, OpenStreetMap, the builder’s own website). AI is used only to read filings into fields and to write the plain-English summary and FAQ answers, which are checked against the record. Facts are checked automatically against the RERA filing. Methodology · How we earn · Report an error
More new projects in Old Madras Road
Bhattarahalli, Old Madras RoadUnder constructionRERA registeredBuyers’ group openPride Euphora
by Pride Housing
Price: Price on requestGet brochure & price →
- 2 BHK, 3 BHK, 4 BHK
- 719 – 1,909 sq ft
- Sep 2027
212 homes
Be one of the first 10 buyers in this groupFounding members — it’s free
Join group for Pride Euphora
Medahalli, Old Madras RoadUnder constructionRERA registeredBuyers’ group openOhana
by A One Shelters
Price: Price on requestGet brochure & price →
- 3 BHK, 4 BHK
- 1,101 – 36,597 sq ft
- Jun 2030 (extended)
2 phases on RERA · 336 homes
Be one of the first 10 buyers in this groupFounding members — it’s free
Join group for Ohana
Bhattarahalli, Old Madras RoadArtist’s impressionUnder constructionRERA registeredBuyers’ group openBrigade Lakecrest
by Brigade Enterprises
Price: Price on requestGet brochure & price →
- Studio, 1 BHK, 2 BHK, 3 BHK
- 329 – 1,421 sq ft
- Mar 2030
604 homes
Be one of the first 10 buyers in this groupFounding members — it’s free
Join group for Brigade Lakecrest