Assetz Marq at a glance
- Possession (RERA)Aug 2023 Date passedWas Jul 2027 · Karnataka RERA
- RERA complaints (project)7 complaintsKarnataka RERA · as on 14 Oct 2026
- Approvals filed8 of 9 on RERAKarnataka RERA uploads · 4 Oct 2026
- Nearest metroWhitefield (Kadugodi) · 3.37 kmstraight line · OpenStreetMap, 5 Oct 2026
- Airport driveapprox. 83 min at peak20.53 km straight line · estimate
- Nearest lakeUnnamed lake · 778 mFrom the RERA map point · OpenStreetMap, 5 Oct 2026
Project summary
Assetz Marq is a residential project by Assetz Whitefield Homes Private Limited in Kannamangala, Bengaluru with 2,148 homes, registered with Karnataka RERA. The completion date on RERA is 30 Aug 2023. It is registered in 4 phases.
Facts collected on 14 Oct 2026 from public records — each linked to its source. Free for buyers. If you book through us, the builder pays us a commission.
Assetz Marq buyers’ group: join to ask for a group price
No one has joined yet. Be one of the first 10 buyers in this group — the founding members.
Join free. When enough buyers have joined, our agent partner asks Assetz Whitefield Homes Private Limited for a group price — for example a lower price, an easier payment plan or waived charges. Nothing is promised: you see what the builder offers and book directly with the builder if you want to. Free for buyers. If you book through us, the builder pays us a commission.
- Gathering buyers
- Talking to the builder
- Group offer
- Group site visit
- Booking
0 buyers have joined · 0 committed
Committed buyers have confirmed their budget, home type and timeline with us on a call; builders negotiate with them. Joining is free and never obliges you to buy.
Join the Assetz Marq buyers’ groupHow group buying works
See it for yourself
Visit the site with our team, or get a call to clear your questions. Free, no obligation.
Key facts: home types, towers, land and possession
- Home types
- Studio, 1 BHK, 2 BHK, 3 BHK, +1 more
- Carpet area
- 213 – 1,612 sq ft
- Towers
- 4
- Floors
- 29
- Total homes
- 2,148
- Land
- 16.83 acres
- Possession (extended)
- Aug 2023
- Built (RERA update)
- Not found in public records yet: construction progress
Assetz Marq RERA number and registration details
- RERA number
- PRM/KA/RERA/1251/446/PR/181210/002206
- Registered on
- 10 Dec 2018
- Promised completion
- 31 Jul 2027
- Extended to
- 30 Aug 2023
- RERA status
- New launch
- Homes booked
- Not found in public records yet: homes booked
- Price
- Not found in public records yet: price
- Project type
- Residential
4 RERA registrations (one per phase) are shown together on this page; dates above are the latest across phases.
Phases and RERA numbers
| Phase | RERA number | Promised completion | Homes | Status | Source |
|---|---|---|---|---|---|
| Building 2 - Tower 5 | PRM/KA/RERA/1251/446/PR/181210/002206 | 30 Nov 2022Extended to 30 Aug 2023 | 690 | New launch | Source (rera.karnataka.gov.in) (opens in a new tab) |
| Building 3 - Tower 6 | PRM/KA/RERA/1251/446/PR/201001/003626 | 30 Sep 2024 | 690 | Completed | Source (rera.karnataka.gov.in) (opens in a new tab) |
| Phase 3A | PRM/KA/RERA/1251/446/PR/240122/004654 | 28 Feb 2026 | 384 | Completed | Source (rera.karnataka.gov.in) (opens in a new tab) |
| Phase 3B | PRM/KA/RERA/1251/446/PR/091122/005433 | 31 Jul 2027 | 384 | Completed | Source (rera.karnataka.gov.in) (opens in a new tab) |
Towers and blocks (RERA filing)
| Tower | Phase | Floors | Basements | Homes |
|---|---|---|---|---|
| Tower 5 | Building 2 - Tower 5 | 28 | 1 | 345 |
| Tower 6 | Building 3 - Tower 6 | 28 | 1 | 345 |
| Marq Phase 3A | Phase 3A | 29 | 1 | 384 |
| Marq Phase 3B | Phase 3B | 29 | 1 | 384 |
A dash (—) means the filing did not state that value.
Summary in plain English
Assetz Marq is a residential project by Assetz Whitefield Homes Private Limited in Kannamangala, Bengaluru East. The project has 2,148 homes across 4 registered phases with completion dates ranging from 30 August 2023 to 31 July 2027.
Written by AI from the RERA record above on 5 Oct 2026. Every number in it was checked against that record; if anything differs, the record wins.
Open space, home loans, escrow and other details
- Open space
- Not found in public records yet: open space
- Water and power
- Water source filed with RERA: BoreWell, Local Authority
- Home loans: approved banks
- Not found in public records yet: bank approvals
- Payment plans
- Not found in public records yet: payment plans
- Maintenance
- Not found in public records yet: maintenance
- Car parking
- Not found in public records yet: car parking charge
- Escrow bank (RERA) · Building 2 - Tower 5
- HDFC, Richmond Road
- Escrow bank (RERA) · Building 3 - Tower 6
- HDFC, Richmond Road
- Escrow bank (RERA) · Phase 3A
- HDFC, Richmond Road
- Escrow bank (RERA) · Phase 3B
- HDFC, Richmond Road
Amenities
- Electricity
- CCTV Surveillance
- Club House
- Community Hall
- Outdoor Sports facility
- Indoor Sports facility
- Swimming Pool
- Gym
- Parks
- Power Backup
- Piped Gas
- Water and Sanitation
- Air Conditioning
Amenities and internal works as filed by the promoter with Karnataka RERA; we have not visited the site.
Assetz Marq location and address
- Address
- SyNo: 169/1, 169/2, part of ( 168, 169/1, 169/2, 169/3, 169/4, 167/3, 167/4, 159/1 & 159/2) Kannamangala Village, Whitefield - Hoskote Road Bangalore, Kannamangala Village,Bangalore 560067
- Village (RERA)
- Kannamangala
- Locality
- Old Madras RoadAlso known as OMR, Old Madras Road
- PIN code
- 560047
- City
- Bengaluru
- State
- Karnataka
- Coordinates
- 13.02549, 77.76409
Distances to landmarks
Not found in public records yet: landmarksAbout Old Madras Road
Not found in public records yet: locality factsCommute times to tech parks and the airport
| To | Straight line | Peak-hour drive (estimate) |
|---|---|---|
| ITPL, Whitefield (main gate)Map point on OpenStreetMap (opens in a new tab) | 5.08 km | approx. 21 min |
| Outer Ring Road tech corridor (RMZ Ecospace, Bellandur)Map point on OpenStreetMap (opens in a new tab) | 14.45 km | approx. 59 min |
| Manyata Tech ParkMap point on OpenStreetMap (opens in a new tab) | 15.83 km | approx. 64 min |
| Kempegowda International AirportMap point on OpenStreetMap (opens in a new tab) | 20.53 km | approx. 83 min |
| KSR Bengaluru City railway station (Majestic)Map point on OpenStreetMap (opens in a new tab) | 21.72 km | approx. 88 min |
| Electronic City Phase 1Map point on OpenStreetMap (opens in a new tab) | 22.31 km | approx. 90 min |
How we calculate
Straight line: from the project’s map point on RERA to the destination’s point on OpenStreetMap.
Peak-hour drive is a rough estimate, not a route: straight line × 1.35 for the road network, at 20 km/h. Real times vary a lot with the route and the hour.
Sources:Source (openstreetmap.org) (opens in a new tab)How we calculate this
Schools and hospitals nearby
Within 2 km
- 7Schools and colleges7 schools, 0 colleges, 0 kindergartens
- 2Hospitals and clinics2 hospitals, 0 clinics
Nearest schools and colleges
- Chrysalis High School · 0.18 km
- Narayana e-Techno School · 1.83 km
- National Public School ITPL · 1.86 km
Nearest hospitals and clinics
- Kannamangala Primary Health Center · 0.75 km
- Miracle Hospital · 1.9 km
Places as mapped on OpenStreetMap (amenity=school, college, kindergarten, university; hospital, clinic), counted within 2 km in a straight line of the RERA map point. Volunteers map these, so some places may be missing or closed. Places data © OpenStreetMap contributors, extract of 5 Oct 2026.
Nearest metro station and railway
- Whitefield (Kadugodi) (ವೈಟ್ಫೀಲ್ಡ್ (ಕಾಡುಗೋಡಿ))Open now — nearest operating metro station3.37 km
- Whitefield (ವೈಟ್ಫೀಲ್ಡ್)Nearest railway station3.25 km
Straight-line distances from the RERA map point to the station points mapped on OpenStreetMap; status (open or under construction) as tagged there. Places data © OpenStreetMap contributors, extract of 5 Oct 2026.
Lake and lake-buffer check
The nearest mapped lake is Unnamed lake (mapped on OpenStreetMap), 778 m from the project’s RERA map point.
The site boundary is not published as a shape, so its nearest edge can be closer than this point. Whether any building sits inside a lake buffer can only be checked on the approved plan.
- Unnamed lake (mapped on OpenStreetMap) on OpenStreetMap (opens in a new tab) 778 m
- Kannamangala Lake on OpenStreetMap (opens in a new tab) (ಕನ್ನಮಂಗಲ ಕೆರೆ)1,048 m
- Unnamed lake (mapped on OpenStreetMap) on OpenStreetMap (opens in a new tab) 1,564 m
The buffer rule
Bengaluru’s lake buffer rule has changed over time: the National Green Tribunal ordered a 75 m buffer in May 2016; the Supreme Court set that order aside on 5 March 2019, leaving the 30 m buffer of the Revised Master Plan 2015. Check the current rule and the approved plan before relying on either number.
- LiveLaw: SC sets aside NGT order enlarging buffer zones (2019) (livelaw.in) (opens in a new tab)
- Citizen Matters: Shrinking lake buffers (citizenmatters.in) (opens in a new tab)
Shortest distance from the RERA map point to the mapped water edge (OpenStreetMap water polygons tagged lake or reservoir, or named lake/kere/tank). Mapped shorelines can differ from the revenue-record boundary of a lake. Places data © OpenStreetMap contributors, extract of 5 Oct 2026.
Sources:Source (openstreetmap.org) (opens in a new tab)Source (livelaw.in) (opens in a new tab)Source (citizenmatters.in) (opens in a new tab)How we calculate this
Satellite time-lapse of the site
Satellite photos load when you scroll to them.
Photos from Esri World Imagery Wayback, centred on the project’s map point; dates are the capture dates in Esri’s metadata. Loaded from Esri when you scroll here.
Sources:Source (livingatlas.arcgis.com) (opens in a new tab)
Assetz Marq home types and carpet areas
Floor plans and brochure not published? The builder shares them only on request. We’ll get the brochure, floor plans and current price list for you, free.
Get brochure, floor plans & price| Home type | Carpet area | Homes |
|---|---|---|
| 1 BHK | 550 – 622 sq ft | 6 |
| 3 BHK | 622 – 1,375 sq ft | 1,232 |
| 4 BHK | 1,563 – 1,612 sq ft | 28 |
| Studio | 213 – 242 sq ft | 192 |
| Studio 1 BHK 2 BHK 3 BHK 4 BHK | 1,046 sq ft | 345 |
| Studio 1 BHK 3 BHK 4 BHK | 1,074 sq ft | 384 |
| Studio, 1 BHK, 3 BHK & 4 BHK | 1,073 sq ft | 384 |
| Studio, 1 BHK, 3b-2t, 3b-3t, 4b-4t | 1,046 sq ft | 345 |
Home types, counts and carpet areas as filed with Karnataka RERA (carpet area, not super built-up).
We have not collected floor-plan drawings; the builder’s sales team can share them.
Assetz Marq possession date and construction status
Timeline
- 1 Dec 2018Building 2 - Tower 5: Project start date given to RERA
- 10 Dec 2018Building 2 - Tower 5: Registered with Karnataka RERA
- 1 Oct 2020Building 3 - Tower 6: Registered with Karnataka RERA
- 1 Oct 2020Building 3 - Tower 6: Project start date given to RERA
- 1 Jan 2022Phase 3A: Project start date given to RERA
- 24 Jan 2022Phase 3A: Registered with Karnataka RERA
- 1 Jul 2022Phase 3B: Project start date given to RERA
- 9 Nov 2022Phase 3B: Registered with Karnataka RERA
- 30 Nov 2022Building 2 - Tower 5: Completion date given at registration
- 30 Aug 2023Building 2 - Tower 5: Covid Extension: completion date moved to this date
- 25 Sep 2024Building 3 - Tower 6: Promoter applied to RERA for completion
- 30 Sep 2024Building 3 - Tower 6: Completion date given at registration
- 27 Feb 2026Phase 3A: Promoter applied to RERA for completion
- 28 Feb 2026Phase 3A: Completion date given at registration
- 24 Jul 2026Phase 3B: Promoter applied to RERA for completion
- 31 Jul 2027Phase 3B: Completion date given at registration
Approvals and documents checklist
27 rows: approvals. Scroll inside the table to see them all.
| Approval | Authority | Source |
|---|---|---|
| Building plan (Building 2 - Tower 5) | BDA - Bangalore Development Authority | Source (rera.karnataka.gov.in) (opens in a new tab) |
| Building plan (Building 3 - Tower 6) | BDA - Bangalore Development Authority | Source (rera.karnataka.gov.in) (opens in a new tab) |
| Building plan (Phase 3A) | BDA - Bangalore Development Authority · No. BDA/LP/EM/EO-03/TA-4/E/17/2021-22 · dated 2021-12-06 | Source (rera.karnataka.gov.in) (opens in a new tab) |
| Land conversion (Phase 3A) | KIADB · No. CI 219 SPQ 95 · dated 1995-12-19 | Source (rera.karnataka.gov.in) (opens in a new tab) |
| Commencement Certificate (Phase 3A) | scan uploaded to RERA | Source (rera.karnataka.gov.in) (opens in a new tab) |
| Water Permission Letter (Phase 3A) | scan uploaded to RERA | Source (rera.karnataka.gov.in) (opens in a new tab) |
| Change of Land Use (Phase 3A) | scan uploaded to RERA | Source (rera.karnataka.gov.in) (opens in a new tab) |
| Conversion Certificate under section 95 of the KLR Act 1964 (Phase 3A) | scan uploaded to RERA | Source (rera.karnataka.gov.in) (opens in a new tab) |
| Approval/NOC under section 109 of KLR Act 1961 (Phase 3A) | scan uploaded to RERA | Source (rera.karnataka.gov.in) (opens in a new tab) |
| Approval/NOC under section 14 of the KTCP Act (Phase 3A) | scan uploaded to RERA | Source (rera.karnataka.gov.in) (opens in a new tab) |
| Fire Force Department (Phase 3A) | scan uploaded to RERA | Source (rera.karnataka.gov.in) (opens in a new tab) |
| Airport Authority of India (Phase 3A) | scan uploaded to RERA | Source (rera.karnataka.gov.in) (opens in a new tab) |
| KSPCB (Phase 3A) | scan uploaded to RERA | Source (rera.karnataka.gov.in) (opens in a new tab) |
| Building plan (Phase 3B) | BDA - Bangalore Development Authority · No. BDA/LP/EM/EO-01/TA-04/E/26/2022-23 · dated 2022-10-27 | Source (rera.karnataka.gov.in) (opens in a new tab) |
| Land conversion (Phase 3B) | KIADB · No. CI 219 SPQ 95 · dated 1995-12-19 | Source (rera.karnataka.gov.in) (opens in a new tab) |
| Commencement Certificate (Phase 3B) | scan uploaded to RERA | Source (rera.karnataka.gov.in) (opens in a new tab) |
| Electricity Permission Letter (Phase 3B) | scan uploaded to RERA | Source (rera.karnataka.gov.in) (opens in a new tab) |
| Water Permission Letter (Phase 3B) | scan uploaded to RERA | Source (rera.karnataka.gov.in) (opens in a new tab) |
| Approved Building/Plotting Plan (Phase 3B) | scan uploaded to RERA | Source (rera.karnataka.gov.in) (opens in a new tab) |
| Approved Section Of Building/Infrastructure Plan of Plotting (Phase 3B) | scan uploaded to RERA | Source (rera.karnataka.gov.in) (opens in a new tab) |
| Conversion Certificate under section 95 of the KLR Act 1964 (Phase 3B) | scan uploaded to RERA | Source (rera.karnataka.gov.in) (opens in a new tab) |
| ESCOM/Electricity (Phase 3B) | scan uploaded to RERA | Source (rera.karnataka.gov.in) (opens in a new tab) |
| KWSSB/Water (Phase 3B) | scan uploaded to RERA | Source (rera.karnataka.gov.in) (opens in a new tab) |
| Fire Force Department (Phase 3B) | scan uploaded to RERA | Source (rera.karnataka.gov.in) (opens in a new tab) |
| Airport Authority of India (Phase 3B) | scan uploaded to RERA | Source (rera.karnataka.gov.in) (opens in a new tab) |
| KSPCB (Phase 3B) | scan uploaded to RERA | Source (rera.karnataka.gov.in) (opens in a new tab) |
| SEIAA (Phase 3B) | scan uploaded to RERA | Source (rera.karnataka.gov.in) (opens in a new tab) |
Documents uploaded to RERA (Phase 3B)
- Building or layout plan · Approved drawings from the planning authorityFiled on RERA ✓ — BDA - Bangalore Development Authority · No. BDA/LP/EM/EO-01/TA-04/E/26/2022-23 · dated 27 Oct 2022
- Commencement certificate · Permission to start buildingFiled on RERA ✓ — scanned copy uploaded; number and date not read yet
- Environment clearance · SEIAA KarnatakaFiled on RERA ✓ — scanned copy uploaded; number and date not read yet
- Fire NOC · Karnataka Fire and Emergency ServicesFiled on RERA ✓ — scanned copy uploaded; number and date not read yet
- Pollution board consent · KSPCBFiled on RERA ✓ — scanned copy uploaded; number and date not read yet
- Water and sewerage · BWSSBFiled on RERA ✓ — scanned copy uploaded; number and date not read yet
- Electricity · BESCOMFiled on RERA ✓ — scanned copy uploaded; number and date not read yet
- Height clearance · Airports Authority of IndiaFiled on RERA ✓ — scanned copy uploaded; number and date not read yet
- Occupancy certificate (OC) · Issued only when the building is finishedNot on RERA yet
From the documents the promoter uploaded to Karnataka RERA, collected 4 Oct 2026. “Filed” means a document is on RERA — we have not checked its contents or validity. Not every approval applies to every project (for example, smaller projects may not need an environment clearance). Each phase is registered separately; this list is for the phase named above. The project page on RERA lists each upload.
Assetz Marq RERA complaints and orders
7 complaints as on Source (rera.karnataka.gov.in) (opens in a new tab)
| Complaint ref | Filed | Subject | Status | Source |
|---|---|---|---|---|
| 01141/2025 | 8 Sep 2025 | Illegal encroachment of common area | Disposed | Source (rera.karnataka.gov.in) (opens in a new tab) |
| 01144/2025 | 8 Sep 2025 | Carpark Allotment done not in my building premises | Disposed | Source (rera.karnataka.gov.in) (opens in a new tab) |
| 01101/2025 | 29 Aug 2025 | Structural Defect – Unplastered Exterior Wall | Disposed | Source (rera.karnataka.gov.in) (opens in a new tab) |
| 00710/2025 | 5 May 2025 | Unauthorised construction | Disposed | Source (rera.karnataka.gov.in) (opens in a new tab) |
| 01084/2024 | 7 Nov 2024 | Delay Compensation owing to delay in handing over the amenities that were due along with the Apartment | Disposed | Source (rera.karnataka.gov.in) (opens in a new tab) |
| 01044/2024 | 22 Oct 2024 | Delay Compensation owing to dealy in handing over the amenities that were due along with the Apartment | Disposed | Source (rera.karnataka.gov.in) (opens in a new tab) |
| 00729/2023 | 9 May 2023 | Booking amount is not refunded completely | Disposed | Source (rera.karnataka.gov.in) (opens in a new tab) |
Court and consumer cases
We list case numbers, courts and outcomes only — never names of private individuals.
About Assetz Whitefield Homes Private Limited
- Promoter type
- Company
- Projects on this site
- 1
- RERA complaints against promoter
- 7
- Company number (CIN)
- U70109KA2012PTC063873
From Karnataka RERA, as collected so far (14 Oct 2026). Complaints are those RERA lists against this promoter across all its projects.
Assetz Whitefield Homes Private Limited’s RERA recordAssetz Whitefield Homes Private Limited delivery record
- 1Projects in Bengaluru on RERA4 approved registrations under Assetz Whitefield Homes Private Limited in Bengaluru Urban and Rural. Source (rera.karnataka.gov.in) (opens in a new tab)
- 2,148Homes registeredAs stated in each registrations.
- 7RERA complaints0 open, 7 disposed. as on Source (rera.karnataka.gov.in) (opens in a new tab)
- 3.3Complaints per 1,000 homes7 complaints ÷ 2,148 homes in its 4 registrations on Karnataka RERA in Bengaluru.
- 3Completion filed on RERARegistrations where the promoter applied to RERA for completion; 3 with an occupancy certificate on RERA.
- 3 of 3Filed by the date given at registrationMedian gap 0 months (on-time ones count as 0). The completion application can come after handover, so this is an upper bound on lateness.
What the complaints are about
7 complaint subjects as written on RERA, as on . Each subject is sorted into one group by keywords (first match wins: delay, refund, registration, quality, litigation, association); one complaint often raises several issues. Source (rera.karnataka.gov.in) (opens in a new tab)
Completion filed on RERA
| Project | Date at registration | Completion filed | Gap |
|---|---|---|---|
| Assetz Marq Phase 3BOC on RERA | 31 Jul 2027 | 24 Jul 2026 | By the date |
| Assetz Marq Phase 3AOC on RERA | 28 Feb 2026 | 27 Feb 2026 | By the date |
| Assetz Marq Building 3 - Tower 6OC on RERA | 30 Sep 2024 | 25 Sep 2024 | By the date |
Measured against the completion date given at registration; many projects had RERA extensions (including the COVID-period extension), shown under the date.
Sources:Source (rera.karnataka.gov.in) (opens in a new tab)How we calculate this
What’s changed since Dec 2018
- 24 Jul 2026Phase 3B: Promoter applied to RERA for completion (occupancy certificate on RERA) Source (rera.karnataka.gov.in) (opens in a new tab)
- 15 Apr 2026Phase 3B: Quarterly update filed for Q4 2025-26: 100% built, 383 of 384 homes booked Source (rera.karnataka.gov.in) (opens in a new tab)
- 11 Mar 2026Phase 3B: Quarterly update filed for Q3 2025-26: 94% built, 383 of 384 homes booked Source (rera.karnataka.gov.in) (opens in a new tab)
- 27 Feb 2026Phase 3A: Promoter applied to RERA for completion (occupancy certificate on RERA) Source (rera.karnataka.gov.in) (opens in a new tab)
- 25 Feb 2026Phase 3A: Quarterly update filed for Q3 2025-26: 100% built, 384 of 384 homes booked Source (rera.karnataka.gov.in) (opens in a new tab)
- 8 Sep 2025Complaint 01141/2025 filed with RERA: “Illegal encroachment of common area” — now disposed Source (rera.karnataka.gov.in) (opens in a new tab)
- 8 Sep 2025Complaint 01144/2025 filed with RERA: “Carpark Allotment done not in my building premises” — now disposed Source (rera.karnataka.gov.in) (opens in a new tab)
- 29 Aug 2025Complaint 01101/2025 filed with RERA: “Structural Defect – Unplastered Exterior Wall” — now disposed Source (rera.karnataka.gov.in) (opens in a new tab)
- 5 May 2025Complaint 00710/2025 filed with RERA: “Unauthorised construction” — now disposed Source (rera.karnataka.gov.in) (opens in a new tab)
- 7 Nov 2024Complaint 01084/2024 filed with RERA: “Delay Compensation owing to delay in handing over the amenities that were due along with the Apartment” — now disposed Source (rera.karnataka.gov.in) (opens in a new tab)
- 22 Oct 2024Complaint 01044/2024 filed with RERA: “Delay Compensation owing to dealy in handing over the amenities that were due along with the Apartment” — now disposed Source (rera.karnataka.gov.in) (opens in a new tab)
- 25 Sep 2024Building 3 - Tower 6: Promoter applied to RERA for completion (occupancy certificate on RERA) Source (rera.karnataka.gov.in) (opens in a new tab)
- 30 Aug 2023Building 2 - Tower 5: Completion date extended to 30 Aug 2023 Source (rera.karnataka.gov.in) (opens in a new tab)
- 9 May 2023Complaint 00729/2023 filed with RERA: “Booking amount is not refunded completely” — now disposed Source (rera.karnataka.gov.in) (opens in a new tab)
- 9 Nov 2022Phase 3B: Registered with Karnataka RERA (PRM/KA/RERA/1251/446/PR/091122/005433); completion date 31 Jul 2027 Source (rera.karnataka.gov.in) (opens in a new tab)
- 27 Oct 2022Phase 3B: Building plan approved by BDA - Bangalore Development Authority (No. BDA/LP/EM/EO-01/TA-04/E/26/2022-23) Source (rera.karnataka.gov.in) (opens in a new tab)
- 1 Jul 2022Phase 3B: Project start date in the RERA record Source (rera.karnataka.gov.in) (opens in a new tab)
- 24 Jan 2022Phase 3A: Registered with Karnataka RERA (PRM/KA/RERA/1251/446/PR/240122/004654); completion date 28 Feb 2026 Source (rera.karnataka.gov.in) (opens in a new tab)
- 1 Jan 2022Phase 3A: Project start date in the RERA record Source (rera.karnataka.gov.in) (opens in a new tab)
- 6 Dec 2021Phase 3A: Building plan approved by BDA - Bangalore Development Authority (No. BDA/LP/EM/EO-03/TA-4/E/17/2021-22) Source (rera.karnataka.gov.in) (opens in a new tab)
- 1 Oct 2020Building 3 - Tower 6: Registered with Karnataka RERA (PRM/KA/RERA/1251/446/PR/201001/003626); completion date 30 Sep 2024 Source (rera.karnataka.gov.in) (opens in a new tab)
- 1 Oct 2020Building 3 - Tower 6: Project start date in the RERA record Source (rera.karnataka.gov.in) (opens in a new tab)
- 10 Dec 2018Building 2 - Tower 5: Registered with Karnataka RERA (PRM/KA/RERA/1251/446/PR/181210/002206); completion date 30 Nov 2022 Source (rera.karnataka.gov.in) (opens in a new tab)
- 1 Dec 2018Building 2 - Tower 5: Project start date in the RERA record Source (rera.karnataka.gov.in) (opens in a new tab)
Newest first. When the RERA crawl sees a new filing, complaint or extension, it is added here with its date.
Home loan EMI calculator
- Monthly EMI
- —
- Down payment
- —
- Loan amount
- —
- Total interest
- —
A calculation only, from the numbers you enter — not a loan offer.
All-in cost: GST, registration and other charges
The calculator loads when you scroll to it.
Assumptions
- Base price: the builder’s price is not published in a form we could collect — enter it from the cost sheet.
- GST 5% on the base price and charges — the usual rate for an under-construction home that is not “affordable housing” (1%).
- Stamp duty about 5.6% and registration 2% — the Karnataka rule (registration was raised from 1% to 2% on 31 Aug 2025). Calculated on the agreement value.
- Car parking, other charges and the maintenance deposit are not in the public record we collect; enter them from the builder’s cost sheet.
- Loan on the agreement value (banks usually lend up to 75–90%); EMI is the standard reducing-balance formula. Example rate only — use your bank’s quote.
Assetz Marq FAQs
What is Assetz Marq and where is it located?
Assetz Marq is a residential project by Assetz Whitefield Homes Private Limited in Kannamangala, Bengaluru East, PIN code 560047, registered on Karnataka RERA.
How many homes are in Assetz Marq?
The project has 2,148 homes across 4 phases.
What home types and carpet areas are available in Assetz Marq?
The project offers Studio, 1 BHK, 2 BHK, 3 BHK, and 4 BHK homes. Carpet areas range from 213 sq ft (Studio) to 1,612 sq ft (4 BHK) across different phases.
When will Assetz Marq be completed?
Building 2 - Tower 5 completion date is 30 August 2023, Building 3 - Tower 6 is 30 September 2024, Phase 3A is 28 February 2026, and Phase 3B is 31 July 2027.
What are the RERA registration numbers for Assetz Marq phases?
The phases are registered as PRM/KA/RERA/1251/446/PR/181210/002206, PRM/KA/RERA/1251/446/PR/201001/003626, PRM/KA/RERA/1251/446/PR/240122/004654, and PRM/KA/RERA/1251/446/PR/091122/005433.
What is the construction status of Assetz Marq?
Phase 3A and Phase 3B are 100% complete as of their latest quarterly updates. Building 3 - Tower 6 has an occupancy certificate uploaded.
How many homes are booked in Assetz Marq?
In Phase 3A, 384 homes are booked. In Phase 3B, 383 homes are booked.
How many RERA complaints are filed on Assetz Marq?
There are 7 complaints on the project: 4 on Building 2 - Tower 5, 2 on Building 3 - Tower 6, 0 on Phase 3A, and 1 on Phase 3B.
What is Assetz Whitefield Homes Private Limited's record on RERA?
The builder has 1 project in the Karnataka RERA records and 7 complaints across all their projects.
Which bank holds escrow for Assetz Marq?
HDFC is the escrow bank for all 4 phases of Assetz Marq.
Written by AI from the RERA record above on 5 Oct 2026. Answers use only that record; check them against the source before you decide.
Questions about Assetz Marq
No questions published yet. Ask the first one: you get an instant answer from this page’s public record, and our team follows up on anything the record does not show.
Bought a home from Assetz Whitefield Homes Private Limited? Review the builder.
Reviews of Assetz Whitefield Homes Private Limited by verified buyers
No verified reviews of Assetz Whitefield Homes Private Limited yet. If you bought a home from them, your review helps other buyers.
How reviews work: only buyers and owners can review; we confirm each purchase by phone before publishing, publish positive and negative reviews alike, never accept payment for reviews, and the builder may reply.
Similar projects within 5 km
| Project | Distance | Homes | Possession (RERA) | Built | Complaints | Price |
|---|---|---|---|---|---|---|
| Royal ViewGreen Edge Developers | 0.5 km | 237 | Dec 2026 | — | 0 | Not collected |
| NirvanaM/s Virtue Infracon | 0.5 km | 40 | Mar 2026 | 100% | 0 | Not collected |
| Ruchira Park EastRuchira Developers LLP | 0.7 km | 284 | Jan 2027 | 69% | 0 | Not collected |
| Platinum East WoodsPlatinum - Narya Infra | 0.8 km | 188 | Mar 2027 | 62% | 0 | Not collected |
| Pavani MirabiliaSai Sravanthi Infra Projects Pvt Ltd | 0.9 km | 1,624 | Mar 2031extended | — | 3 | Not collected |
| ELV High GardenELV Projects Private Limited | 1 km | 219 | Oct 2027extended | 30% | 7 | Not collected |
Projects of the same kind within 5 km in a straight line of this project’s RERA map point, nearest first. % built is the promoter’s latest quarterly figure on RERA (shown for single-registration projects); prices are from the builder’s own website where we found one.
Sources and last checked dates
Collected on 14 Oct 2026 by AI research agents reading public pages. Facts are written in our own words. Not found yet: price; court cases; landmarks; specifications; news.
How to check on RERA: On rera.karnataka.gov.in/viewAllProjects, type the registration number in 'Registration No', press Search, then click the 'View Project Details' icon. Complaints open from the 'Complaints / Litigation' icon in the same row. Registration numbers: PRM/KA/RERA/1251/446/PR/181210/002206, PRM/KA/RERA/1251/446/PR/201001/003626, PRM/KA/RERA/1251/446/PR/240122/004654, PRM/KA/RERA/1251/446/PR/091122/005433.
- RERA record last checked: 14 Oct 2026
- Last change in the record (registration, quarterly filing or complaint): 15 Apr 2026
How this page is made: software builds it from public records (Karnataka RERA filings, OpenStreetMap, the builder’s own website). AI is used only to read filings into fields and to write the plain-English summary and FAQ answers, which are checked against the record. Facts are checked automatically against the RERA filing. Methodology · How we earn · Report an error
More new projects in Old Madras Road
- Kannamangala, Old Madras Road© Esri, Maxar, Earthstar GeographicsUnder constructionRERA registeredBuyers’ group open
Royal View
by Green Edge
Price: Price on requestGet brochure & price →
- 2 BHK, 3 BHK, 4 BHK
- 977 – 2,708 sq ft
- Dec 2026
237 homes
Be one of the first 10 buyers in this groupFounding members — it’s free
Join group for Royal View
Kannamangala, Old Madras RoadReady to moveRERA registeredBuyers’ group openNirvana
by M/s Virtue Infracon
Price: Price on requestGet brochure & price →
- 2 BHK, 3 BHK
- 746 – 1,095 sq ft
- Mar 2026
40 homes
Be one of the first 10 buyers in this groupFounding members — it’s free
Join group for Nirvana
Kannamangala, Old Madras RoadUnder constructionRERA registeredBuyers’ group openRuchira Park East
by Ruchira
Price: Price on requestGet brochure & price →
- 2 BHK, 3 BHK, 3.5 BHK
- 878 – 1,511 sq ft
- Jan 2027
284 homes
Be one of the first 10 buyers in this groupFounding members — it’s free
Join group for Ruchira Park East